Sec. 3. (a) To determine the amount of retainage to be withheld, the division shall elect one (1) of the following options:

(1) To withhold no more than six percent (6%) of the dollar value of all work satisfactorily completed until the public work is fifty percent (50%) complete, and nothing further after that.

(2) To withhold no more than three percent (3%) of the dollar value of all work satisfactorily completed until the public work is substantially complete.

(b) Upon substantial completion of the work, the division shall withhold the following:

(1) If there are any remaining uncompleted minor items, until those items are completed, an amount equal to two hundred percent (200%) of the value of each item as determined by the architect-engineer.

(2) Any amounts required to be withheld under section 8(b) of this chapter.

As added by P.L.24-1985, SEC.7. Amended by P.L.75-2012, SEC.1.

Disclaimer: These codes may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.