2019 Indiana Code
Title 36. Local Government
Article 10. Recreation, Culture, and Community Facilities
Chapter 9. Marion County Capital Improvement Board
36-10-9-6.5. Prohibition on certain contract limitations for a project

Universal Citation: IN Code § 36-10-9-6.5 (2019)
IC 36-10-9-6.5 Prohibition on certain contract limitations for a project

Sec. 6.5. (a) The following definitions apply throughout this section:

(1) "Contract" includes a lease or other agreement.

(2) "Contract limitation" refers to a bid specification, project agreement, lease provision, or other contract document that does any of the following:

(A) Requires a bidder, offeror, or contractor in any contractor tier to enter into or adhere to an agreement with a labor organization relating to a project.

(B) Prohibits a bidder, offeror, or contractor in any contractor tier from entering into or adhering to an agreement with a labor organization relating to a project.

(C) Discriminates against a bidder, offeror, or contractor in any contractor tier for any of the following:

(i) Becoming or remaining a signatory to an agreement with a labor organization relating to a project.

(ii) Refusing to become or remain a signatory to an agreement with a labor organization relating to a project.

(iii) Adhering or refusing to adhere to an agreement with a labor organization relating to a project.

(3) "Project" refers to a project of the board for the construction or lease of a facility and all buildings, facilities, structures, and improvements related to that facility to be financed in whole or in part from funds derived from the establishment of a tax area under IC 36-7-31.5.

(4) "Public benefit" refers to a grant, a tax abatement, a tax credit, or establishment or use of tax area revenues related to a project.

(b) A contract under this chapter or another law relating to a project may not require a contractor or subcontractor to enter into a contract limitation as a condition of being awarded and performing work on the contract. Any such provision is void.

(c) A public entity may not award a public benefit that is conditioned upon a requirement that the person awarded the public benefit include a contract limitation in a contract document related to a project. Any such provision is void.

As added by P.L.109-2019, SEC.19.

Disclaimer: These codes may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.