IC 4-13.6-7-8 Final settlement with contractor

     Sec. 8. (a) Except for amounts withheld:

(1) from the contractor under section 3 of this chapter for uncompleted minor items; and

(2) under subsection (b);

the division may make a full, final, and complete settlement with a contractor, including providing for full payment of all escrowed principal and escrowed income, not later than sixty-one (61) days following the date of substantial completion if the contractor has materially fulfilled all of its obligations under the public works contract.

     (b) If the division receives a claim from a subcontractor or a supplier under section 9 of this chapter, the division shall withhold the amount of the claim until the claim is resolved under section 9(c) of this chapter.

     (c) After the division makes a final settlement with a contractor, all claims by subcontractors and suppliers to funds withheld from that contractor under section 2 of this chapter are barred.

As added by P.L.24-1985, SEC.7. Amended by P.L.75-2012, SEC.2.

 

Disclaimer: These codes may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.