2006 Indiana Code - CHAPTER 4. SCHEDULES FOR DETERMINATIONS ON PERMITS
IC 13-15-4Chapter 4. Schedules for Determinations on Permits
IC 13-15-4-1
Deadlines for acting on applications; renewals
Sec. 1. (a) Except as provided in sections 2, 3, and 6 of this
chapter, the commissioner shall approve or deny an application filed
with the department after July 1, 1995, within the following number
of days:
(1) Three hundred sixty-five (365) days for an application
concerning the following:
(A) A new hazardous waste or solid waste landfill.
(B) A new hazardous waste or solid waste incinerator.
(C) A major modification of a solid waste landfill.
(D) A major modification of a solid waste incinerator.
(E) A new hazardous waste treatment or storage facility.
(F) A new Part B permit issued under 40 CFR 270 et seq. for
an existing hazardous waste treatment or storage facility.
(G) A Class 3 modification under 40 CFR 270.42 to a
hazardous waste landfill.
(2) Two hundred seventy (270) days for an application
concerning the following:
(A) A Class 3 modification under 40 CFR 270.42 of a
hazardous waste treatment or storage facility.
(B) A major new National Pollutant Discharge Elimination
System permit.
(3) One hundred eighty (180) days for an application
concerning the following:
(A) A new solid waste processing or recycling facility.
(B) A minor new National Pollutant Discharge Elimination
System individual permit.
(C) A permit concerning the land application of wastewater.
(4) One hundred fifty (150) days for an application concerning
a minor new National Pollutant Discharge Elimination System
general permit.
(5) One hundred twenty (120) days for an application
concerning a Class 2 modification under 40 CFR 270.42 to a
hazardous waste facility.
(6) Ninety (90) days for an application concerning the
following:
(A) A minor modification to a solid waste landfill or
incinerator permit.
(B) A wastewater facility or water facility construction
permit.
(7) The amount of time provided for in rules adopted by the air
pollution control board for an application concerning the
following:
(A) An air pollution construction permit that is subject to
326 IAC 2-2 and 326 IAC 2-3.
(B) An air pollution facility construction permit (other than
as defined in 326 IAC 2-2).
(C) Registration of an air pollution facility.
(8) Sixty (60) days for an application concerning the following:
(A) A Class 1 modification under 40 CFR 270.42 requiring
prior written approval, to a hazardous waste:
(i) landfill;
(ii) incinerator;
(iii) treatment facility; or
(iv) storage facility.
(B) Any other permit not specifically described in this
section for which the application fee exceeds forty-nine
dollars ($49) and for which a time frame has not been
established under section 3 of this chapter.
(b) When a person holding a valid permit concerning an activity
of a continuing nature has made a timely and sufficient application
for a renewal permit under the rules of one (1) of the boards, the
commissioner shall approve or deny the application on or before the
expiration date stated in the permit for which renewal is sought.
As added by P.L.1-1996, SEC.5. Amended by P.L.224-1999, SEC.4;
P.L.138-2000, SEC.5; P.L.240-2003, SEC.9.
Disclaimer: These codes may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.