(2) Upon notification by the director, the chairman shall immediately notify the representatives of the state to the panel and the public members. The chairman shall also notify the applicable county and city for their appointment of members as provided in subsection (2) of section 39-7408B, Idaho Code. Within thirty (30) days after the notification, the board of commissioners of the county and the city council shall select the members to serve on the panel. The panel shall be created at that time and notification of the creation of the panel shall be made to the chairman.
(3) Within thirty (30) days after appointment of panel members, the panel shall meet to review and establish a timetable for the consideration of the draft site license.
(4) The panel shall:
(5) Comment and input on the proposed commercial solid waste facility may be presented orally or in writing at the public hearing, and shall continue to be accepted in writing by the panel for thirty (30) days after the public hearing date. The public hearing shall be held in the same county as the proposed site. If the proposed site is adjacent to a city or populated area in a neighboring county, it is recommended that public hearings also be held in the neighboring county.
(6) The panel shall consider, but not be limited to, the following:
(7) The panel shall consider the concerns and objections submitted by the public. The panel shall facilitate efforts to provide that the concerns and objections are mitigated by proposing additional conditions regarding the construction of the commercial solid waste facility. The panel may propose conditions which integrate the provisions of the city or county ordinances, permits or requirements.
(8) Within one hundred eighty (180) days after creation, the panel shall recommend to the director that the license be issued, issued with conditions, or rejected. The director shall act on a license application within sixty (60) days after receipt of the panel's recommendation. If the panel recommends conditions, a clear statement of the need for a condition must be submitted to the director. If the panel recommends rejection, a clear statement of the reasons for the denial must be submitted to the director.
(9) The director shall issue, issue with conditions or reject a siting license only as recommended by the siting panel. The director may reconvene a siting panel and request reconsideration of its original recommendation prior to the director's final action.
(10) An applicant or any person aggrieved by a decision of the director pursuant to this chapter may within sixty (60) days of the director's decision, and, after all remedies have been exhausted under the provisions of this chapter, seek judicial review under the procedures provided in chapter 52, title 67, Idaho Code, and may also seek de novo judicial review.
History:
[39-7408D, added 1996, ch. 419, sec. 2, p. 1396; am. 2000, ch. 469, sec. 102, p. 1555.]
Disclaimer: These codes may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.