45-507. Claim of lien. (1) Any person claiming a lien pursuant to the provisions of this chapter must file a claim for record with the county recorder for the county in which such property or some part thereof is situated.

(2) The claim shall be filed within ninety (90) days after the completion of the labor or services, or furnishing of materials.

(3) The claim shall contain:

(a) A statement of his demand, after deducting all just credits and offsets;

(b) The name of the owner, or reputed owner, if known;

(c) The name of the person by whom he was employed or to whom he furnished the materials; and

(d) A description of the property to be charged with the lien, sufficient for identification.

(4) Such claim must be verified by the oath of the claimant, his agent or attorney, to the effect that the affiant believes the same to be just.

(5) A true and correct copy of the claim of lien shall be served on the owner or reputed owner of the property either by delivering a copy thereof to the owner or reputed owner personally or by mailing a copy thereof by certified mail to the owner or reputed owner at his last known address. Such delivery or mailing shall be made no later than five (5) business days following the filing of said claim of lien.

Disclaimer: These codes may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.