2005 Idaho Code - 42-403 — PROOF OF COMPLETION OF WORKS

                                  TITLE  42
                       IRRIGATION AND DRAINAGE -- WATER
                            RIGHTS AND RECLAMATION
                                  CHAPTER 4
                     APPROPRIATIONS FOR USE OUTSIDE STATE
    42-403.  PROOF OF COMPLETION OF WORKS. Proof of completion of works under
such permit shall be made in accordance with the laws of the state of Idaho
relative to proof of completion under a permit to appropriate the public
waters of the state of Idaho, as to all works of diversion under such permit:
provided, that the department of water resources may as a condition to the
issuance of a certificate of completion under such proof require from the
officer or official mentioned in section 42-401 a certificate to the effect
that the proper public records of such sister state show the works to have
been completed under said permit, said certificate to show in second feet the
capacities of the various conduits constructed and to show in acre feet the
capacities of reservoir, if any there be, constructed in such sister state
under said permit.

Disclaimer: These codes may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.