103D-326 Fiscal responsibility.

HI Rev Stat § 103D-326 (2015) What's This?

[§103D-326] Fiscal responsibility. Every contract modification, change order, or contract price adjustment under a contract shall be subject to prior written certification by the appropriate fiscal officer for funding the project or the contract, as to the effect of the contract modification, change order, or adjustment in contract price on the total project budget or the total contract budget. In the event that the certification of the fiscal officer discloses a resulting increase in the total project budget or the total contract budget, the procurement officer shall not execute or make such contract modification, change order, or adjustment in contract price unless sufficient funds are available therefor, or the scope of the project or contract is adjusted so as to permit the degree of completion that is feasible within the total project budget or total contract budget as it existed prior to the contract modification, change order, or adjustment in contract price under consideration; provided, that with respect to the validity, as to the contractor, of any executed contract modification, change order, or adjustment in contract price which the contractor has reasonably relied upon, it shall be presumed that there has been compliance with this section. [L Sp 1993, c 8, pt of §2]

Disclaimer: These codes may not be the most recent version. Hawaii may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.