§672E-9 - Additional construction defects.

     [§672E-9]  Additional construction defects.  A construction defect discovered after the notice of claim is served may not be alleged in an action until the claimant has given the contractor:

     (1)  A written notice of claim regarding the alleged defect under section 672E-3; and

     (2)  An opportunity to repair the construction defect or reject the notice of claim under section 672E-4. [L 2004, c 119, pt of §2]

 

Disclaimer: These codes may not be the most recent version. Hawaii may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.