§ 44-14-367. Notice; required statement

Universal Citation: GA Code § 44-14-367 (2019)

Failure of a lien claimant to commence a lien action to collect the amount of his or her claim within 365 days from the date of filing the lien, or failure of the lien claimant to file the statutory notice of commencement of lien action in the county where the property is located, renders the claim of lien unenforceable. A claim of lien may be disregarded if no notice of commencement of lien action was filed within 395 days from the date the claim of lien was filed. Any lien filed after March 31, 2009, shall include on the face of the lien the following statement in at least 12 point bold font: "This claim of lien expires and is void 395 days from the date of filing of the claim of lien if no notice of commencement of lien action is filed in that time period." Failure to include such language shall invalidate the lien and prevent it from being filed. No release or voiding of such liens shall be required. A lien shall expire sooner and be disregarded once it is determined that no notice of commencement was timely filed in response to a notice of contest pursuant to Code Section 44-14-368.

History:

Code 1981, § 44-14-367, enacted by Ga. L. 1998, p. 860, § 2; Ga. L. 2000, p. 1589, § 3; Ga. L. 2008, p. 1063, § 6/SB 374.

Disclaimer: These codes may not be the most recent version. Georgia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.