2017 Georgia Code
Title 44 - Property
Chapter 14 - Mortgages, Conveyances to Secure Debt, and Liens
Article 8 - Liens
Part 3 - Mechanics and Materialmen
§ 44-14-366. Waiver of lien or claim upon bond in advance of furnishing labor, services, or materials void; interim waiver and release upon payment; unconditional waiver and release upon final payment; affidavit of nonpayment

Universal Citation: GA Code § 44-14-366 (2017)
  • (a) A right to claim a lien or to claim upon a bond may not be waived in advance of furnishing of labor, services, or materials. Any purported waiver or release of lien or bond claim or of this Code section executed or made in advance of furnishing of labor, services, or materials is null, void, and unenforceable.
  • (b) No oral or written statement by the claimant purporting to waive, release, impair, or otherwise adversely affect a lien or bond claim is enforceable or creates an estoppel or impairment of claim of lien or claim upon a bond unless:
    • (1) It is pursuant to a waiver and release form duly executed by claimant prescribed below; and
    • (2) The claimant has received payment for the claim as set forth in subsection (f) of this Code section.
  • (c) When a claimant is requested to execute a waiver and release in exchange for or in order to induce payment other than final payment, the waiver and release shall substantially follow the following form, in boldface capital letters in at least 12 point font and the priority of such claimant's lien rights, except as to retention, shall upon such payment thereafter run from the day after the date specified in such Interim Waiver and Release upon Payment form:

    "INTERIM WAIVER AND RELEASE

    UPON PAYMENT

    STATE OF GEORGIA

    COUNTY OF ____

    THE UNDERSIGNED MECHANIC AND/OR MATERIALMAN HAS BEEN EMPLOYED BY

    ____ (NAME OF CONTRACTOR) TO FURNISH ____ (DESCRIBE

    MATERIALS AND/OR LABOR) FOR THE CONSTRUCTION OF IMPROVEMENTS KNOWN AS

    ____ (TITLE OF THE PROJECT OR BUILDING) WHICH IS LOCATED IN THE

    CITY OF ____, COUNTY OF ____, AND IS OWNED BY ____

    (NAME OF OWNER) AND MORE PARTICULARLY DESCRIBED AS FOLLOWS:

    ____

    ____

    ____

    (DESCRIBE THE PROPERTY UPON WHICH THE IMPROVEMENTS WERE MADE BY USING

    EITHER A METES AND BOUNDS DESCRIPTION, THE LAND LOT DISTRICT, BLOCK AND

    LOT NUMBER, OR STREET ADDRESS OF THE PROJECT.)

    UPON THE RECEIPT OF THE SUM OF $____, THE MECHANIC AND/OR MATERIALMAN

    WAIVES AND RELEASES ANY AND ALL LIENS OR CLAIMS OF LIENS IT HAS UPON THE

    FOREGOING DESCRIBED PROPERTY OR ANY RIGHTS AGAINST ANY LABOR AND/OR

    MATERIAL BOND THROUGH THE DATE OF ____ (DATE) AND EXCEPTING THOSE RIGHTS

    AND LIENS THAT THE MECHANIC AND/OR MATERIALMAN MIGHT HAVE IN ANY RETAINED

    AMOUNTS, ON ACCOUNT OF LABOR OR MATERIALS, OR BOTH, FURNISHED BY THE

    UNDERSIGNED TO OR ON ACCOUNT OF SAID CONTRACTOR FOR SAID BUILDING OR

    PREMISES.

    GIVEN UNDER HAND AND SEAL THIS ____ DAY OF ____, ____.

    ____(SEAL)

    ____

    ____

    (WITNESS)

    ____

    (ADDRESS)

    NOTICE: WHEN YOU EXECUTE AND SUBMIT THIS DOCUMENT, YOU SHALL BE

    CONCLUSIVELY DEEMED TO HAVE BEEN PAID IN FULL THE AMOUNT STATED ABOVE, EVEN

    IF YOU HAVE NOT ACTUALLY RECEIVED SUCH PAYMENT, 60 DAYS AFTER THE DATE

    STATED ABOVE UNLESS YOU FILE EITHER AN AFFIDAVIT OF NONPAYMENT OR A CLAIM

    OF LIEN PRIOR TO THE EXPIRATION OF SUCH 60 DAY PERIOD. THE FAILURE TO

    INCLUDE THIS NOTICE LANGUAGE ON THE FACE OF THE FORM SHALL RENDER THE FORM

    UNENFORCEABLE AND INVALID AS A WAIVER AND RELEASE UNDER O.C.G.A. SECTION

    44-14-366."

    Provided, however, that the failure to correctly complete any of the blank

    spaces in the above form shall not invalidate said form so long as the subject

    matter of said release may reasonably be determined.

  • (d) When a claimant is requested to execute a waiver and release in

    exchange for or in order to induce making of final payment, the waiver and

    release shall substantially follow the following form in boldface capital

    letters in at least 12 point font:

    "WAIVER AND RELEASE

    UPON FINAL PAYMENT

    STATE OF GEORGIA

    COUNTY OF ____

    THE UNDERSIGNED MECHANIC AND/OR MATERIALMAN HAS BEEN EMPLOYED BY

    ____ (NAME OF CONTRACTOR) TO FURNISH ____ (DESCRIBE

    MATERIALS AND/OR LABOR) FOR THE CONSTRUCTION OF IMPROVEMENTS KNOWN AS

    ____ (TITLE OF THE PROJECT OR BUILDING) WHICH IS LOCATED IN THE

    CITY OF ____, COUNTY OF ____, AND IS OWNED BY ____

    (NAME OF OWNER) AND MORE PARTICULARLY DESCRIBED AS FOLLOWS:

    ____

    ____

    ____

    (DESCRIBE THE PROPERTY UPON WHICH THE IMPROVEMENTS WERE MADE BY USING

    EITHER A METES AND BOUNDS DESCRIPTION, THE LAND LOT DISTRICT, BLOCK AND

    LOT NUMBER, OR STREET ADDRESS OF THE PROJECT.)

    UPON THE RECEIPT OF THE SUM OF $ ____, THE MECHANIC AND/OR MATERIALMAN

    WAIVES AND RELEASES ANY AND ALL LIENS OR CLAIMS OF LIENS IT HAS UPON THE

    FOREGOING DESCRIBED PROPERTY OR ANY RIGHTS AGAINST ANY LABOR AND/OR

    MATERIAL BOND ON ACCOUNT OF LABOR OR MATERIALS, OR BOTH, FURNISHED BY THE

    UNDERSIGNED TO OR ON ACCOUNT OF SAID CONTRACTOR FOR SAID PROPERTY.

    GIVEN UNDER HAND AND SEAL THIS ____ DAY OF ____, ____.

    ____(SEAL)

    ____

    ____

    (WITNESS)

    ____

    (ADDRESS)

    NOTICE: WHEN YOU EXECUTE AND SUBMIT THIS DOCUMENT, YOU SHALL BE

    CONCLUSIVELY DEEMED TO HAVE BEEN PAID IN FULL THE AMOUNT STATED ABOVE, EVEN

    IF YOU HAVE NOT ACTUALLY RECEIVED SUCH PAYMENT, 60 DAYS AFTER THE DATE

    STATED ABOVE UNLESS YOU FILE EITHER AN AFFIDAVIT OF NONPAYMENT OR A CLAIM

    OF LIEN PRIOR TO THE EXPIRATION OF SUCH 60 DAY PERIOD. THE FAILURE TO

    INCLUDE THIS NOTICE LANGUAGE ON THE FACE OF THE FORM SHALL RENDER THE FORM

    UNENFORCEABLE AND INVALID AS A WAIVER AND RELEASE UNDER O.C.G.A. SECTION

    44-14-366."

    Provided, however, that the failure to correctly complete any of the blank

    spaces in the above form shall not invalidate said form so long as the subject

    matter of said release may reasonably be determined.

  • (e) Nothing contained in this Code section shall affect:
    • (1) The enforceability of any subordination of lien rights by a

      potential lien claimant to the rights of any other party which may have or

      acquire an interest in all or any part of the real estate, factories,

      railroads, or other property for which the potential lien claimant has

      furnished labor, services, or material, even though such subordination is

      entered into in advance of furnishing labor, services, or material and even

      though the claimant has not actually received payment in full for its claim;

    • (2) The enforceability of any waiver of lien rights given in connection

      with the settlement of a bona fide dispute concerning the amount due the lien

      claimant for labor, services, or material which have already been furnished;

    • (3) The validity of a cancellation or release of a recorded claim of

      lien or preliminary notice of lien rights; or

    • (4) The provisions of paragraph (2) of subsection (a) of Code Section

      44-14-361.2, paragraphs (3) and (4) of subsection (a) and subsections (b) and

      (c) of Code Section 44-14-361.4, or Code Section 44-14-364.

  • (f) (1) When a waiver and release provided for in this Code section is

    executed by the claimant, it shall be binding against the claimant for all

    purposes, subject only to payment in full of the amount set forth in the

    waiver and release.

    • (2) Such amounts shall conclusively be deemed paid in full upon the

      earliest to occur of:

      • (A) Actual receipt of funds;
      • (B) Execution by the claimant of a separate written acknowledgment of

        payment in full; or

      • (C) Sixty days after the date of the execution of the waiver and

        release, unless prior to the expiration of said 60 day period the claimant

        files a claim of lien or files in the county in which the property is located

        an affidavit of nonpayment, using substantially the following form in boldface

        capital letters in at least 12 point font:

        "AFFIDAVIT OF NONPAYMENT UNDER

        O.C.G.A. SECTION 44-14-366

        STATE OF GEORGIA

        COUNTY OF ____

        THE UNDERSIGNED MECHANIC AND/OR MATERIALMAN HAS BEEN EMPLOYED BY

        ____ (NAME OF CONTRACTOR) TO FURNISH ____

        (DESCRIBE MATERIALS AND/OR LABOR) FOR THE CONSTRUCTION OF

        IMPROVEMENTS KNOWN AS ____ (TITLE OF THE PROJECT OR

        BUILDING) WHICH IS LOCATED IN THE CITY OF ____, COUNTY OF

        ____, AND IS OWNED BY ____ (NAME OF OWNER) AND MORE

        PARTICULARLY DESCRIBED AS FOLLOWS:

        ____

        ____

        ____

        (DESCRIBE THE PROPERTY UPON WHICH THE IMPROVEMENTS WERE MADE BY

        USING EITHER A METES AND BOUNDS DESCRIPTION, THE LAND LOT

        DISTRICT, BLOCK AND LOT NUMBER, OR STREET ADDRESS OF THE PROJECT.)

        PURSUANT TO O.C.G.A. SECTION 44-14-366 THE UNDERSIGNED EXECUTED A

        LIEN WAIVER AND RELEASE WITH RESPECT TO THIS PROPERTY DATED

        ____, ____. THE AMOUNT SET FORTH IN SAID WAIVER AND RELEASE

        ($____) HAS NOT BEEN PAID, AND THE UNDERSIGNED HEREBY GIVES NOTICE

        OF SUCH NONPAYMENT.

        THE ABOVE FACTS ARE SWORN TRUE AND CORRECT BY THE UNDERSIGNED, THIS

        ____ DAY OF ____, ____.

        ____(SEAL)

        CLAIMANT'S SIGNATURE

        SWORN TO AND EXECUTED

        IN THE PRESENCE OF:

        ____

        WITNESS

        ____

        NOTARY PUBLIC

        WITHIN SEVEN DAYS OF FILING THIS AFFIDAVIT OF NONPAYMENT, THE FILING

        PARTY SHALL SEND A COPY OF THE AFFIDAVIT BY REGISTERED OR CERTIFIED

        MAIL OR STATUTORY OVERNIGHT DELIVERY TO THE OWNER OF THE PROPERTY. IF

        THE FILING PARTY IS NOT IN PRIVITY OF CONTRACT WITH THE PROPERTY

        OWNER AND A NOTICE OF COMMENCEMENT IS FILED FOR THE IMPROVEMENT ON

        THE PROPERTY FOR WHICH THE FILING PARTY'S LABOR, SERVICES, OR

        MATERIALS WERE FURNISHED, A COPY OF THE AFFIDAVIT SHALL BE SENT TO

        THE CONTRACTOR AT THE ADDRESS SHOWN ON THE NOTICE OF COMMENCEMENT.

        WHENEVER THE OWNER OF THE PROPERTY IS AN ENTITY ON FILE WITH THE

        SECRETARY OF STATE'S CORPORATIONS DIVISION, SENDING A COPY OF THE

        LIEN TO THE COMPANY'S ADDRESS OR THE REGISTERED AGENT'S ADDRESS ON

        FILE WITH THE SECRETARY OF STATE SHALL BE DEEMED SUFFICIENT."
    • (3) A claimant who is paid, in full, the amount set forth in the waiver and release form after filing an affidavit of nonpayment shall upon request execute in recordable form an affidavit swearing that payment in full has been received. Upon recordation thereof in the county in which the Affidavit of Nonpayment was recorded, the affidavit of nonpayment to which it relates shall be deemed void.
    • (4) Nothing in this Code section shall shorten the time within which to file a claim of lien.
    • (5) A waiver and release provided in this Code section shall be suspended upon filing of an affidavit of nonpayment until payment in full has been received.
    • (6) The claimant may rely upon the information contained in the waiver and release form when completing for filing the affidavit of nonpayment or claim of lien.
Disclaimer: These codes may not be the most recent version. Georgia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.