(a) When a contractor has performed in accordance with the provisions of a contract, the owner shall pay the contractor within 15 days of receipt by the owner or the owner's representative of any payment request based upon work completed or service provided under the contract.

(b) When a subcontractor has performed in accordance with the provisions of its subcontract and the subcontract conditions precedent to payment have been satisfied, the contractor shall pay to that subcontractor and each subcontractor shall pay to its subcontractor, within ten days of receipt by the contractor or subcontractor of each periodic or final payment, the full amount received for such subcontractor's work and materials based on work completed or service provided under the subcontract, provided that the subcontractor has provided or provides such satisfactory reasonable assurances of continued performance and financial responsibility to complete his or her work as the contractor in his or her reasonable discretion may require, including but not limited to a payment and performance bond.

Disclaimer: These codes may not be the most recent version. Georgia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.