§ 36-91-93 - Rights of persons protected by payment bond or security deposit; governmental entity not a party

O.C.G.A. 36-91-93 (2010)
36-91-93. Rights of persons protected by payment bond or security deposit; governmental entity not a party


(a) Every person entitled to the protection of the payment bond or security deposit required to be given who has not been paid in full for labor or material furnished in the prosecution of the work referred to in such bond or security deposit before the expiration of a period of 90 days after the day on which the last of the labor was done or performed by such person or the material or equipment or machinery was furnished or supplied by such person for which such claim is made, or when he or she has completed his or her subcontract for which claim is made, shall have the right to bring an action on such payment bond or security deposit for the amount, or the balance thereof, unpaid at the time of the commencement of such action and to prosecute such action to final execution and judgment for the sum or sums due such person; provided, however, that:

(1) Any person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing such payment bond or security deposit on a public works construction project where the contractor has not complied with the notice of commencement requirements shall have the right of action upon the payment bond or security deposit upon giving written notice to the contractor within 90 days from the day on which such person did or performed the last of the labor or furnished the last of the material or machinery or equipment for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was performed or done. The notice to the contractor may be served by registered or certified mail, postage prepaid, or statutory overnight delivery, duly addressed to the contractor, at any place at which the contractor maintains an office or conducts his or her business or at his or her residence, by depositing such notice in any post office or branch post office or any letter box under the control of the United States Postal Service; alternatively, notice may be served in any manner in which the sheriffs of this state are authorized by law to serve summons or process; and

(2) Any person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing such payment bond or security deposit on a public works construction project where the contractor has complied with the notice of commencement requirements in accordance with subsection (a) of Code Section 36-91-92 shall have the right of action on the payment bond or security deposit, provided that such person shall, within 30 days from the filing of the notice of commencement or 30 days following the first delivery of labor, material, machinery, or equipment, whichever is later, give to the contractor a written notice setting forth:

(A) The name, address, and telephone number of the person providing labor, material, machinery, or equipment;

(B) The name and address of each person at whose instance the labor, material, machinery, or equipment is being furnished;

(C) The name and the location of the public works construction site; and

(D) A description of the labor, material, machinery, or equipment being provided and, if known, the contract price or anticipated value of the labor, material, machinery, or equipment to be provided or the amount claimed to be due, if any.

(b) Nothing contained in this Code section shall limit the right of action of a person entitled to the protection of the payment bond or security deposit required to be given pursuant to this article to the 90 day period following the day on which such person did or performed the last of the labor or furnished the last of the material or machinery or equipment for which such claim is made.

(c) Every action instituted under this Code section shall be brought in the name of the claimant without making the governmental entity for which the work was done or was to be done a party to such action.

Disclaimer: These codes may not be the most recent version. Georgia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.