2006 Georgia Code - 13-11-7
13-11-7. (a) Except as provided in Code Section 13-11-5,
if a periodic or final payment to a contractor is delayed by more
than 15 days or if a periodic or final payment to a subcontractor
is delayed more than ten days after receipt of periodic or final
payment by the contractor or subcontractor, the owner, contractor,
or subcontractor, as the case may be, shall pay his or her
contractor or subcontractor interest, beginning on the day
following the due date, at the rate of 1 percent per month or a pro
rata fraction thereof on the unpaid balance as may be due. However,
no interest is due unless the person being charged interest has
been notified of the provision of this Code section at the time the
request for payment is made. Acceptance of progress payments or
final payment shall release all claims for interest on said
payments. (b) Nothing in this
chapter shall prohibit owners, contractors, and subcontractors from
agreeing by contract to rates of interest, payment periods, and
contract and subcontract terms different from those stipulated in
this Code section, and in this event, these contractual provisions
shall control. In case of a willful breach of the contract
provisions as to the time of payment, the interest rate specified
in this Code section shall apply.
Disclaimer: These codes may not be the most recent version. Georgia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.