§ 34–1435. Recovery of fees and costs.

Universal Citation: DC Code § 34–1435 (2018)

(a) The Commission shall allow the local distribution company to recover actual dollar-for-dollar prudently costs incurred, including a compliance fee under § 34-1434, in complying with a mandated renewable energy portfolio standard. The electricity distribution company may also pass through its prudently incurred additional costs, if any, associated with complying with the standard, through the end of the year of standard offer service in which the requirement took effect.

(b) An electricity supplier may recover a compliance fee if:

(1) The payment of a compliance fee is the least-cost measure to ratepayers as compared to the purchase of tier one renewable sources, tier two renewable sources, or solar energy to comply with a renewable energy portfolio standard; or

(2) There are insufficient tier one renewable sources, tier two renewable sources, or solar energy available for the electricity supplier to comply with a renewable energy portfolio standard.

(c) Any cost recovery under this section:

(1) May be in the form of a nonbypassable surcharge to current applicable customers; and

(2) Shall be disclosed on applicable customer bills.

(Apr. 12, 2005, D.C. Law 15-340, § 7, 52 DCR 2285.)

Section References

This section is referenced in § 34-1433 and § 34-1436.

Disclaimer: These codes may not be the most recent version. District of Columbia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.