§ 910. Conditional use permit for electrical substations [For application of this section, see 85 Del. Laws, c. 44, § 2] [Effective Jan. 1, 2026].
Universal Citation:
26 DE Code § 910 (2025)
Learn more
This media-neutral citation is based
on the American Association of Law Libraries Universal Citation Guide and is not
necessarily the official citation.
§ 910. Conditional use permit for electrical substations [For application of this section, see 85 Del. Laws, c. 44, § 2] [Effective Jan. 1, 2026]. 85 Del. Laws, c. 44, § 1;
No county shall deny a conditional use permit to any electrical substation, along with any directly related project infrastructure, proposed to be located on unincorporated land within such county where the following conditions apply:
(1) The substation is being proposed to support the operation of a proposed renewable energy generation project of 250 MW or greater;
(2) The proposed substation would be located in a heavy industrial zone;
(3) An electrical substation is an allowed conditional use within the proposed zone; and
(4) The specific zoning district in which the proposed substation would be located already has an electric substation located in such zone with a rating of 230kv or greater as of August 3, 2023.
Disclaimer: These codes may not be the most recent version. Delaware may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.