2019 Connecticut General Statutes
Title 22a - Environmental Protection
Chapter 444 - Coastal Management
Section 22a-106 - Criteria and process for action on coastal site plans.

Universal Citation: CT Gen Stat § 22a-106 (2019)

(a) In addition to determining that the activity proposed in a coastal site plan satisfies other lawful criteria and conditions, a municipal board or commission reviewing a coastal site plan shall determine whether or not the potential adverse impacts of the proposed activity on both coastal resources and future water-dependent development activities are acceptable.

(b) In determining the acceptability of potential adverse impacts of the proposed activity described in the coastal site plan on both coastal resources and future water-dependent development opportunities a municipal board or commission shall: (1) Consider the characteristics of the site, including the location and condition of any of the coastal resources defined in section 22a-93; (2) consider the potential effects, both beneficial and adverse, of the proposed activity on coastal resources and future water-dependent development opportunities; and (3) follow all applicable goals and policies stated in section 22a-92 and identify conflicts between the proposed activity and any goal or policy.

(c) Any persons submitting a coastal site plan as defined in subsection (b) of section 22a-105 shall demonstrate that the adverse impacts of the proposed activity are acceptable and shall demonstrate that such activity is consistent with the goals and policies in section 22a-92.

(d) A municipal board or commission approving, modifying, conditioning or denying a coastal site plan on the basis of the criteria listed in subsection (b) of this section shall state in writing the findings and reasons for its action.

(e) In approving any activity proposed in a coastal site plan, the municipal board or commission shall make a written finding that the proposed activity with any conditions or modifications imposed by the board: (1) Is consistent with all applicable goals and policies in section 22a-92; (2) incorporates as conditions or modifications all reasonable measures which would mitigate the adverse impacts of the proposed activity on both coastal resources and future water-dependent development activities.

(P.A. 79-535, S. 12, 25.)

Cited. 192 C. 353; 228 C. 187.

Subsec. (e):

Municipal board or commission is required to make written findings in approving coastal site plan but board's failure to state its reasons in writing is not fatal to board's decision because reviewing court must search the record for sufficiency of evidence supporting board's decision. 112 CA 239.

Disclaimer: These codes may not be the most recent version. Connecticut may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.