2019 Connecticut General Statutes
Title 16 - Public Service Companies
Chapter 277 - Department of Energy and Environmental Protection. Public Utilities Regulatory Authority. Office of Consumer Counsel. Miscellaneous Provisions
Section 16-19uu - Adjustments to competitive transition assessment with respect to economic recovery revenue bonds.

Universal Citation: CT Gen Stat § 16-19uu (2019)

(a) At such time as economic recovery revenue bonds are issued to fund the economic recovery transfer, the Public Utilities Regulatory Authority shall ensure that the competitive transition assessment charged to customers of each electric distribution company is adjusted to reflect the lower charge to be paid by customers. No electric distribution company may bill any customer an amount for the competitive transition assessment that is in excess of the amount necessary to fund the economic recovery transfer.

(b) At such time as the competitive transition assessment charged to customers has allowed full or partial recovery by the financing entity of any economic recovery revenue bonds and full or partial recovery by the electric distribution company of stranded costs not funded with the proceeds of economic recovery revenue bonds, the authority shall ensure that the competitive transition assessment charged to customers of each electric distribution company is adjusted to reflect, in the case of a partial recovery, the lower charge to be paid by customers, and, in the case of a full recovery, the absence of such assessment. No electric distribution company may bill any customer an amount for the competitive transition assessment that is in excess of the amount necessary to fund economic recovery revenue bonds or stranded costs.

(P.A. 10-179, S. 138; P.A. 11-80, S. 1; P.A. 14-134, S. 65.)

History: P.A. 10-179 effective May 7, 2010; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011; P.A. 14-134 deleted references to electric company, effective June 6, 2014.

See Secs. 16-245e to 16-245k re economic recovery revenue bonds.

Disclaimer: These codes may not be the most recent version. Connecticut may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.