(a) The Commissioner of Energy and Environmental Protection, in consultation with the electric distribution companies, shall review the state’s energy and capacity resource assessment and approve the Integrated Resources Plan for the procurement of energy resources, including, but not limited to, conventional and renewable generating facilities, energy efficiency, load management, demand response, combined heat and power facilities, distributed generation and other emerging energy technologies to meet the projected requirements of customers in a manner that minimizes the cost of all energy resources to customers over time and maximizes consumer benefits consistent with the state’s environmental goals and standards. The Integrated Resources Plan shall seek to lower the cost of electricity.

(b) On or before January 1, 2012, and biennially thereafter, the Commissioner of Energy and Environmental Protection, in consultation with the electric distribution companies, shall prepare an assessment of (1) the energy and capacity requirements of customers for the next three, five and ten years, (2) the manner of how best to eliminate growth in electric demand, (3) how best to level electric demand in the state by reducing peak demand and shifting demand to off-peak periods, (4) the impact of current and projected environmental standards, including, but not limited to, those related to greenhouse gas emissions and the federal Clean Air Act goals and how different resources could help achieve those standards and goals, (5) energy security and economic risks associated with potential energy resources, and (6) the estimated lifetime cost and availability of potential energy resources.

(c) Resource needs shall first be met through all available energy efficiency and demand reduction resources that are cost-effective, reliable and feasible. The projected customer cost impact of any demand-side resources considered pursuant to this subsection shall be reviewed on an equitable basis with nondemand-side resources. The Integrated Resources Plan shall specify (1) the total amount of energy and capacity resources needed to meet the requirements of all customers, (2) the extent to which demand-side measures, including efficiency, conservation, demand response and load management can cost-effectively meet these needs in a manner that ensures equity in benefits and cost reduction to all classes and subclasses of consumers, (3) needs for generating capacity and transmission and distribution improvements, (4) how the development of such resources will reduce and stabilize the costs of electricity to each class and subclass of consumers, and (5) the manner in which each of the proposed resources should be procured, including the optimal contract periods for various resources.

(d) The Integrated Resources Plan shall consider: (1) Approaches to maximizing the impact of demand-side measures; (2) the extent to which generation needs can be met by renewable and combined heat and power facilities; (3) the optimization of the use of generation sites and generation portfolio existing within the state; (4) fuel types, diversity, availability, firmness of supply and security and environmental impacts thereof, including impacts on meeting the state’s greenhouse gas emission goals; (5) reliability, peak load and energy forecasts, system contingencies and existing resource availabilities; (6) import limitations and the appropriate reliance on such imports; (7) the impact of the Integrated Resources Plan on the costs of electric customers; and (8) the effects on participants and nonparticipants. Such plan shall include options for lowering the rates and cost of electricity.

(e) In approving the Integrated Resources Plan, the Commissioner of Energy and Environmental Protection shall conduct an uncontested proceeding that shall include not less than one public meeting and one technical meeting at which technical personnel shall be available to answer questions. Such meetings shall be transcribed and posted on the department’s Internet web site. Not less than fifteen days before any such public meeting and thirty days before any such technical meeting, said commissioner shall publish notice of either such meeting and post the text of the proposed Integrated Resources Plan on the department’s Internet web site. Notice of such public meeting or technical meeting may also be published in one or more newspapers having state-wide circulation if deemed necessary by the commissioner. Such notice shall state the date, time, and place of the meeting, the subject matter of the meeting and time period during which comments may be submitted to said commissioner, the statutory authority for the proposed Integrated Resources Plan and the location where a copy of the proposed plan may be obtained or examined. Said commissioner shall provide a time period of not less than sixty days from the date the notice is published on the department’s Internet web site for public review and comment. Said commissioner shall consider fully all written and oral comments concerning the proposed Integrated Resources Plan after all public meetings and before approving the final plan. Said commissioner shall (1) notify by electronic mail each person who requests such notice, and (2) post on the department’s Internet web site the electronic text of the final Integrated Resources Plan and a report summarizing all public comments and the changes made to the final plan in response to such comments and the reasons therefor. The commissioner shall submit the final Integrated Resources Plan by electronic means, or as requested, to the joint standing committees of the General Assembly having cognizance of matters relating to energy and the environment. Said commissioner may modify the Integrated Resources Plan to correct clerical errors at any time without following the procedures outlined in this subsection.

(f) Not later than two years after the adoption of the Integrated Resources Plan, and every two years thereafter, the Commissioner of Energy and Environmental Protection shall report to the joint standing committees of the General Assembly having cognizance of matters relating to energy and the environment regarding goals established and progress toward implementation of said plan, as well as any recommendations concerning such plan. Any such report may be submitted electronically.

(g) All reasonable costs associated with the department’s development of the resource assessment and the Integrated Resources Plan shall be recoverable through the assessment in section 16-49. All electric distribution companies’ reasonable costs associated with the development of the plan shall be recoverable through a reconciling nonbypassable component of electric rates as determined by the authority.

(h) In the event that the Integrated Resources Plan approved by the Commissioner of Energy and Environmental Protection contains any provision the implementation of which requires funding through new or amended rates or charges, the Public Utilities Regulatory Authority may open a proceeding to review such provision, in accordance with the procedures established in sections 16-19 and 16-19e, to ensure that rates remain just and reasonable.

(P.A. 07-242, S. 51; P.A. 09-218, S. 4; P.A. 11-80, S. 89; P.A. 13-298, S. 20.)

History: P.A. 07-242 effective June 4, 2007; P.A. 09-218 amended Subsec. (b) to change assessment submittal from annually to biennially and amended Subsec. (e) to eliminate requirement that department approve, or modify and approve, procurement plan not later than 60 days after submittal, effective July 8, 2009; P.A. 11-80 amended Subsec. (a) to require Department of Energy and Environmental Protection, in consultation with Connecticut Energy Advisory Board and electric distribution companies, to develop plan, to change reference to a comprehensive plan to reference to an integrated resources plan and to add provision re plan to seek to lower the cost of electricity, amended Subsec. (b) to change date from on or before January 1, 2008, to on or before January 1, 2012, and to require department, in consultation with the board and companies, to prepare an assessment, amended Subsec. (c) to change “procurement plan” to “integrated resources plan”, to add provision in Subdiv. (2) that needs be met in a manner that ensures equity to all classes and subclasses of consumers and to add in Subdiv. (4) “each class and subclass of”, amended Subsec. (d) to change “procurement plan” to “integrated resources plan”, to add Subdiv. (8) re effects on participants and nonparticipants and to add provisions re options for lowering rates and cost, public hearing and commissioner’s ability to approve or reject the plan, amended Subsec. (e) to require that procurement manager, in consultation with electric distribution companies, regional independent system operator and Connecticut Energy Advisory Board, develop a procurement plan and hold public hearings, to delete provision re review of plan, and to add provisions re conduct and notice of hearings and re commissioner’s approval or rejection of plan, amended Subsec. (f) to change date from on or before September 30, 2009, to on or before March 1, 2012, to change “Department of Public Utility Control” to “Department of Energy and Environmental Protection” and to change “procurement plan” to “integrated resources plan”, amended Subsec. (g) to delete reference to electric distribution companies, to include integrated resources plan and to replace reference to systems benefits charge with reference to the assessment in Sec. 16-49 and added Subsec. (h) re decisions of authority guided by goals of department and plans, effective July 1, 2011 (Revisor’s note: In Subsec. (h), a provision re goals of the plans was reworded editorially by the Revisors for clarity); P.A. 13-298 amended Subsec. (a) to replace provision re developing plan with provision re approving plan, amended Subsec. (b) to delete reference to Connecticut Energy Advisory Board, amended Subsec. (d) to replace “procurement plan” with “Integrated Resources Plan” in Subdiv. (7) and to delete provision re hearing on plan and approval or rejection of plan, substantially revised Subsec. (e) to delete provisions re procurement plan and to add provisions re approval process for Integrated Resources Plan and modification of plan to correct errors, amended Subsec. (f) to replace “On or before March 1, 2012” with “Not later than two years after the adoption of the Integrated Resources Plan” and to add provision re electronic submission of report, amended Subsec. (g) to replace “All costs” with “All reasonable costs” re recovery of cost from developing resource assessment and plan and to add provision re recovery of electric distribution companies’ reasonable costs, amended Subsec. (h) to delete provision re decisions of Public Utilities Regulatory Authority and to add provision authorizing authority to open proceeding for review, and made technical and conforming changes, effective July 8, 2013.

Disclaimer: These codes may not be the most recent version. Connecticut may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.