(a) No school building project for which state assistance is sought shall be undertaken except according to a plan and on a site approved by the Department of Construction Services, the town or regional board of education and by the building committee of such town or district. No such school building project shall be undertaken at an expense exceeding the sum which the town or regional district may appropriate for the project. In the case of a school building project financed in whole or in part by an energy conservation lease purchase agreement, the expense of the project shall not exceed the sum which the town or regional school district approved for the project. A copy of final plans and specifications for each phase of site development and construction of all school building projects and for each phase thereof including site development shall be filed with the Commissioner of Construction Services subject to the provisions of section 10-292 before the start of such phase of development or construction shall be begun. In the case of a school building project which is a new construction, extension or replacement of a building to be used for public school purposes, the town or regional board of education and the building committee of such town or district, prior to the approval of the architectural plans pursuant to the provisions of section 10-292, shall provide for a Phase I environmental site assessment in accordance with the American Society for Testing and Materials Standard #1527, Standard Practice for Environmental Site Assessments: Phase I Environmental Site Assessment Process, or similar subsequent standards. The costs of performing such Phase I environmental site assessment shall be considered eligible costs of such school construction project. A town or regional school district may commence a phase of development or construction before completion of final plans and specifications for the whole project provided a copy of the latest preliminary plan and cost estimate for such project which has been approved by the town or regional board of education and by the building committee shall be submitted with the final plans and specifications for such phase. Any board of education which, prior to the approval of a grant commitment by the General Assembly, commences any portion of a school construction project or causes any such project to be let out for bid, shall not be eligible for a school construction grant until a grant commitment is so approved.

(b) The Department of Construction Services shall not approve a school building project plan or site, as applicable, if:

(1) The site is in an area of moderate or high radon potential, as indicated in the Department of Energy and Environmental Protection’s Radon Potential Map, or similar subsequent publications, except where the school building project plan incorporates construction techniques to mitigate radon levels in the air of the facility;

(2) The plans incorporate new roof construction or total replacement of an existing roof and do not provide for the following: (A) A minimum roof pitch of one-half inch per foot, except that for a total replacement of an existing roof, the Commissioner of Construction Services may permit the minimum roof pitch to be reduced to one-quarter inch per foot if the commissioner finds, based upon written certification from a licensed architect or engineer provided by the town or regional board of education, that (i) such reduction of roof pitch will not impede drainage or cause pooling of water that may leak into the building to a greater degree than that of a roof of a minimum roof pitch of one-half inch per foot, (ii) the cost of replacing the roof with a minimum roof pitch of one-half inch per foot would substantially exceed the cost of replacing the roof with a minimum roof pitch of one-quarter inch per foot, (iii) the time needed to replace the roof with a minimum roof pitch of one-half inch per foot would be substantially longer than the time needed to replace the roof with a minimum roof pitch of one-quarter inch per foot, and (iv) the existing building would not support a roof with a roof pitch of one-half inch per foot without a substantial rebuilding of the existing building, (B) a minimum twenty-year unlimited manufacturer’s guarantee for water tightness covering material and workmanship on the entire roofing system, (C) the inclusion of vapor retarders, insulation, bitumen, felts, membranes, flashings, metals, decks and any other feature required by the roof design, and (D) that all manufacturer’s materials to be used in the roofing system are specified to meet the latest standards for individual components of the roofing systems of the American Society for Testing and Materials;

(3) In the case of a major alteration, renovation or extension of a building to be used for public school purposes, the plans do not incorporate the guidelines set forth in the Sheet Metal and Air Conditioning Contractors National Association’s publication entitled “Indoor Air Quality Guidelines for Occupied Buildings Under Construction” or similar subsequent publications;

(4) In the case of a new construction, extension, renovation or replacement, the plans do not provide that the building maintenance staff responsible for such facility are trained in or are receiving training in, or that the applicant plans to provide training in, the appropriate areas of plant operations including, but not limited to, heating, ventilation and air conditioning systems pursuant to section 10-231e, with specific training relative to indoor air quality; or

(5) In the case of a project for new construction, extension, major alteration, renovation or replacement involving a school entrance for inclusion on any listing submitted to the General Assembly in accordance with section 10-283 on or after July 1, 2008, the plans do not provide for a security infrastructure for such entrance.

(1949 Rev., S. 1496; 1953, S. 990d; 1957, P.A. 593, S. 10; 1967, P.A. 294, S. 1; P.A. 73-358, S. 2; P.A. 76-418, S. 15, 18; P.A. 85-589, S. 2, 3; P.A. 88-360, S. 43, 63; P.A. 91-220, S. 5, 8; P.A. 93-378, S. 2, 4; P.A. 03-76, S. 30; 03-220, S. 6; P.A. 04-26, S. 8; 04-168, S. 1; P.A. 07-208, S. 1; P.A. 11-51, S. 90; 11-80, S. 1.)

History: 1967 act specified that site must be approved as well as plan; P.A. 73-358 required filing of plans and specifications “for each phase of site development and construction” before each phase begins and allowed commencement of phase before final plans complete for whole project if final phase plans and latest preliminary plan and cost estimates have been submitted; P.A. 76-418 made provisions applicable to projects for which state assistance sought, included reference to districts, forbade letting project out for bid until grant commitment approved and allowed commencement of phase before approval of grant commitment under same conditions as previously applied; P.A. 85-589 amended section to allow towns which commence projects or let projects out for bid to remain eligible for project grants effective July 1, 1985, and transferred site approval power from state board of education to department of education; P.A. 88-360 substituted “commissioner” for “state board” of education; P.A. 91-220 required that filing of plans and specifications be pursuant to Sec. 10-292; P.A. 93-378 added provision regarding project financed by energy conservation lease purchase agreement, effective July 1, 1993; P.A. 03-76 made a technical change, effective June 3, 2003; P.A. 03-220 designated existing provisions as Subsec. (a) and amended same by making a technical change and adding provisions re environmental site assessment, and added Subsec. (b) re grounds for rejection of a plan or site, effective July 1, 2003; P.A. 04-26 made technical changes in Subsec. (b)(4), effective April 28, 2004; P.A. 04-168 amended Subsec. (b)(2)(A) by adding provisions permitting a reduction in minimum roof pitch, effective June 1, 2004; P.A. 07-208 added Subsec. (b)(5) re school entrances, effective July 1, 2007; pursuant to P.A. 11-51, “Commissioner of Education” and “Department of Education” were changed editorially by the Revisors to “Commissioner of Construction Services” and “Department of Construction Services”, respectively, effective July 1, 2011; pursuant to P.A. 11-80, “Department of Environmental Protection” was changed editorially by the Revisors to “Department of Energy and Environmental Protection” in Subsec. (b)(1), effective July 1, 2011.

Disclaimer: These codes may not be the most recent version. Connecticut may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.