2024 California Code
Public Contract Code - PCC
DIVISION 2 - GENERAL PROVISIONS
PART 1 - ADMINISTRATIVE PROVISIONS
CHAPTER 6.6 - Alternative Project Delivery Program: Construction Manager/General Contractor Authority
Section 6950.

Universal Citation:
CA Pub Cont Code § 6950 (2024)
Learn more This media-neutral citation is based on the American Association of Law Libraries Universal Citation Guide and is not necessarily the official citation.

6950. The Legislature finds and declares all of the following:

(a) The alternative public works project delivery methods authorized under this chapter should be evaluated for the purposes of exploring whether the potential exists for reduced project costs, expedited project completion, or design features that are not achievable through the traditional project delivery methods.

(b) The design sequencing and Construction Manager/General Contractor project delivery methods rely on existing design-bid-build and design-build procurement methods respectively and have been successfully used by both public and private sector entities in California and other states for over a decade on projects that require a quick startup as they allow construction to begin before the design plans are complete for the entire project.

(c) Both methods also have the benefit of allowing for earlier collaboration between the project owner and construction contractor.

(d) This chapter shall not be deemed to provide a preference for these project delivery methods over other delivery methodologies.

(Added by Stats. 2012, Ch. 767, Sec. 1. (SB 1549) Effective January 1, 2013.)

Disclaimer: These codes may not be the most recent version. California may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.