2011 California Code
Civil Code
DIVISION 4. GENERAL PROVISIONS [3274 - 9566]
CHAPTER 2. Preliminary Notice
Section 8200


CA Civ Code § 8200 (through 2012 Leg Sess) What's This?

(a) Except as otherwise provided by statute, before recording a lien claim, giving a stop payment notice, or asserting a claim against a payment bond, a claimant shall give preliminary notice to the following persons:

(1) The owner or reputed owner.

(2) The direct contractor or reputed direct contractor to which the claimant provides work, either directly or through one or more subcontractors.

(3) The construction lender or reputed construction lender, if any.

(b) The notice shall comply with the requirements of Chapter 2 (commencing with Section 8100) of Title 1.

(c) Compliance with this section is a necessary prerequisite to the validity of a lien claim or stop payment notice under this title.

(d) Compliance with this section or with Section 8612 is a necessary prerequisite to the validity of a claim against a payment bond under this title.

(e) Notwithstanding the foregoing subdivisions:

(1) A laborer is not required to give preliminary notice.

(2) A claimant with a direct contractual relationship with an owner or reputed owner is required to give preliminary notice only to the construction lender or reputed construction lender, if any.

(Added by Stats. 2010, Ch. 697, Sec. 20. Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697.)

Disclaimer: These codes may not be the most recent version. California may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.