2019 Arkansas Code
Title 20 - Public Health and Welfare
Subtitle 2 - Health and Safety
Chapter 23 - Boiler Safety
Subchapter 3 - Certification of Boilers
§ 20-23-308. New Boilers and Unfired Pressure Vessels - Fees

Universal Citation: AR Code § 20-23-308 (2019)
  • (a) The following fees shall be paid before permits may be issued for the installation of any boiler or unfired pressure vessel:

    • (1) Boilers:

      • (A) Up to 25 horsepower, incl. $15.00

      • (B) Over 25 horsepower to 50 horsepower, incl. 20.00

      • (C) Over 50 horsepower to 100 horsepower, incl. 25.00

      • (D) Over 100 horsepower to 200 horsepower, incl. 30.00

      • (E) Over 200 horsepower to 300 horsepower, incl. 50.00

      • (F) Over 300 horsepower to 400 horsepower, incl. 60.00

      • (G) Over 400 horsepower to 500 horsepower, incl. 70.00

      • (H) Over 500 horsepower 95.00

    • (2) Unfired pressure vessels, including hot water storage containers:

      • (A) 500 gallons capacity or less $15.00

      • (B) 501 gallons capacity to 1,000 gallons capacity 20.00

      • (C) 1,001 gallons capacity to 5,000 gallons capacity 40.00

      • (D) 5,001 gallons capacity and over 50.00

  • (b) The fee paid for the issuance of a permit for the installation of pressure piping shall be one hundred dollars ($100).

Disclaimer: These codes may not be the most recent version. Arkansas may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.