2014 Arizona Revised Statutes
Title 33 - Property
§ 33-994 Right of owner of property against which lien is claimed to withhold payment to original contractor; procedure

AZ Rev Stat § 33-994 (2014) What's This?

33-994. Right of owner of property against which lien is claimed to withhold payment to original contractor; procedure

Upon service of the notice and claim of lien, the owner may retain, out of the amount due or to become due the original contractor, the value of the labor or material furnished as shown by the notice and claim of lien. The owner shall furnish the original contractor with a true copy of the notice and claim of lien and if the contractor does not, within ten days after receipt of the copy, give the owner written notice that he intends to dispute the claim, he shall be considered as assenting to the demand, which shall be paid by the owner when it becomes due.

Disclaimer: These codes may not be the most recent version. Arizona may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.