In re Beckstrom

Annotate this Case
In re Beckstrom (H.A. Manosh) (2003-274); 176 Vt. 622; 852 A.2d 561

2004 VT 32

[Filed 08-Apr-2004]
                  

                                 ENTRY ORDER

                                 2004 VT 32

                      SUPREME COURT DOCKET NO. 2003-274

                              MARCH TERM, 2004

  In re Appeal of Beckstrom, et al.    }	APPEALED FROM:
  (H.A. Manosh, Appellant)	       }
                                       }
                               	       }	Environmental Court
                                       }	
   	                               }
                                       }	DOCKET NO. 212-11-98 Vtec

                                                Trial Judge: Merideth Wright

             In the above-entitled cause, the Clerk will enter:


       ¶  1.  H.A. Manosh Corp. appeals from a decision of the
  environmental court declaring that a permit to erect a radio tower and
  support building was rendered null and void by its failure to commence
  construction within one year. Plaintiffs, comprised of persons who live in
  the neighborhood of the proposed tower, have cross-appealed from the
  court's determination that the permit was not also rendered void by
  Manosh's alleged misrepresentations in the permit application.  We affirm
  the court's ruling on the misrepresentation claim, but reverse its decision
  that the permit was void for failure to commence construction within one
  year.  

       ¶  2.  This case has a complex procedural history.  Manosh owns a
  radio tower located on what the parties refer to as the Jones property in
  the Town of Hyde Park.  On April 18, 1997, Manosh applied for a zoning
  permit to erect a radio tower and support building on a separate
  twenty-nine-acre parcel that it owns in the Town.  The application
  described the tower as 100 feet high and the building as a "cement block
  structure."  Several witnesses at trial testified that Manosh informed the
  zoning administrator at the time of the application that the company's
  intent was to relocate the Jones tower to the twenty-nine-acre parcel site,
  but that intention was not stated in the permit application, and it was
  established at trial that the Jones tower is closer to seventy-five feet
  tall, measured to the base of the metal structure rather than the foot of
  its concrete base.  

       ¶  3.  The administrator approved the application as a permitted
  use.  In fact, however, the tower was not a permitted use in the zoning
  district where the site was located, but no party appealed the issuance of
  the permit and it became final.  The application form signed by Manosh
  stated that "[a]ny permit issued as a result of this application shall be
  null and void in the event of misrepresentation or failure to undertake
  construction within one year of approval of this Zoning Permit."  The
  permit was issued on April 23, 1997, and showed an expiration date of April
  23, 1998. 
   
       ¶  4.  Within several months after issuance of the permit, Manosh
  became interested in revising its plans in order to relocate a different
  150-foot tower (later determined to be closer to 160 feet), owned by the
  Lamoille County Sheriff's Department, from its existing location in the
  Village of Hyde Park to the new twenty-nine-acre site.  In July 1997, the
  zoning administrator granted Manosh's request to amend the permit to allow
  a 150-foot tower.  The amended permit was appealed shortly thereafter by an
  adjoining landowner, but no hearing before the zoning board of adjustment
  was convened.  In September, Manosh applied for an Act 250 permit to erect
  a 150-foot tower and support building at the new site by relocating the
  so-called Village tower and shifting the antennas from the Jones tower to
  the Village tower, and to upgrade a logging road for access to the site. 
  The permit was granted in November, but was later revoked in February 1999.  

       ¶  5.  In the meantime, in August 1998, plaintiffs appealed the
  original zoning permit to the ZBA, which ruled the appeal untimely. 
  Plaintiffs also appealed the administrator's decision not to institute
  enforcement proceedings based on plaintiffs' allegations that the permit
  was void for failure to undertake construction within one year. The ZBA
  ruled that the permit had not expired, citing Manosh's undertakings in
  laying underground electrical conduits and upgrading the access road.  The
  ZBA later ruled that the initial appeal of the amended permit in July had
  been timely, that the tower was not a permitted use, and that a conditional
  use permit would be required.  In March 1999, the ZBA granted Manosh's
  application to amend the April 1997 permit, and issued a conditional use
  permit and site plan approval authorizing Manosh to relocate the Village
  tower to the new site.  

       ¶  6.  All of the ZBA rulings were appealed to the environmental
  court.  In response to cross-motions for summary judgment, the court ruled
  that the original April 1997 permit was final, notwithstanding the fact
  that it authorized a non-permitted use in the district, but that material
  facts were in dispute as to whether it had expired for lack of construction
  or was void based on alleged misrepresentations in the application. The
  court further ruled that the July 1997 amendment authorizing a 150-foot
  tower required a conditional use application, but remanded to the Town's
  planning agency for further proceedings, including the filing of a more
  complete application and a determination whether the new permit complied
  with an interim bylaw, enacted by the Town in January 1999, imposing a
  moratorium on  the erection of communications towers (the April 1997 permit
  was exempt from the bylaw in question). 

       ¶  7.  An evidentiary hearing addressed solely to the issues
  concerning the April 1997 permit was then held over two separate days in
  May and November 2002.  In May 2003, the court issued a written decision,
  rejecting plaintiffs' claim that Manosh had made fraudulent
  misrepresentations in applying for the permit, but finding nevertheless
  that the permit had expired and was void because Manosh had failed to
  undertake construction within one year of its issuance.  Both parties have
  appealed from the court's decision.      

       ¶  8.  Manosh contends the court erred in concluding that the permit
  had expired due to the failure to  undertake construction within one year
  of its issuance.  The trial court found in this regard that from January
  1998 to the expiration date in late April, Manosh performed work on the
  road leading up to the site and installed underground electrical conduit
  along the roadway.  The court also found that additional work "may" have
  been done at the tower site itself, including clearing and "some subsurface
  concrete work."  The evidence underlying these findings shows that, during
  the four-month period in question, Manosh committed almost 400 work-hours
  to the tower project, incurring expenses in excess of $26,000. Time-sheets
  and testimony established without contradiction that Manosh installed
  utility lines, graded and graveled the road leading to the site, cleared
  the site, and poured concrete.  Although the evidence does not identify the
  purpose of the poured concrete, it is reasonable to infer that it was
  related to construction of the "cement-block" support building specified in
  the permit.  
        
       ¶  9.  Although we will not - absent clear error - disturb the trial
  court's factual findings, "[q]uestions of law are reviewed de novo,
  allowing us to proceed with a nondeferential, on-the-record review."   In
  re Gulli, 174 Vt. 580, 582, 816 A.2d 485, 488 (2002)(mem).   In concluding
  that Manosh  failed to commence construction within the one-year permit
  period, the trial court here applied a legal standard which precluded
  consideration of work other than that directly related to the structures
  specified in the permit - the tower and support building.  Thus, the court
  found that grading the access road, laying utility lines, and clearing the
  tower site were immaterial, and appeared to further conclude that the
  pouring of concrete at the site - without more specific information - was
  inadequate to demonstrate that construction had commenced. 

       ¶  10.  Although Vermont law provides little guidance on this issue,
  other jurisdictions have taken a broader view of what constitutes a
  commencement of "construction" than the trial court here, holding that the
  standard to be applied should reflect the purpose to be served.  As one
  court has explained: "It is settled that the purpose of statutes or
  ordinances providing for automatic expiration or revocation of use permits
  when work has not commenced or a use established is to prevent the
  reservation of land for future purposes when the permittee has no good
  faith intent to presently commence upon the proposed use."  Cmty. Dev.
  Comm'n of Mendocino County v. City of Fort Bragg, 251 Cal. Rptr. 709, 712
  (Cal. Ct. App. 1988).  The Court of Appeals there held that despite "the
  absence of actual on-site construction," id. at 713, the developer's good
  faith intent to proceed with a permitted housing project had been
  demonstrated through the expenditure of funds on such "pre-construction"
  work as engineering and architectural studies, test borings, surveying, and
  the removal of two small pre-existing structures.  Id. at 1132.  The court
  thus concluded that the trial court had erred in "apply[ing] a standard
  concerned with the extent of construction alone," and reversed the trial
  court's judgment that the permit had expired.  Id.    

       ¶  11.  Other courts have applied a similar line of analysis.  In
  City of Ellsworth v. Doody, 629 A.2d 1221, 1223 (Me. 1993), for example,
  the Supreme Judicial Court of Maine rejected a municipality's contention
  that a permit to construct a lakefront cottage had expired under an
  ordinance requiring "significant progress of construction" within six
  months of issuance.  The court agreed with the homeowner "that the fact
  that he did not actually begin construction of the building until two years
  after obtaining the permit is not determinative."  Id.  Evidence that the
  permittee had "cleared the site, built a driveway and installed a septic
  system" within six months of issuance was sufficient to satisfy the
  ordinance.  Id.   A similar conclusion was reached in State ex rel.
  Helujon, Ltd. v. Jefferson County, 964 S.W.2d 531 (Mo. Ct. App. 1998),
  where it was alleged that the developer of a casino project had failed to
  commence development within twelve months of issuance of a zoning permit,
  as required by local ordinance.  The court found, however, that the
  clearing of trees and shrubs at a cost of over $17,000, removal of a
  pre-existing residence, and placement of a construction trailer on the site
  - while not in themselves requiring a permit - were a "necessary
  preliminary to the overall project" and thus sufficient to satisfy the
  intent of the ordinance.  Id. at 541.  Equally instructive - from the
  opposite perspective - is Ross v. Montgomery County, 250 A.2d 635 (Md.
  1969), where the court affirmed a trial court ruling that a builder had
  failed to commence construction of a proposed apartment building within the
  requisite six-month permit period. The record evidence showed that all of
  the work on the project had been performed in a single day, and consisted
  of one seven-by-fifteen foot excavation and the installation of a single
  footing.  This demonstrated, in the court's view, that the permit holder
  had not "in good faith, beg[un] actual construction under the building
  permit within a period of six months after its issuance." Id. at 638.    
   
       ¶  12.  These decisions articulate a fair and reasonable approach to
  determine whether construction has commenced within the time limit imposed
  by a zoning ordinance or permit, focused on whether -  viewed as a whole -
  the work, time, and expenditures invested in the project demonstrate a good
  faith intent to presently commence upon the permitted use.  Applying that
  approach here,  we find that the evidence clearly supports a conclusion
  that Manosh commenced construction before the permit had expired.  As
  noted, the record shows that over a period of several months, Manosh
  invested nearly 400 work-hours in the tower project, at a cost in excess of
  $26,000.  The extent and duration of the work demonstrates a good faith
  intent to make present use of the permit, not merely an artificial attempt
  to preserve the permit for future use.  Moreover, all of the work and money
  invested for grading of the access road, clearing of the project site,
  laying utility lines, and pouring of an undetermined amount of concrete -
  while not specified in the permit itself - was plainly designed to
  facilitate completion of the overall project.  Accordingly, we conclude the
  trial court erred in ruling that the permit had expired before construction
  commenced. (FN1)    
       
       ¶  13.  In their cross-appeal, plaintiffs contend the trial court
  erroneously rejected their claim that  the permit was null and void based
  on allegations that Manosh had intentionally misrepresented its intent to
  erect a 100-foot tower when it submitted its application in April 1997. 
  Plaintiffs' rather intricate theory at trial was that Manosh knew the
  actual height of the Jones tower was 75 feet and intentionally
  misrepresented its height as 100 feet.  They claimed that Manosh never
  intended to actually relocate the Jones tower, but instead had formulated a
  secret intent to erect a tower between 150 and 190 feet, and hoped that
  approval for the higher tower would be easier to obtain, and appear to be
  less extreme, if the initial permit specified a tower of up to 100 feet.
  The trial court was unpersuaded, finding as follows:  

    Based on the voluminous evidence submitted in this proceeding, we
    cannot find that the April 1997 permit application was a
    misrepresentation of [Manosh's] plans at the time the application
    was filed.  Rather, at the time it was filed [Manosh] was pursuing
    plans to install the Jones tower at that site, believing it to be
    approximately 100 feet tall, even though within a few months after
    that application [Manosh] had revised and expanded its plans to
    move the taller Village Communications tower to the site, or to
    install an even taller tower at the site.  The April 1997 permit
    is therefore not void for misrepresentation at the time the
    application was filed.

       ¶  14.  We will not disturb the trial court's factual findings
  unless, viewed in the light most favorable to the prevailing party, and
  disregarding any modifying evidence, they are clearly erroneous.  In re
  Shantee Point, Inc., 174 Vt. 248, 263, 811 A.2d 1243, 1255 (2002).  It is
  the within the trial court's province to determine the credibility of the
  witnesses and weigh the persuasive effect of the evidence.  Id.  A finding
  of fraudulent misrepresentation requires a showing that Manosh knowingly
  made a false representation of fact, or knowingly concealed facts, with the
  intention to mislead or deceive.  Silva v. Stevens, 156 Vt. 94, 103, 589 A.2d 852, 857 (1991).

       ¶  15.  A review of the record evidence reveals that the court's
  findings are amply supported by the testimony of several witnesses that
  Manosh's sole intent at the time of the April 1997 application was to move
  the Jones tower to the new site because the owner of the Jones property
  planned to use his land for other purposes.  There was also testimony that
  Manosh had, in good faith, based its estimate of the tower's height on
  information in a relevant FCC license.  A site plan dated April 17, 1998,
  illustrating the location of the 100-foot tower at the proposed new site,
  further supports the court's finding that Manosh intended to relocate the
  Jones tower to the new site at the time of the permit application. (FN2) 
  There was also testimony and documentary evidence that several months after
  receiving the April 1997 permit, Manosh was approached about moving the
  so-called Village tower - which was believed to be 150 feet in height - to
  the new site, which led to Manosh's subsequent efforts to amend the permit
  to allow a 150-foot high tower and to obtain an Act 250 permit. Thus, ample
  evidence supported the court's conclusion that the permit was not void for
  misrepresentations made at the time of the application.   
   
       ¶  16.  Plaintiffs urge, nevertheless, that the court's findings are
  overwhelmingly refuted by circumstantial evidence demonstrating an intent
  to deceive, including the fact that the permit application misstated the
  height of the Jones tower, failed to expressly state that Manosh intended
  to relocate the Jones tower, and omitted any plans to upgrade the access
  road to the site.  Plaintiffs also note that within several months of 
  receiving the permit, Manosh undertook extensive efforts to place a taller
  tower on the site.  And they note further that Manosh failed to undertake
  any preliminary work at the site until January 1998, nearly eight months
  after receiving the initial permit.  As noted earlier, however, the trial
  court is entitled to weigh the evidence and the credibility of the
  witnesses, and its findings will not be disturbed where - as here - they
  are supported by credible evidence, even in the presence of substantial
  modifying evidence.  Gulli, 174 Vt. at 582, 816 A.2d  at 488; N.A.S.
  Holdings, Inc., v. Pafundi, 169 Vt. 437, 438, 736 A.2d 780, 783 (1999).
  Accordingly, we discern no basis to disturb the trial court's conclusion
  that no misrepresentation had occurred at the time of the application to
  invalidate the permit. (FN3)

       Affirmed in part; the judgment voiding the April 1997 permit for
  failure to commence construction within one year of its issuance is
  reversed.           



                                       BY THE COURT:



                                       _______________________________________
                                       Jeffrey L. Amestoy, Chief Justice

                                       _______________________________________
                                       John A. Dooley, Associate Justice

                                       _______________________________________
                                       Denise R. Johnson, Associate Justice

                                       _______________________________________
                                       Marilyn S. Skoglund, Associate Justice

                                       _______________________________________
                                       Paul L. Reiber, Associate Justice


------------------------------------------------------------------------------
                                  Footnotes


FN1.  Plaintiffs' assertion that this preliminary work was somehow unrelated
  to the proposed tower project because the zoning administrator later
  approved Manosh's request for an amended permit to allow a 150-foot tower
  is unsupported by any citation to authority, and finds no support in reason
  or logic.

FN2.  Although plaintiffs assert in passing that the trial court erroneously
  admitted this site-plan for lack of an adequate foundation, they produce no
  argument or authority to support the claim, and we therefore decline to
  address it.  Johnson v. Johnson, 158 Vt. 160, 164, n.*, 605 A.2d 857, 859,
  n.* (1992).

FN3.  Plaintiffs make a brief argument that the court improperly excluded
  two documents allegedly relevant to the misrepresentation claim: an
  application, dated April 13, 1998,  for an amendment to add 30 feet to an
  Act 250 permit allowing a tower of 160 feet at the site, and a decision of
  the Environmental Board, dated February 13, 1999, revoking the permit for
  the 160-foot tower.  The court ruled that both exhibits were "too remote in
  time" to reflect anything material to Manosh's state of mind at the time of
  the April 1997 application.  Citing no pertinent authority, plaintiffs have
  failed to demonstrate that the court abused its broad discretion to
  determine whether the evidence was too remote to be of relevance.  See In
  re Letourneau, 168 Vt. 539, 554, 726 A.2d 31, 41 (1998) ("[T]he trial court
  has broad discretion to exclude marginally relevant evidence that is
  remote, tends to confuse the issues or causes a waste of time.").


Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.