Larkin v. City of Burlington

Annotate this Case
Larkin v. City of Burlington (99-219); 172 Vt. 566; 772 A.2d 553

[Filed 31-Apr-2001]


                                 ENTRY ORDER

                      SUPREME COURT DOCKET NO. 1999-219

                            SEPTEMBER TERM, 2000

John Larkin	                       }	APPEALED FROM:
                                       }
                                       }
     v.	                               }	Chittenden Superior Court
                                       }	
City of Burlington	               }
                                       }	DOCKET NO. S1406-97 CnC

                                                Trial Judge: Matthew I. Katz

             In the above-entitled cause, the Clerk will enter:


       Plaintiff John Larkin appeals the superior court's dismissal of his
  suit seeking damages  resulting from defendant City of Burlington's refusal
  to apply to his zoning permit application the  terms of a consent judgment
  entered into by the City and a previous owner of the subject property.   We
  affirm.

       In 1985, Northshore Partnership and Northshore Development, Inc.
  (hereinafter "Northshore")  entered into a development agreement with the
  City concerning property owned by Northshore.   Northshore later sought the
  City's approval to develop a portion of the property commonly referred to 
  as the marina site.  The City denied the permit application.  Northshore
  appealed the permit denial  and brought a damages suit in the superior
  court, (FN1) which was eventually settled pursuant to a  consent judgment
  signed by the City and Northshore on April 26, 1989.  The consent judgment 
  allowed Northshore to apply for a permit seeking no more than sixty
  residential units on the marina  site.  Under the agreement, permit
  approval would be "subject to all ordinances and regulations duly  adopted
  and in effect on the date hereof."  The consent judgment provided that it
  "shall be binding on  the successors and assigns of Northshore."

       In March 1990, the City granted Northshore approval to construct a
  38-condominium-unit  development on the marina site.  Two years later, the
  City extended the zoning permit to allow  construction on the project by no
  later than March 1993.  Northshore never built the project and  never
  sought an extension of the permit deadline.  Eventually, title to the
  property was transferred to  the Chittenden Bank through foreclosure
  proceedings.  Larkin entered into a purchase and sale 

 

  agreement with the bank on March 14, 1997.  Before he purchased the
  property, Larkin was given a  copy of a May 1995 appraisal specifically
  noting that the property had no development permits or  approvals, and that
  the status of the 1989 consent judgment was unclear.  The purchase and sale 
  agreement itself contained handwritten amendments, initialed by Larkin,
  indicating that the property  would be conveyed "as is" under a limited
  warranty deed.

       In June 1997, the same month he purchased the subject property from
  the bank, Larkin sought  the benefits of the consent judgment in applying
  for a zoning permit to construct a sixty-unit elderly  housing project on
  the marina site.  In August 1997, following two days of public hearings,
  the  planning commission denied the permit based on design review criteria
  contained in the then-current  zoning laws, as opposed to those in place at
  the time of the 1989 consent judgment.  The commission  stated that the
  large scale and site design of the planned buildings created a 460-foot
  continuous  vertical wall that blocked lake views from public access
  trails.  The commission concluded that the  development would need to be
  scaled down and sited differently to avoid creating a massive visual 
  barrier and to better respect the area's natural areas.

       In September 1997, Larkin appealed the planning commission's decision
  to the environmental  court.  Larkin also filed a suit in the superior
  court, seeking damages and injunctive and declaratory  relief based on
  claims that the City's refusal to apply the consent judgment to his permit
  application  violated a court order, violated his constitutional due
  process and property rights, and constituted a  breach of contract.  The
  parties agreed to consolidate the two actions in the environmental court. 
  In  June 1998, the environmental court granted partial summary judgment in
  favor of Larkin, ruling that  the consent judgment applied to his zoning
  permit application.  The court remanded the matter to the  planning
  commission to consider the application in light of the 1989 consent
  judgment, and  simultaneously transferred the matter to the superior court,
  presumably to consider the viability of  Larkin's damage claims.  The City
  filed a notice of appeal of the environmental court's decision, but  this
  Court dismissed it for failure to appeal from a final judgment or seek
  interlocutory appeal.  In  July 1999, the planning commission granted
  Larkin approval to build two eighteen-unit residential  structures on the
  marina site.  The permit was granted under terms of the consent judgment.

       Meanwhile, the City moved for dismissal of the transferred superior
  court action, claiming that  the court lacked subject matter jurisdiction
  to consider the matter.  In November 1998, the superior  court granted the
  City's motion, ruling that the environmental court had already granted
  Larkin the  declaratory relief he sought, and that he was not entitled to
  damages stemming from the City's  exercise of its governmental authority. 
  Noting that the City of Burlington and its planning  regulations had
  changed considerably since Northshore's permit application in the
  mid-1980s, the  court stated that the City may not barter away its
  attributes of sovereignty with respect to its zoning  powers.  In response
  to Larkin's motion for reconsideration, the court concluded that Larkin's 
  complaint should be dismissed not only for the reasons stated in its
  earlier order, but also because the  environmental court had exclusive
  subject matter jurisdiction over claims stemming from actions  taken by
  city officials concerning zoning matters.  On appeal, Larkin contends that
  the superior court  erred in dismissing his complaint for lack of subject
  matter jurisdiction, arguing that his claim for  damages was outside the
  environmental court's narrowly defined statutory authority, and that the 
  superior court retained jurisdiction over its own consent judgment.  For
  the most part, Larkin does  not brief the initial (and alternative) basis
  for the superior court's judgment - that the City was not  bound by a
  consent judgment requiring it to abdicate its zoning authority.  

 

       We need not address which court had subject matter jurisdiction over
  Larkin's damage claims  because, regardless of which one did, we agree with
  the superior court that those claims should be  dismissed.  Before
  addressing the substantive issues, we make the following preliminary
  points.   First, the environmental court's decision regarding the
  applicability of the consent judgment was not  a final judgment because the
  matter was remanded to the planning commission and transferred to the 
  superior court.  See Huddleston v. Univ. of Vermont, 168 Vt. 249, 251, 719 A.2d 415, 417 (1998)  (court's order is not final unless it resolves
  controversy between parties); In re Cliffside Leasing Co.,  167 Vt. 569,
  570, 701 A.2d 325, 325 (1997) (mem.) (environmental court's decision
  remanding  matter to zoning board was interlocutory ruling).  Second, the
  City had no obligation to file a cross-appeal because it was content with
  the superior court's final order.  See Huddleston, 168 Vt. at 255,  719 A.2d  at 419 (appellee seeking to challenge aspects of trial court decision
  must file timely cross-appeal unless party was content with final order);
  Valley Realty v. Town of Hartford, 165 Vt. 463,  465 n.2, 685 A.2d 292, 294
  n.2 (1996) (cross-appeal is unnecessary where appellee is content with 
  final order but raises alternative grounds to support it); Coll v. Johnson,
  161 Vt. 163, 167, 636 A.2d 336, 339 (1993) (same).  Third, we will not
  reverse the trial court's underlying decision if the record  before us
  reveals any legal grounds that would justify the result.  In re Handy, ___
  Vt. ___, ___, 764 A.2d 1226, 1234 (2000); see Levinsky v. Diamond, 151 Vt.
  178, 185, 559 A.2d 1073, 1079 (1989)  ("function of this Court is to affirm
  the action of the trial court on any basis available and appropriate  under
  the law"); see also Richards v. Union High Sch. Dist. 32, 137 Vt. 132, 134,
  400 A.2d 987, 989  (1979) ("Error will not result in reversal if the record
  before us discloses any legal ground which  would justify the result, even
  though the ground may not have been raised below and may not be 
  briefed."); Braune v. Rochester, 126 Vt. 527, 533, 237 A.2d 117, 121 (1967)
  ("Our rule is that we  will affirm a ruling of a trial court upon any legal
  ground shown by the record, even though the  ground may not have been
  raised below, and may not be briefed.").

       As noted, the principal basis for the superior court's dismissal of
  Larkin's claims was that the  City cannot contract away its zoning
  authority.  It is well settled that a municipality cannot  contractually
  deprive itself of its legislative or governmental powers.  10 E. McQuillin,
  The Law of  Municipal Corporations § 29.07, at 277 (3d ed. 1999); see
  Vermont Dep't of Pub. Serv. v.  Massachusetts Mun. Wholesale Elec. Co., 151
  Vt. 73, 81-82, 558 A.2d 215, 222 (1988)  (municipality's statutory
  authority to exercise its police powers is in nature of public trust and
  thus  cannot be bartered away).  Accordingly, courts are likely to find
  "illegal contract zoning . . . where  there is an express bilateral
  agreement that bargains away the municipality's future use of the police 
  power."  3 A. Rathkopf & D. Rathkopf, The Law of Zoning and Planning §
  29A.03[1][b], [f], at 27,  33-34 (1990) ("courts generally have held that
  rezoning agreements that protect land from future  rezonings are void as
  'illegal contract' zoning"); see Attman v. Mayor, 552 A.2d 1277, 1278 (Md. 
  1989) (although municipality may enter into binding settlement agreement
  concerning certain aspects  of land use, it may not contract away exercise
  of its zoning power).

       Courts, however, have recognized the need for land-use agreements
  between developers and  municipalities to assure stability in permitting
  large projects; thus, the trend has been to allow such  agreements unless
  they constitute a usurpation of the municipality's zoning authority.  See
  Rathkopf  & Rathkopf, supra, § 29A.03[1][a], [c], at 22-23, 30.  In fact,
  several states have codified the process 

 

  for entering into development agreements.  Id. § 29A.03[1][g][i], at 34-35. 
  While these statutes  generally authorize local governments to assure
  developers that zoning regulations in effect at the  time of an agreement
  will remain in effect until the project is completed, they also require
  provisions  in the agreements that pertain to the duration of the agreement
  and the conditions upon which the  agreement may be terminated.  Id., at 35
  n.50.  Even so, "[t]he extent to which a local government  may validly
  restrict or limit its future use of the police power under statutorily
  authorized  development agreements is an issue that has not as yet been
  clearly resolved by state courts."  Id. §  29A.03[1][g][ii], at 38.

       In this case, Larkin argued that the City had to consider his 1997
  permit application under the  1989 consent judgment between the City and
  Northshore, even though the application was filed by a  different developer
  and was for an entirely different project than the one submitted by
  Northshore  nearly a decade earlier.  Larkin's construction of the
  agreement would require the City to apply it to  any permit application
  concerning the subject property by any subsequent owner at any future time, 
  at least until the property was developed.  This would, in effect, freeze
  the zoning of the property  until that time.  In taking this position,
  Larkin relied on the absence of a termination provision or any  other
  provision in the development agreement between the City and Northshore
  limiting the duration  of the City's commitment to allow development of the
  subject property under its zoning laws in  effect at the time of the
  judgment.  He also necessarily relied on the provision stating that the 
  agreement "shall be binding on the successors and assigns of Northshore."

       Because we conclude that the latter provision does not apply to
  Larkin, we need not consider  whether the development agreement unlawfully
  limited the City's zoning authority or further whether  principles of res
  judicata applied to the consent judgment notwithstanding the unlawfulness
  of the  agreement.  The boilerplate language "successors and assigns," when
  referring to corporations,  ordinarily applies only when another
  corporation, through legal succession, assumes  the rights and  obligations
  of the first corporation.  Atchison Casting Corp. v. Dofasco, Inc., 889 F. Supp. 1445,  1458-59 (D. Kan. 1995).  Here, following foreclosure, Larkin
  purchased from a bank a portion of the  property formerly owned by
  Northshore and subject to a development agreement between the City  and
  Northshore.  The agreement, which was incorporated into the 1989 consent
  judgment, concerned  the personal rights of the developer with respect to
  the property.  No provision of the agreement  indicated that it ran with
  the land.  Nor was Larkin a successor to Northshore as a continuation of 
  Northshore's corporate entity.  See Farm & Home Sav. Ass'n v. Strauss, 671 S.W.2d 682, 684-85  (Tex. Ct. App. 1984) (when used in contractual
  provision, "successors" is term of art that does not  encompass third-party
  purchasers of land from corporation).  Nor did Northshore assign Larkin, 
  either orally or in writing, its interests under the consent judgment.  See
  Oquirrh Ass'n v. First Nat'l  Leasing Co., 888 P.2d 659, 663 (Utah Ct. App.
  1994) ("successors and assigns" language can only  refer to those who
  succeed to party's interest "in the contract through inheritance,
  assignment, or the  like," rather than to party's interest or claim "in the
  premises"); cf. Lamb v. Geovjian, 165 Vt. 375,  380, 683 A.2d 731, 735
  (1996) (identity of parties for res judicata purposes is present when one
  party  is so identified in interest with other party that they represent
  one single legal right); Davis v. Saab  Scania of Amer., Inc., 133 Vt. 317,
  320, 339 A.2d 456, 458 (1975) (res judicata barred suit against  successor
  corporation).  Under these circumstances, neither the agreement nor the
  consent judgment  extended to Larkin.

 

       Finally, we conclude, as a matter of law, that Larkin cannot prevail
  on his estoppel claim,  which was not addressed either by the environmental
  court or the superior court.  Estoppel against  the government is applied
  only in rare instances in which the elements of estoppel are met and "'the 
  injustice that would result from a failure to uphold an estoppel is of
  sufficient magnitude to justify  any effect upon public interest or policy
  that would result from raising estoppel.'" Worker's Comp.  Div. v. Hodgdon,
  ___ Vt. ___, ___, 759 A.2d 73, 75 (2000) (quoting Stevens v. Dep't of Soc. 
  Welfare, 159 Vt. 408, 419, 620 A.2d 737, 743 (1992)); see Wesco, Inc. v.
  City of Montpelier, 169  Vt. 520, 523-24, 739 A.2d 1241, 1244 (1999)
  (equitable estoppel is based on grounds of fair dealing  and justice, and
  may be invoked against government only in extraordinary circumstances); In
  re  Letourneau, 168 Vt. 539, 547-48, 726 A.2d 31, 37-38 (1998) (same); see
  also Tour Costa Rica v.  Country Walkers, Inc., ___ Vt. ___, ___, 758 A.2d 795, 799, 801 (2000) (under doctrine of  promissory estoppel, promise is
  binding if injustice can be avoided only by enforcing promise;  whether
  justice requires enforcement of promise is question of law).  Here, even
  assuming Larkin  could meet the four elements of equitable estoppel, which
  does not appear to be the case, there is no  injustice in declining to
  award him damages for expenses resulting from him going to court to obtain 
  a remedy to which he was not entitled.  Cf. Chioffi v. City of Winooski,
  165 Vt. 37, 39-41, 676 A.2d 786, 788-89 (1996) (damages are normally not
  available for regulatory delay resulting from appeal  process).  This is
  not a situation in which Larkin conferred benefits upon the City without
  receiving  benefits in return; indeed, in the end, his application was
  permitted under the 1989 consent judgment.  Cf. Marrone v. Town of Hampton,
  466 A.2d 907, 910-11 (N.H. 1983) (concluding that because  town did not
  have legal authority to permit landscaping restricting access to public
  beach, plaintiffs  were not entitled to damages for their reliance on
  town's representations inducing them to make  improvements, but allowing
  plaintiffs to maintain quantum meruit action seeking reimbursement for 
  improvements).


       Affirmed.


                                       BY THE COURT:


                                       _______________________________________
                                       Jeffrey L. Amestoy, Chief Justice

                                       _______________________________________
                                       John A. Dooley, Associate Justice

                                       _______________________________________
                                       James L. Morse, Associate Justice

                                       _______________________________________
                                       Denise R. Johnson, Associate Justice

                                       _______________________________________
                                       Marilyn S. Skoglund, Associate Justice



------------------------------------------------------------------------------
                                  Footnotes


FN1.  The suit was brought before jurisdiction over zoning matters became
  vested in the  environmental court.  See 4 V.S.A. § 1001(b).



Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.