Christenson v. Crowned Ridge Wind, LLC
Annotate this Case
The Supreme Court affirmed the decision of the South Dakota Public Utilities Commission (PUC) approving the application of Crowned Ridge Wind, LLC for a permit to construct a wind energy farm in northeast South Dakota, holding that the PUC acted within its discretion in this case.
After a contested hearing, the PUC issued a written decision approving the permit. Two individuals who lived in rural areas near the project and had intervened to oppose Crowned Ridge's application sought review. The circuit court affirmed. The Supreme Court affirmed, holding (1) neither of the Intervenors' evidentiary claims were sustainable; and (2) even if the Intervenors' claims were preserved for appeal, the PUC acted within its discretion when it denied the Intervenors' challenges to certain testimony.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.