In re Application of E. Ohio Gas Co.
Annotate this CaseUpon its implementation of an automated-meter-reading (“AMR”) program, the East Ohio Gas Company, d/b/a Dominion East Ohio (“Dominion”), sought to recover costs associated with its AMR program. The Public Utilities Commission (“Commission”) reduced Dominion’s proposed customer charge from $0.54 per customer per month to $0.42 per customer per month because Dominion had allegedly failed to timely implement the AMR program. The Supreme Court reversed in part and affirmed in part, holding that the Commission’s order was substantively unreasonable because its reduction of Dominion’s AMR charge was not rationally tied to Dominion’s alleged failure to meet certain deadlines. Remanded.