Dynalectric Co. of Nev., Inc. v. Clark & Sullivan Constructors, Inc.

Annotate this Case
Justia Opinion Summary

After Clark and Sullivan Constructors (C&S), a general contractor, solicited bids for a public works project, Dynalectric, a subcontractor, submitted a bid to perform electrical work on the project. C&S incorporated Dynalectric's bid into its bid for the contract, and C&S was awarded the project. Subsequently, Dynalectric repudiated its obligations to C&S. C&S sued Dynalectric in district court under various theories of liability, including promissory estoppel. The district court entered judgment for C&S on its promissory estoppel claim and awarded C&S $2,501,615 in damages, which represented the difference between Dynaletric's bid and the amount C&S paid the three replacement contractors to complete the work. Dynalectric appealed, contending that the district court applied the incorrect measure of damages. The Supreme Court affirmed, holding (1) the determination of the appropriate measure of damages in any given case turns on considerations of what justice requires and the foreseeability and certainty of the particular damages award sought; and (2) the presumptive measure of damages for a general contractor that reasonably relies on a subcontractor's unfulfilled promise is the difference between the nonperforming subcontractor's original bid and the cost of the replacement subcontractor's performance.

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.