PER CURIAM.
Plaintiffs appeal as of right from a judgment of no cause of action in favor of defendant, with
costs and attorney fees ordered under MCR 2.625 and MCR 2.403(O). We affirm.
Defendant provides electrical service to plaintiffs’ dairy farm and maintains electrical distribution
lines across the street from the dairy farm. In 1985, plaintiffs filed a lawsuit against defendant alleging
that stray voltage, described as neutral-to-earth voltage, had leaked from the power lines into the
ground owned by plaintiffs, decreasing the milk production of the dairy cattle. The lawsuit was
dismissed in 1988 pursuant to a settlement. Defendant subsequently converted the electrical system on
plaintiffs’ property from a grounded to an ungrounded system. The parties delayed execution of the
release effectuating the settlement so they could monitor the new ungrounded system. Plaintiffs did not
execute the release until June 1, 1990. The release document specified a consideration of $750,000,
but excepted “future personal injury and death and future incidents and claims which are unrelated,
separate and apart from the incidents and claims from which this document is intended to release as
hereinafter set forth, whether past, present or future . . . .” The release also specified that defendant
agreed to “take reasonable steps at its expense to isolate the VanDenBerg farms . . . by converting the
line serving said farms to operate at 4,800 volts, ungrounded, and to monitor said conversion in an effort
to eliminate the . . . electric distribution system as a source of stray voltage on said farms.” The release
parenthetically referred to “stray voltage” as “also known as transient voltage and neutral to earth
voltage.” Further, the release contained an integration clause declaring that, “no promise, inducement or
agreement not herein expressed has been made to the undersigned, that this Release contains the entire
-1
agreement between the parties, and that the terms of this Release are contractual and not a mere
recital.”
In 1992, plaintiffs filed the instant lawsuit, setting forth a number of counts based on allegations
that, notwithstanding the new system installed by defendant, milk production continued at a decreased
level as a direct result of stray voltage, transients and the harmonics created by the electrical system.
The trial court ordered directed verdicts on all counts in plaintiffs’ complaint, except for contract and
negligence theories of liability. The jury, by special verdict, found in favor of defendant based on the
June 1, 1990 release. The jury answered “no” to the following question, which the parties failed to
challenge: “Do you find that plaintiffs are entitled to sue Consumers Power again, despite their
settlement of the prior lawsuit and their signing the June 1, 1990 out-of-court settlement and release
agreement?”
Plaintiffs contend that it is against public policy to interpret the release between a customer and
a public utility as barring any future suit over the quality of service when the customer has no other utility
to bargain with for services. We find that this issue is not properly before us because plaintiffs have
insufficiently briefed any particular decision of the trial court that they believe was in error. Goolsby v
Detroit, 419 Mich 651, 655 n 1; 358 NW2d 856 (1984). We note that the record does not show that
plaintiffs’ attorney asked the trial court to construe the consequences of the release as a matter of law
until moving for a new trial or judgment notwithstanding the verdict. During trial, plaintiffs opposed
defendant’s motion for a directed verdict by offering parol evidence to aid the factfinder in construing
the release. Because reversible error must be that of the trial court, and not error to which the
aggrieved party contributed by plan or negligence, plaintiffs, having offered evidence of the release’s
ambiguity, cannot now argue that the trial court rather than the jury should have construed the release.
Detroit v Larned Associates, 199 Mich App 36, 38; 501 NW2d 189 (1993).
More importantly, we find no support for plaintiffs’ argument that the jury was permitted to
construe the release in a manner that violates public policy. Although plaintiffs characterize this issue as
one involving a release of a future action, the jury was instructed that it must find a release of “future
damages.” Further, the principal case relied on by plaintiffs, Southwestern Public Service Co v
Artesia Alfalfa Growers’ Ass’n, 67 NM 108; 353 P 2d 62 (1960), which involved a covenant not to
sue in the ordinary course of business, is distinguishable from the instant case involving a release
executed as part of a monetary lawsuit settlement. Releases given in exchange for a compromised
settlement of an action or preexisting claim have been upheld as valid. See generally Cudnik v William
Beaumont Hosp, 207 Mich App 378, 387-388 n 8; 525 NW2d 891 (1994). Indeed, the law favors
settlements. Stefanac v Cranbrook Educational Community (After Remand), 435 Mich 155, 163;
458 NW2d 56 (1990). The instant release was executed as part of a settlement of plaintiffs’ preexisting
action against defendant. Because the release did not purport to exculpate defendant from any potential
claim arising from its operation of the electricity distribution system, we find that plaintiffs have
established no public policy basis for relief.
Plaintiffs next argue that the trial court improperly denied their request to amend the contract
count before mediation and trial. We disagree. Although plaintiffs argue that they moved to amend the
complaint to clarify the contract claim, the trial court denied the motion based on plaintiffs’ attorney’s
-2
representation that he sought to add a cause of action for breach of an alleged August 31, 1988
agreement to trim trees, as distinguished from a claim that defendant had breached the June 1, 1990
release. We conclude that the trial court acted within its discretion in denying this motion to amend
when plaintiffs sought leave to amend to add the new contract claim only three months prior to trial and
after mediation had occurred and discovery had closed. Weymers v Khera, 454 Mich 639, 658-660;
563 NW2d 647 (1997).
Plaintiffs next contend that the trial court abused its discretion in a number of rulings, thus
denying them substantial justice. We decline to consider these arguments because they have been
insufficiently briefed. A party may not merely announce a position and then leave it to this Court to
discover and rationalize the basis of the claim. Goolsby, supra at 655 n 1; In re Toler, 193 Mich App
474, 477; 484 NW2d 672 (1992).
Plaintiffs next claim the jury’s verdict was inherently inconsistent, arguing that because the
release establishes the contract under which defendant agreed to trim trees, the jury could not have also
found that this same release bars plaintiffs’ claim under the tree-trimming agreement. Because the form
of the verdict is in essence a jury instruction and plaintiffs failed to timely raise this issue, we will review
this issue only if necessary to prevent manifest injustice. Bieszck v Avis Rent-A-Car System, Inc, 224
Mich App 295, 302; 568 NW2d 401 (1997). We conclude that no manifest exists because special
verdict question number one was not inherently inconsistent.
We note that cases discussing inconsistencies in the verdict generally address situations where a
jury answers more than one question. See, e.g., Harrington v Velat, 395 Mich 359, 359-360; 235
NW2d 357 (1975); Granger v Fruehauf Corp, 429 Mich. 1, 5-10; 412 NW2d 199 (1987). In the
case at bar, the jury only rendered a verdict on the first question of the special verdict form because that
question instructed the jury not to answer any further questions if it answered “no.” However, the
principles applied in cases of multiple verdicts are instructive regarding the proper approach to apply to
plaintiffs’ claim of inconsistency. Hence, we will make every attempt to harmonize the jury’s “no”
answer to question number one with plaintiffs’ contract claim alleging a breach of the release document.
Granger, supra at 9.
We find that the jury’s negative response to question number one reconciles with plaintiffs’
contract claim once it is recognized that a factual question existed for the jury on whether the June 1,
1990 release provision requiring that defendant “take reasonable steps at its expense to isolate the
VanDenberg farms” can be construed as containing an agreement to trim trees, as plaintiffs claimed at
trial. The jury could have determined that the release did not contemplate that defendant agreed to trim
trees. If the jury found no such agreement within the release, it would be left with the task of
determining whether the alleged voltage and associated damage to cows (caused by untrimmed trees
coming into contact with power lines after the June 1, 1990 release was signed) came within the scope
of the $750,000 settlement paid by defendant in exchange for plaintiffs’ release in the prior lawsuit. If
the jury found that the alleged damages came within the scope of this settlement (e.g., that plaintiffs gave
up their right to obtain future damages), the jury could logically have found that plaintiffs could not sue
defendant again in response to question number one. Because the jury’s verdict can be harmonized
with plaintiffs’ contract claim, we hold that the form of the verdict caused no manifest injustice.
-3
Plaintiffs next contend that the trial court should have granted their request for a res ipsa loquitur
instruction. Because plaintiffs did not object on the record to the jury instructions on this
-4
ground, we will only consider this issue if necessary to prevent manifest injustice. Mina v General Star
Indemnity Co, 218 Mich App 678, 680; 555 NW2d 1 (1996), rev’d in part on other grounds 455
Mich 865 (1997). No manifest injustice resulted from the absence of a res ipsa loquitur instruction
because this doctrine did not apply to the instant facts. Plaintiffs’ attorney argued at trial that plaintiffs
had proven a negligent act, the failure to trim trees, and furthermore, the jury’s answer to question
number one made it unnecessary for the jury to decide whether plaintiffs proved their negligence theory.
See generally Cloverleaf Car Co v Phillips Petroleum Co, 213 Mich App 186, 193-194; 540
NW2d 297 (1995) (major purpose of the doctrine of res ipsa loquitur is to create at least an inference
of negligence where the plaintiff is unable to prove the occurrence of a negligent act).
Finally, we consider the issues raised by plaintiffs concerning the trial court’s award of mediation
sanctions. Plaintiffs first argue that the trial court erroneously awarded investigation and preparation fees
occurring after their rejection of a mediation evaluation because these fees were not necessitated by
their rejection. We reject plaintiffs’ claim because MCR 2.403(O)(6) does not limit an award of
attorney fees to services performed at the trial. Joerger v Gordon Food Service, Inc, 224 Mich App.
167, 179; 568 NW2d 365 (1997). The phrase “necessitated by the rejection of the mediation
evaluation” denotes only a temporal demarcation, precluding recovery of fees for hours spent before
rejection of the mediation evaluation. Severn v Sperry Corp, 212 Mich App 406, 417; 538 NW2d 50
(1995). Further, we are not persuaded that the trial court abused its discretion in determining the
amount of attorney fees. J C Building Corp II v Parkhurst Homes, Inc, 217 Mich App 421, 428;
552 NW2d 466 (1996); Haberkorn v Chrysler Corp, 210 Mich App 354, 379-380; 533 NW2d
373 (1995).
We refuse to analyze plaintiffs’ remaining allegations of error regarding the trial court’s award of
mediation sanctions. Plaintiffs’ contention that defendant is not entitled to any mediation sanction
because they improved their position before the trial is not properly before us because it lacks citation to
supporting authority. Goolsby, supra at 655 n 1. Plaintiffs’ argument concerning expert witness fees is
not properly before us because it is not included in the statement of the issues. Meagher v McNeely &
Lincoln, Inc, 212 Mich App 154, 156; 536 NW2d 851 (1995). Finally, plaintiffs’ assertion that
defendant is not entitled to all requested expenses is not properly before us because it has been
insufficiently briefed. Goolsby, supra at 655 n 1.
Affirmed.
/s/ Hilda R. Gage
/s/ E. Thomas Fitzgerald
/s/ Michael R. Smolenski
-5
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.