GreenRoots, Inc. v. Energy Facilities Siting Bd.
Annotate this Case
The Supreme Judicial Court affirmed the order of the Energy Facilities Siting Board approving a project change petition filed by NSTAR Electric Company, doing business as Eversource Energy, that would move the boundaries of an electric substation 190 feet from the location that had previously been approved, holding that the Board did not err in approving the project change.
Specifically, the Supreme Judicial Court held (1) the Board did not err in determining that GreenRoots, Inc. did not satisfy the applicable legal standard for the reopening of a completed adjudicatory proceeding; (2) the Board complied with the statutory and regulatory requirements regarding public participation and environmental justice; and (3) the Board's conclusion that Eversource reasonably addressed risks from future sea level rise under the circumstances was supported by substantial evidence.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.