SENECA WASTE SOLUTIONS, INC., Plaintiff-Appellant, vs. SHEAFFER MANUFACTURING COL, LLC, and SHEAFFER PEN CORPORATION, A Division of BIC USA, INC., Defendants-Appellees.
Annotate this Case
Download PDF
IN THE COURT OF APPEALS OF IOWA
No. 9-610 / 09-0325
Filed November 12, 2009
SENECA WASTE SOLUTIONS, INC.,
Plaintiff-Appellant,
vs.
SHEAFFER MANUFACTURING COL, LLC,
and SHEAFFER PEN CORPORATION, A
Division of BIC USA, INC.,
Defendants-Appellees.
________________________________________________________________
Appeal from the Iowa District Court for Lee (North) County, Cynthia
Danielson, Judge.
Seneca Waste Solutions, Inc. appeals from the district court order granting
summary judgment in favor of the defendants on its breach of contract claim.
REVERSED AND REMANDED.
Brenda . Myers-Maas, West Des Moines, for appellant.
Benjamin P. Roach of Nyemaster, Goode, West, Hansell & O‟Brien, P.C.,
Des Moines, for appellees.
Heard by Eisenhauer, P.J., Potterfield, J., and Mahan, S.J.*
*Senior judge assigned by order pursuant to Iowa Code section 602.9206 (2009).
2
MAHAN, S.J.
Seneca Waste Solutions, Inc. (Seneca Waste) appeals from the district
court order granting summary judgment in favor of the defendants on its breach
of contract claim. Seneca Waste contends the district court erred in concluding
the contract between the parties limited the amount it could be paid for its
services to $170,000.00. In the alternative, Seneca Waste contends it is entitled
to the full $170,000.00 available under the contract. We reverse and remand.
I. Background Facts and Proceedings.
Sheaffer Manufacturing Co.,
L.L.C. (Sheaffer) operated a facility in Fort Madison that manufactured writing
instruments. In 2006, the company decided to close the facility. The process
required the cleaning and decontamination of the facility, and Sheaffer sought
bids from several environmental contractors to perform this work.
On September 7, 2006, Seneca Waste submitted a bid to perform the
required work for an estimated total cost of $143,520.67. It submitted a second
bid on September 17, 2006, for $128,756.72 after a change in subcontractors
lowered the projected cost of cleanup. Based on its bid, Sheaffer chose Seneca
Waste to perform the work.
On November 9, 2006, the parties entered into a written contractual
agreement for Seneca Waste to provide the cleanup services. The agreement
provides in pertinent part:
2. Scope of Work. The Contractor will furnish all of the
materials to perform all of the Work as described in the first page of
the letter dated September 7, 2006, and sent by Seneca Waste
Solutions, LLC to Michele Pancza, BIC Consumer Products
Manufacturing Co. Inc., together with the itemized worksheet used
3
to calculate the project cost estimate, which are attached hereto
and made a part of this Agreement as Exhibit A.
....
5. Contract Price and Payments. The work shall be
charged on a Time and Materials Cost Basis at the rates quoted by
Contractor in Exhibit A, except that the Work shall not exceed One
Hundred Seventy Thousand Dollars ($170,000.), inclusive of all
taxes, subcontractor fees, and any and all other surcharges, costs
and expenses. Sheaffer will pay Contractor upon satisfactory
completion of Work and within forty-five (45) days of receipt of
invoice.
....
9. Applicable Law. Any controversy or claim arising out of
or relating to this Agreement, or the breach thereof, shall be
governed and construed with the laws of the State of Iowa without
regard to the conflict of law rules of such State.
....
12. Complete Agreement. This Agreement, together with
all exhibits attached hereto, constitutes the full and complete
understanding and agreement of the parties relating to the subject
matter hereof and supersedes all prior or contemporaneous
understandings and agreements relating to such subject matter.
Any waiver, modification or amendment of any provision of this
Agreement shall be effective only if in writing and signed by the
parties hereto.
Attached to the agreement is Seneca Waste‟s September 7, 2006 letter and bid
to Sheaffer.
The first paragraph of the September 7, 2006 letter described in
paragraph two of the agreement reads:
Seneca Waste Solutions, LLC, is pleased to submit to the
BIC/Sheaffer Pen this Budgetary T&M estimate for performing
decontamination/cleaning/demolition services as per the scope of
work specified in the Vendor-Provided Sheaffer Closure/Clean-up
Activities Document. The project timeline is estimated at 20
working days.
All vacuumed and rinsate residuals and
decontamination liquids shall be off loaded on site in approved
containers. This project shall be performed on a Time and Material
Cost Basis Port-To-Port with an estimated cost based upon
projects of similar nature, specified scope of work and onsite preestimate inspections. Attached is the itemized worksheet used to
calculate the project cost estimate.
4
The bid goes on to note modifications to the scope of work being performed will
affect the project time and cost. It further states the estimate for the disposal of
50/50 waste water sludge through Heritage Environmental Services to be $5186
for 4000 gallons of sludge with the amount “subject to change based on waste
analysis and volume.” The bid concludes with the following language:
Heritage environmental estimate is based on preferred rates
extended to Seneca via a mutual aid agreement. Extra effort has
been made to quantify the cost of this scope of work, however due
to its nature, the rates and terms may be subject to modifications as
the work proceeds and with mutual consent of BIC.
Seneca Waste began performing its services for Sheaffer. Around that
time, Sheaffer shut down its on-site waste water treatment plant. Seneca Waste
was informed of the shut down, but did not object. The rinsate, or washwater,
was then disposed of through Heritage Environmental Services rather than onsite as previously anticipated. The amount of waste water requiring treatment or
disposal ultimately amounted to 18,000 gallons.
On January 5, 2007, an email from Michele Pancza to another Sheaffer
employee states Pancza had received a call from a Seneca Waste employee
“indicating they may be approaching the „not-to-exceed‟ price agreed upon by the
contract.” Seneca Waste claimed “the difference is in the volume of wastewater
which they have had to dispose.” Pancza states she did not agree to exceed the
contract price but concedes “they may have a point.”
On January 15, 2007, Craig Smith sent an email to Pancza to inform her
Seneca Waste was nearly finished with the project. It states in pertinent part:
5
We are keeping an eye on the total costs of the project as we near
our price cap. We are coordinating our efforts with Brent Packard
at Sheaffer to see that this project is completed soon and to your
satisfaction. I just wanted to keep you in the loop as we finish up
this project.
In response, Pancza asked to be informed as to the final cost of the project once
known.
Seneca Waste billed Sheaffer for a total of $211,599.47 to perform the
cleanup work. Sheaffer paid, and Seneca Waste accepted, $145,980.87 for this
work. Upon being billed in an amount that exceeded the $170,000.00 price cap
for the contract, Sheaffer tendered $24,019.13 to Seneca Waste to round out its
total payment for services at $170,000.00. Seneca Waste did not accept this
payment.
Seneca Waste filed suit against Sheaffer and Sheaffer Pen Corporation.1
It alleged the defendants failed to pay the amount due for the services provided.
Both parties filed motions for summary judgment.
Following a hearing, the
district court entered its ruling granting summary judgment in favor of the
defendants. It found the plain language of the contract capped Seneca Waste‟s
billing at $170,000.00.
The court rejected Seneca Waste‟s argument that
language in the bid anticipating a modification of the projected service costs if the
workload were to increase was incorporated into the contract. Accordingly, the
court held “[Seneca Waste‟s] claim that they are entitled to money in excess of
the contract‟s „not-to-exceed‟ clause fails as a matter of law.”
1
Sheaffer Pen alleges it should not have been a party to this action as it did not own or
operate the facility in question, or contract with Seneca Waste for the services provided.
6
II. Scope and Standard of Review. We review the district court‟s ruling
on summary judgment for the correction of errors at law. Iowa R. App. P. 6.907;
Lobberecht v. Chendrasekhar, 744 N.W.2d 104, 106 (Iowa 2008). Summary
judgment is appropriate
if the pleadings, depositions, answers to interrogatories, and
admissions on file, together with the affidavits, if any, show that
there is no genuine issue as to any material fact, and that the
moving party is entitled to a judgment as a matter of law.
Iowa R. Civ. P. 1.981(3); Lobberecht, 744 N.W.2d at 106. The moving party has
the burden to establish it is entitled to judgment as a matter of law, and the
evidence must be viewed in the light most favorable to the nonmoving party.
Hunter v. City of Des Moines Mun. Hous. Auth., 742 N.W.2d 578, 584 (Iowa
2007).
III. Contract Construction. Seneca Waste contends the district court
erred in construing the contract to have a $170,000.00 price cap under the facts
of this case. It argues the contract incorporates the initial bid by reference, and
that only the work listed in the initial bid is subject to the $170,000.00 price cap.
Because it performed additional work not anticipated in its initial bid, Seneca
Waste claims it is entitled to payment in excess of $170,000.00.
When reviewing the district court‟s construction of a contract, we must
keep in mind the cardinal rule that the intent of the parties controls. Iowa Fuel &
Minerals, Inc. v. Iowa State Bd. of Regents, 471 N.W.2d 859, 862 (Iowa 1991).
Except in cases of ambiguity, we determine the parties‟ intent from what the
contract says. Id. Therefore, if the parties‟ intent is clear and unambiguous from
the words of the contract, we enforce the contract as written. Id. at 863. When
7
there are ambiguities in a contract, they are strictly construed against the drafter.
Id. An ambiguity exists when a genuine uncertainty exists concerning which of
two reasonable constructions is proper.
Id.
“The test for ambiguity is an
objective one: „Is the language fairly susceptible to two interpretations?‟” Id.
The language at issue here states,
The work shall be charged on a Time and Materials Cost Basis at
the rates quoted by Contractor in Exhibit A, except that the Work
shall not exceed One Hundred Seventy Thousand Dollars
($170,000.), inclusive of all taxes, subcontractor fees, and any and
all other surcharges, costs and expenses.
This language is clear and unambiguous. It states the basis for how charges are
calculated, the rates at which Seneca Waste may charge, and places a price cap
of $170,000.00 on all work performed.
Seneca Waste argues the contract incorporates by reference the
September 7, 2006 letter and bid it submitted to Sheaffer. It claims that when
read as a whole, the price cap only applies to the work set forth in the September
7, 2006 letter and bid.
Under the paragraph entitled “Scope of Work,” the
contract states:
The Contractor will furnish all of the materials to perform all of the
Work as described in the first page of the letter dated September 7,
2006, and sent by Seneca Waste Solutions, LLC to Michele
Pancza, BIC Consumer Products Manufacturing Co. Inc., together
with the itemized worksheet used to calculate the project cost
estimate, which are attached hereto and made a part of this
Agreement as Exhibit A.
Under the doctrine of incorporation by reference, one document becomes
part of another separate document simply by reference as if the former is fully set
out in the latter.
Hofmeyer v. Iowa Dist. Court, 640 N.W.2d 225, 228 (Iowa
8
2001). “Where a writing refers to another document, that other document, or so
much of it as is referred to, is to be interpreted as part of the writing.”
Id.
(emphasis added). “[C]lear and specific reference is required to incorporate an
extrinsic document by reference.”
Id.
Whether material is incorporated by
reference presents a question of law. Id.
Seneca Waste points to the defendants‟ response to its request for
admissions. They responded “Admit” to the following request:
The Contractor Agreement attached as Exhibit A to Defendants‟
Answer incorporates the September 7, 2006 letter from Seneca
Waste Solutions, LLC to Michele Pancza, the “Budgetary T&M
Estimate Worksheet prepared for: Sheaffer Pen Plant Closure,” and
the “Vendor-Provided Sheaffer Closure Clean-Up Activities”
worksheets, all of which are part of the Agreement governing this
dispute.
We agree the contract agreement incorporates these documents. The
September 7, 2006 letter and attachments were wholly incorporated into this
contract.
As such, there is a genuine issue of material fact concerning the
amount that Seneca Waste is entitled to under the contract. This case is not ripe
for summary judgment. We therefore reverse the grant of summary judgment
and remand the case to the district court for further proceedings consistent with
this opinion.
REVERSED AND REMANDED.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.