Edwards v. IPUC
Annotate this Case
Samuel and Peggy Edwards, residents of Rexburg, Idaho, refused to allow PacifiCorp, doing business as Rocky Mountain Power Company, to install a smart electrical meter on their property due to health concerns. Rocky Mountain considered this refusal a violation of its terms of service, which required access to electrical meter bases. After negotiations failed, Rocky Mountain informed the Edwards that their electrical service would be terminated unless they allowed the installation. The Edwards filed a formal complaint with the Idaho Public Utilities Commission (PUC), arguing they had not denied access and should be allowed to opt-out of the smart meter installation.
The PUC consolidated the Edwards' complaint with similar complaints from other customers and granted Rocky Mountain's motion to dismiss, concluding that the Edwards had not provided evidence that smart meters presented a legitimate safety concern and that Rocky Mountain had the authority to access and replace meters. The Edwards' motion for reconsideration was also dismissed by the PUC, leading them to appeal to the Idaho Supreme Court.
The Idaho Supreme Court reviewed whether the PUC properly determined that Rocky Mountain had the authority to access the Edwards' property to replace the existing meter with a smart meter. The Court affirmed the PUC's decision, concluding that the tariff provisions allowed Rocky Mountain to access and replace meters. The Court also found that the Edwards' constitutional arguments were waived due to insufficient support and authority. The PUC's orders dismissing the Edwards' complaint and denying reconsideration were affirmed.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.