Maxum Indemnity Company v. Westfield Insurance Company et al, No. 2:2010cv00428 - Document 48 (S.D.W. Va. 2011)

Court Description: MEMORANDUM OPINION AND ORDER granting Westfield Insurance Company's 27 MOTION for Summary Judgment; granting Brickstreet Mutual Insurance Company's 25 MOTION for Summary Judgment; denying as moot Brickstreet Mutual Insurance Company 's 6 MOTION to Dismiss; denying Maxum Indemnity Company's 29 , 31 and 33 MOTIONS for Summary Judgment; this case is dismissed and stricken from the docket of the court. Signed by Judge John T. Copenhaver, Jr. on 1/25/2011. (cc: attys; any unrepresented party) (tmh)

Download PDF
Maxum Indemnity Company v. Westfield Insurance Company et al Doc. 48 UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF WEST VIRGINIA AT CHARLESTON MAXUM INDEMNITY COMPANY, Plaintiff, v. CASE NO. 2:10-cv-00428 WESTFIELD INSURANCE COMPANY, and BRICKSTREET MUTUAL INSURANCE COMPANY, Defendants. MEMORANDUM OPINION AND ORDER Pending are Brickstreet Mutual Insurance Company’s motion to dismiss, filed April 30, 2010, and the parties’ cross motions for summary judgment, each filed October 25, 2010.1 I. This action arises from the death of Richard Patrick, 1 Plaintiff filed three separate motions for summary judgment, each purporting to address a different issue, along with supporting memoranda collectively totaling fifty-one pages. Plaintiff may well have intended to present what it believed to be segregable issues in an efficient manner rather than to circumvent the page limitation set forth in Local Rule of Civil Procedure 7.1(a). Nevertheless, plaintiff’s motions are at least partially duplicative and have resulted in unnecessary proliferation of filings and needless extra work for both defendants and the court. Inasmuch as the motions pertain to the same overarching issue, namely, whether plaintiff is entitled to summary judgment on its claim for declaratory relief and equitable contribution, plaintiff should have presented a single motion and, absent relief by court order, abided by Rule 7.1(a)’s page limitation. Dockets.Justia.com who was accidentally killed on March 16, 2009, while working for a general contractor at a construction project in Charleston, West Virginia. Following his death, Patrick’s estate threatened to file a tort action against, among others, the general contractor and a subcontractor involved in the construction project. Maxum Indemnity Company (“Maxum”), which had issued a commercial general liability insurance policy to the subcontractor, settled with the decedent’s estate, securing a full release of all claims arising from the incident, including any claims against the general contractor. Maxum now seeks an order declaring that the subcontractor owed no duty to indemnify the general contractor for claims arising from the incident. Maxum further seeks equitable contribution from the general contractor’s insurers, defendants Westfield Insurance Company (“Westfield”) and Brickstreet Mutual Insurance Company (“Brickstreet”). In the factual discussion that follows, the court will examine (1) the relevant contract and insurance policy provisions, (2) the accident causing Patrick’s death, and (3) Maxum’s settlement with Patrick’s estate.2 2 The facts spelled out herein are drawn in large part from the parties’ Stipulation of Facts and Controlling Legal Issues, filed on September 23, 2010. 2 A. The Relevant Contract and Insurance Policy Provisions In July 2007, KM Associates, LLC (“KM Associates”), the owner and manager of the Shops at Kanawha, a shopping center in Charleston, entered into a Construction Management Services Agreement with CTC Enterprise Ventures Corporation (“CTC Enterprise”). (Stipulation of Facts ¶ 4). Pursuant to the agreement, CTC Enterprise was to serve as construction manager for a major renovation project at the shopping center, overseeing the project’s design, bidding, and construction phases. (Construction Management Services Agreement at 1-2, attached as Ex. 4 to Compl.). On December 30, 2008, KM Associates awarded the general construction contract to Agsten Construction Company, Inc. (“Agsten”). (Stipulation of Facts ¶ 5). Agsten held a commercial general liability policy issued by defendant Westfield, an insurance company with its principal place of business in Ohio, and a workers’ compensation and employers’ liability policy issued by defendant Brickstreet, an insurance company with its principal place of business in West Virginia. (Id. ¶ 3). On March 3, 2009, Agsten entered into a subcontract (the “Subcontract”) with Kanawha Valley Construction and Erection 3 Company (“Kanawha Valley”), pursuant to which Kanawha Valley agreed to furnish supervision, labor, and equipment for erecting all structural steel at the construction project. at 3, attached as Ex. 6 to Compl.). (Subcontract The Subcontract required, inter alia, that Kanawha Valley indemnify and hold harmless KM Associates, CTC Enterprise, and Agsten from and against all claims arising from Kanawha Valley’s performance of the subcontract. (Id. § 4.6.1). Specifically, the Subcontract’s indemnification clause provided pertinently as follows: To the fullest extent permitted by law, the Subcontractor shall indemnify and hold harmless the Owner, Contractor, Architect, Architect’s consultants, and agents and employees of any of them from and against claims, damages, losses and expenses, including but not limited to attorney’s fees, arising out of or resulting from performance of the Subcontractor’s Work under this Subcontract, provided that any such claim, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property . . ., but only to the extent caused by the negligent acts or omissions of the Subcontractor, the Subcontractor’s Sub-subcontractors, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, regardless of whether or not such claim, damage, loss or expense is caused in part by a party indemnified hereunder. (Id.). The Subcontract also required Kanawha Valley to purchase and maintain a commercial general liability insurance policy, with KM Associates, CTC Enterprise, and Agsten named as “additional insureds” for claims “caused in whole or in part by [Kanawha Valley’s] negligent acts or omissions during [Kanawha 4 Valley’s] operations.” (Id. ¶¶ 13.1, 13.4). Consistent with its obligations under the Subcontract, Kanawha Valley obtained a commercial general liability insurance policy from Maxum (the “Maxum Policy” or “Policy”), an insurance company with its principal place of business in Georgia. (Stipulation of Facts ¶ 1). The Maxum Policy, which contained a $1 million per-occurrence limit and $5 million in aggregate coverage, provided that Maxum “will pay those sums that the Insured becomes legally obligated to pay as ‘damages’ because of ‘bodily injury’ or ‘property damage’ to which this insurance applies.” (Maxum Policy at 1). The Policy defines the “Insured” as Kanawha Valley, its executive officers and directors, and its stockholders. It further states in an amendment that an “additional insured” is [a]ny person or organization for whom you [Kanawha Valley] are performing operations when you and such person or organization have agreed in writing in a contract or agreement prior to the date of loss that such person or organization be added as an additional insured on your policy. (Compl. Ex. 1 at 40). The Maxum Policy excludes from coverage “‘[b]odily injury’ or ‘property damage’ for which the Insured is obligated to pay ‘damages’ by reason of the assumption of liability in a 5 contract or agreement.” (Maxum Policy at 1). The Policy then excepts from this exclusion “liability for ‘damages’ . . . [a]ssumed in a contract or agreement that is an ‘insured contract.’” (Id.). It defines an “insured contract” as, among other things, [t]hat part of any other contract or agreement pertaining to your [Kanawha Valley’s] business . . . under which you assume the tort liability of another party to pay for “bodily injury” or “property damage” to a third person or organization. Tort liability means a liability that would be imposed by law in the absence of any contract or agreement. (Id. at 15). B. The Accident On March 16, 2009, Richard Patrick, an Agsten employee, was working at the Shops of Kanawha construction site when he was fatally injured. (Stipulation of Facts ¶ 16). The U.S. Department of Labor’s Occupation Safety and Health Administration (“OSHA”), which conducted a subsequent investigation, described the incident as follows: [Patrick] was drilling anchor bolt holes for new metal clip welded to the column. [Kanawha Valley] was installing metal bar joist adjacent to the column. A rough terrain forklift equipped with jib was used to lift the bar joist. While the fourth bar joist was being erected the 1 inch wide 8 foot long synthetic web sling was cut into by the top flange of the bar joist allowing the end of the 530 pound bar joist to fall striking [Patrick] on the head. 6 (OSHA Inspection Report at 4, attached as Ex. 7 to Compl.). On April 28, 2009, OSHA issued a Citation and Notification of Penalty to Agsten, finding that Agsten had committed a number of “serious” violations of OSHA’s Safety and Health Regulations for Construction. For example, OSHA found that Agsten “did not instruct [Patrick] to stay clear of loads being lifted while working in near proximity to the erection of steel members.” (Citation & Notification of Penalty at 7, attached as Ex. 8 to Compl.). Agsten subsequently entered into an Informal Settlement Agreement with OSHA, agreeing to pay a $1,875 penalty for its violations. Compl.). (Settlement Agreement at 2, attached as Ex. 10 to OSHA also issued a Citation and Notice of Penalty to Kanawha Valley, finding that it likewise violated the safety regulations governing construction sites. (Stipulation of Facts ¶ 19). C. Maxum’s Settlement and Suit for Declaratory Judgment By letter dated August 28, 2009, counsel for the estate of Richard Patrick formally advised KM Associates, CTC Enterprise, Agsten, and Kanawha Valley that the estate intended to assert a tort action against these entities for their roles in the accident. Compl.). (Letter from Estate at 2, attached as Ex. 12 to Attached to the letter was a copy of the estate’s draft 7 complaint (the “Draft Complaint”), which asserted four counts against the various entities. Count I of the Draft Complaint alleged that Kanawha Valley, inter alia, negligently exposed Patrick to the falling bar joist and negligently failed to remove the defective web sling from service. (Id. at 7-8). In Count II of the Draft Complaint, the estate asserted a so-called “deliberate intent” claim against Agsten under West Virginia Code § 23-4-2(d)(2)(ii). (Id. at 8-9). Specifically, the estate alleged that Agsten “intentionally directed and/or required [Patrick] to drill anchor bolts in an area where steel bar joists in excess of 500 pounds were being lifted overhead[,] thereby creating an unsafe working condition.” (Id. at 8). The estate further alleged in Count II of the Draft Complaint that such working conditions violated state and federal safety regulations and that Agsten, despite having “a subjective realization and appreciation” of the risks, intentionally exposed Patrick to the unsafe working conditions. (Id.). Count III of the Draft Complaint alleged negligence on behalf of KM Associates and CTC Enterprise, while Count IV sought punitive damages against Kanawha Valley and Agsten. (Id. at 9-10). In October 2009, KM Associates, CTC Enterprise, and Agsten tendered their defense and indemnification to Kanawha 8 Valley’s insurer, Maxum. (Stipulation of Facts ¶ 29). By letter dated October 27, 2009, Kanawha Valley requested that Maxum settle all claims arising from Patrick’s death. (Kanawha Valley Settlement Letter at 3-4, attached as Ex. 16 to Compl.). According to Kanawha Valley, the indemnification clause in the Subcontract clearly required that Kanawha Valley indemnify KM Associates, CTC Enterprise, and Agsten. (Id. at 3). And, because the Subcontract was an “insured contract,” Kanawha Valley’s duty to indemnify Agsten was, according to Kanawha Valley, covered under the Maxum Policy. (Id.). Finally, Kanawha Valley maintained that coverage was also available to KM Associates, CTC Enterprise, and Agsten as “additional insureds” under the Policy. (Id.). On January 7, 2010, Maxum entered into a Release and Settlement Agreement with Patrick’s estate, paying $750,000 to fully settle all claims arising from the construction accident. (Release & Settlement Agreement at 2, attached as Ex. 20 to Compl.). Patrick’s estate agreed to release and discharge Kanawha Valley, KM Associates, CTC Enterprise, and Agsten, as well as each entity’s employees and agents, from all claims arising from Patrick’s death. (Id.). The settlement agreement did not resolve the relative fault of the four entities, nor did 9 it determine whether Kanawha Valley was obligated to indemnify the others or whether Maxum was entitled to contribution. On April 1, 2010, Maxum instituted this action against Westfield and Brickstreet, seeking declaratory relief and equitable contribution. Specifically, Maxum seeks a declaration that (1) the Subcontract between Agsten and Kanawha Valley does not require that Kanawha Valley indemnify Agsten, and (2) the Maxum Policy does not provide coverage for the claims asserted against Agsten. With respect to its claim for equitable contribution, Maxum claims that, inasmuch as Kanawha Valley was not required to indemnify Agsten, and inasmuch further as Agsten was not otherwise covered under the Policy, Agsten’s insurers, defendants Westfield and Brickstreet, must reimburse Maxum for their share of the sums Maxum paid in settlement of the underlying tort action. As mentioned, each of the parties now moves for summary judgment.3 II. A party is entitled to summary judgment “if the pleadings, the discovery and disclosure materials on file, and 3 Inasmuch as the parties are completely diverse and the amount in controversy exceeds $75,000, the court possesses diversity jurisdiction pursuant to 28 U.S.C. § 1332(a). 10 any affidavits show that there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(c). Material facts are those necessary to establish the elements of a party’s cause of action. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). In assessing a motion for summary judgment, a court must neither resolve disputed facts nor weigh the evidence, Russell v. Microdyne Corp., 65 F.3d 1229, 1239 (4th Cir. 1995), nor may it make determinations of credibility. Murphy, 797 F.2d 179, 182 (4th Cir. 1986). Sosebee v. Rather, the party opposing the motion is entitled to have his or her version of the facts accepted as true and, moreover, to have all internal conflicts resolved in his or her favor. Charbonnages de France v. Smith, 597 F.2d 406, 414 (4th Cir. 1979). Inferences that are “drawn from the underlying facts . . . must be viewed in the light most favorable to the party opposing the motion.” United States v. Diebold, Inc., 369 U.S. 654, 655 (1962). Regarding contract cases specifically, our court of appeals has observed the matter of “interpretation is a subject particularly suited for summary judgment.” Bank of Montreal v. Signet Bank, 193 F.3d 818, 835 (4th Cir. 1999). If “the contract is unambiguous on the dispositive issue,” or if extrinsic 11 evidence definitively resolves the interpretative issue concerning an ambiguous contract, summary judgment is appropriate. Goodman v. Resolution Trust Corp., 7 F.3d 1123, 1126 (4th Cir. 1993). However, “an ambiguous contract that cannot be resolved by credible, unambiguous, extrinsic evidence discloses genuine issues of material fact,” rendering summary judgment “inappropriate.” Sempione v. Provident Bank, 75 F.3d 951, 959 (4th Cir. 1996). III. A. Whether the Subcontract Required Indemnification The parties’ primary dispute in this matter concerns the scope of the Subcontract’s indemnification provision. Specifically, the parties disagree over whether that provision required Kanawha Valley to indemnify Agsten for the “deliberate intent” claim asserted by Patrick’s estate pursuant to West Virginia Code § 23-4-2(d)(2)(ii). See infra note 5 (discussing the two types of deliberate intent claims). Defendants Westfield and Brickstreet contend that the Subcontract’s plain and unambiguous language required indemnification for all claims arising from the construction incident, whereas Maxum maintains that the Subcontract’s indemnification clause encompasses only 12 those claims arising from Agsten’s negligent conduct. In resolving this dispute, the court must first assess the Subcontract’s terms and, if clear and unambiguous, apply them as intended by the parties. 638, 648 (W. Va. 2010). See Benson v. AJR, Inc., 698 S.E.2d As mentioned, the indemnification clause provides pertinently as follows: To the fullest extent permitted by law, the Subcontractor shall indemnify and hold harmless the Owner, Contractor, Architect, Architect’s consultants, and agents and employees of any of them from and against claims, damages, losses and expenses . . . arising out of or resulting from performance of the Subcontractor’s Work under this Subcontract, provided that any such claim, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property . . ., but only to the extent caused by the negligent acts or omissions of the Subcontractor, the Subcontractor’s Sub-subcontractors, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, regardless of whether or not such claim, damage, loss or expense is caused in part by a party indemnified hereunder. (Subcontract § 4.6.1). Stated more succinctly and as relevant to this matter, the provision mandates that Kanawha Valley indemnify Agsten from any claim arising out of bodily injury or death caused, in whole or in part, by Kanawha Valley’s negligent acts or omissions in performing the Subcontract, whether or not Agsten was also partially responsible for the claim. The indemnification provision’s language is plain and 13 unambiguous, and applying that provision in this case demonstrates that Kanawha Valley was required to indemnify Agsten from the kind of deliberate intent claim asserted by Patrick’s estate. Neither party disputes that Patrick’s death resulted in part from Kanawha Valley’s negligence in employing a defective sling at the construction project. Inasmuch as Kanawha Valley’s negligent acts partially caused Patrick’s death, the Subcontract required Kanawha Valley to indemnify Agsten from any claims resulting therefrom. Whether or not Agsten also contributed to Patrick’s death, through its negligent conduct or otherwise, is simply irrelevant. The lone condition precedent to Kanawha Valley’s indemnification obligation was that a claim arise from bodily injury or death resulting from Kanawha Valley’s negligence. Inasmuch as that condition was satisfied here, Kanawha Valley squarely owed an obligation to indemnify Agsten. Notwithstanding this plain language, Maxum asserts that Kanawha Valley owed no duty to indemnify Agsten for the “deliberate intent” claim. Maxum raises two contentions to support its reading of the Subcontract. First, it contends that Kanawha Valley was not required to indemnify Agsten because the Subcontract did not “clearly and definitely show an intention to indemnify against” claims alleging more than mere negligence. 14 In other words, inasmuch as the Subcontract did not specify that Kanawha Valley owed a duty to indemnify Agsten for claims of “deliberate intent,” Maxum asserts that Kanawha Valley owed no such duty. To support its contention in this regard, Maxum emphasizes the long-standing rule in West Virginia that a contract attempting “to relieve a party from liability for his own negligence . . . must be clear and definite.” Bowlby-Harman Lumber Co. v. Commodore Servs., 144 W. Va. 239, 107 S.E.2d 602, 607 (1959). From this rule, Maxum concludes that “logically the requirements for indemnification of a party for his acts of ‘deliberate intent’ must certainly be heightened.” (Mem. Supp. Maxum’s Mot. Summ. J. at 13). Maxum’s contention is unpersuasive. To begin with, Maxum’s reliance on the “clear and definite” rule announced in Bowlby-Harman is misplaced. As subsequently explained by the Supreme Court of Appeals of West Virginia, the requirement that indemnity agreements contain clear and definite language resulted from so-called “sole negligence” indemnity agreements, pursuant to which an indemnitor is obliged to indemnify an indemnitee, even if the indemnitee was one hundred percent at fault for the underlying claim. See Dalton v. Childress Serv. Corp., 189 W. Va. 428, 432 S.E.2d 98, 101 (1993). 15 The “clear and definite” rule alleviates the risk of the indemnitor not securing an appropriate insurance fund by putting the indemnitor on notice that it is responsible for the indemnitee’s sole negligence, thereby encouraging the indemnitor to secure adequate insurance. Id. As mentioned, Kanawha Valley’s duty to indemnify was triggered only if Kanawha Valley was at least partially responsible for the underlying claim. The Subcontract thus does not attempt to indemnify Agsten for its sole negligence, rendering the “clear and definite” standard inapplicable here.4 Maxum next contends that, regardless of the Subcontract’s language, it would contravene public policy to require Kanawha Valley to indemnify Agsten for acts of “deliberate intent” under West Virginia Code § 23-4-2(d)(2)(ii). (Mem. Supp. Maxum’s Mot. Summ. J. at 15). Maxum correctly asserts that there is no “West Virginia case directly on point as to the right of indemnification for willful acts” and instead 4 Even assuming the “clear and definite” standard applies here, the Subcontract plainly alerted Kanawha Valley that it was obliged to indemnify Agsten for any claim arising in part from Kanawha Valley’s negligent conduct, whether or not Agsten was also responsible. See Marlin v. Wetzel Cnty. Bd. of Ed., 212 W. Va. 215, 569 S.E.2d 462 (2002) (concluding that an identical indmenity provision “clearly shifted legal responsibility for some measure of the plaintiff-workers’ alleged tort liability”). Kanawha Valley was thus expected to (and did) secure adequate insurance to cover such claims. 16 cites decisions from other jurisdictions for the proposition that “the majority of courts nationally do not permit indemnification for intentional or wanton misconduct.” (Id. at 17). Two principles of West Virginia law, however, lead this court to predict with confidence that requiring a party to indemnify for a deliberate intent claim of the variety asserted in the Draft Complaint does not offend West Virginia public policy.5 First, West Virginia law does not prohibit indemnification for fraudulent, reckless, or wanton misconduct. In Marlin v. Wetzel County Board of Education, 212 W. Va. 215, 569 S.E.2d 462 (2002), the Supreme Court of Appeals faced facts materially indistinguishable from the instant matter and 5 The court notes that West Virginia Code § 23-4-2(d) provides “two separate and distinct methods of proving ‘deliberate intention.’” Mayles v. Shoney’s, Inc., 185 W. Va. 88, 92, 405 S.E.2d 15, 19 (1990). First, an employee may establish a deliberate intent claim by proving that his employer “acted with a consciously, subjectively and deliberately formed intention to produce the specific result or injury or death to an employee.” W. Va. Code § 23-4-2(d)(2)(i). Alternatively, the employee may show deliberate intent by establishing, inter alia, that the employer intentionally exposed the employee to a specific unsafe working condition, despite the employer’s actual knowledge of the existence of the unsafe working condition and the high degree of risk and the strong probability of serious injury presented thereby. Id. § 23-4-2(d)(2)(ii). Inasmuch as Patrick’s estate asserted the latter type of deliberate intent claim, the court need not address and expresses no judgment as to whether West Virginia public policy prohibits indemnifying a party for damages resulting from the first type of deliberate intent claim. 17 concluded that a contract mandated indemnification. In that case, the Wetzel County Board of Education (the “Board”) had entered into a construction contract with a general contractor to renovate a local high school. Id. at 465. The contract between the Board and the contractor included an indemnification provision requiring the contractor to indemnify and hold harmless the Board from all claims arising from the contractor’s performance of the contract. Id. During the ensuing renovations, several of the contractor’s employees were exposed to asbestos dust. Id. at 466. Three years later, when the workers learned they had been exposed, they filed suit against the Board and the contractor, asserting that both were negligent in failing to warn the workers of the asbestos. Id. The workers also alleged that the defendants had “fraudulently, deceitfully and willfully, wantonly and recklessly concealed from the workers the fact that they were being exposed to unsafe levels of asbestos.” Id. Relying on its contract with the contractor, the Board demanded indemnification and, after the contractor’s insurer refused to provide coverage, filed a complaint for declaratory relief. In resolving the dispute, the court first explained that indemnification clauses are encouraged in West Virginia, 18 inasmuch as such agreements serve our goals of encouraging compromise and settlement by reducing settlement discussions to bilateral discussions, by encouraging adequate levels of insurance, and by allowing the parties to a contract to allocate among themselves the burden of defending claims. Id. at 468 (internal quotation marks omitted). The court then reviewed the indemnification clause and concluded that the provision “clearly shifted legal responsibility for some measure of the plaintiff-workers’ alleged tort liability from the Board to [the contractor.]” Id. at 469. The court reached this conclusion notwithstanding the fact that the plaintiffs had asserted claims alleging more than mere negligence. Indeed, the plaintiff-workers in that case alleged that the Board had fraudulently and recklessly concealed the fact that they had been exposed, conduct at least as culpable as that giving rise to the type of deliberate intent claim asserted by Patrick’s estate against Agsten. The court’s decision in Wetzel thus severely undermines Maxum’s contention that public policy precludes indemnification in this case. It is also noteworthy that West Virginia law does not prohibit an employer from insuring against the risk of liability arising under West Virginia Code § 23-4-2(d)(2)(ii). In Erie Insurance Property and Casualty Co. v. Stage Show Pizza, JTS, 19 Inc., 210 W. Va. 63, 553 S.E.2d 257 (2001), the Supreme Court of Appeals examined a particular “employers’ liability” insurance policy purchased by an employer and concluded that the policy provided coverage for a § 23-4-2(d)(2)(ii) deliberate intent claim asserted against the employer by one of its employees. Inasmuch as insurance is simply “a contract whereby one undertakes to indemnify another or to pay a specified amount upon determinable contingencies,” W. Va. Code § 33-1-1, the court’s holding in Stage Show Pizza suggests that West Virginia public policy does not preclude indemnification for damages arising from a § 23-4-2(d)(2)(ii) deliberate intent claim. In short, the Subcontract’s plain terms required Kanawha Valley to indemnify Agsten. Moreover, recent precedent of the Supreme Court of Appeals suggests that West Virginia public policy permits indemnification for a deliberate intent claim such as the one asserted by Patrick’s estate. Accordingly, this court concludes that Kanawha Valley was obliged to indemnify Agsten for any damages arising from the construction accident. B. Whether Maxum is Entitled to Reimbursement from Westfield and Brickstreet Under the Doctrine of Equitable Contribution Notwithstanding the indemnity provision, Maxum contends that it is entitled to reimbursement from Westfield and 20 Brickstreet pursuant to the doctrine of equitable contribution. Maxum maintains that it acted in the best interest of its insured, Kanawha Valley, when it settled with Patrick’s estate. To disallow reimbursement would, according to Maxum, “reward an insurance company who tried to dodge paying to settle claims on behalf of its insured and punish a company who tried to do the right thing.” (Maxum’s Reply Br. at 5). Equitable contribution is the right to recover from a co-obligor who shares liability for a loss with the party seeking contribution. See Exec. Risk Indem., Inc. v. Charleston Area Med. Ctr., Inc., 681 F. Supp. 2d 694, 708 (S.D. W. Va. 2009). With respect to insurance, the right to contribution arises when several insurers are obligated to indemnify or defend the same loss or claim, and one insurer has paid more than its share of the loss or defended action without any participation by the others. Id. Equitable contribution permits reimbursement to the insurer that paid more than its share on the theory that the debt it paid was equally and concurrently owed by the other insurers. Id. Maxum is not entitled to equitable contribution for the simple reason that the settlement funds it paid were not equally and concurrently owed by Westfield or Brickstreet. 21 Kanawha Valley, in consideration for being awarded the Subcontract, expressly agreed to indemnify Agsten for any claim or loss resulting from Kanawha Valley’s negligence in performing the Subcontract. Indeed, absent Kanawha Valley’s negligence, there would have been no accident and no claim or loss. Under the Subcontract then, Agsten was not accountable for any loss or injury occurring during construction activities undertaken by Kanawha Valley. Just as Kanawha Valley has no right of recovery against Agsten, Kanawha Valley’s insurer, Maxum, has no right to recover from Agsten’s insurers, Westfield and Brickstreet. To conclude otherwise would effectively negate the indemnity agreement and impose liability on Westfield and Brickstreet when their insured bargained to avoid that very result. Maxum calculated and accepted premiums from Kanawha Valley with full knowledge that, pursuant to the “insured contract” provision of the Maxum Policy, it might be called upon to satisfy a full judgment against Kanawha Valley and Agsten. Maxum cannot now rely on equitable principles to avoid an obligation plainly called for by both the Subcontract and the Maxum Policy.6 6 Although the West Virginia courts have not yet addressed the interplay between an indemnification agreement and the doctrine of equitable contribution, “most, if not all, jurisdictions to have faced the question of whether an indemnification agreement could relieve particular insurers of an obligation to pay . . . have answered in the affirmative.” St. 22 IV. Pursuant to the foregoing analysis, it is ORDERED as follows: 1. That Westfield’s motion for summary judgment be, and it hereby is, granted; 2. That Brickstreet’s motion for summary judgment be, and it hereby is, granted; 3. That Brickstreet’s motion to dismiss be, and it hereby is, denied as moot; 4. That each of Maxum’s motions for summary judgment be, and they hereby are, denied; and 5. That this case be dismissed and stricken from the docket of the court. Paul Fire Ins. v. Am. Intern. Spec. Lines, 365 F.3d 263, 272 (4th Cir. 2004); see also Am. Indem. Lloyds v. Travelers Prop., 335 F.3d 429, 436 (5th Cir. 2003) (“[T]he clear majority of jurisdictions . . . gives controlling effect to the indemnity obligation of one insured to the other insured over ‘other insurance’ or similar clauses in the policies of the insurers, particularly where one of the policies covers the indemnity obligation.”); 15 Couch on Insurance § 218:19, p. 218-25 (3d ed. 1999) (“In a variety of commercial relationships, such as . . . contractor-subcontractor, the contracts between the parties contain indemnification agreements in which one agrees to hold the other harmless for its own acts of negligence or that of its employees. Such contractual arrangements can nullify a right to contribution.”). 23 The Clerk is directed to forward copies of this written opinion and order to all counsel of record and any unrepresented parties. DATED: January 25, 2011 John T. Copenhaver, Jr. United States District Judge 24

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.