Kaseburg et al v. Port of Seattle et al, No. 2:2014cv00784 - Document 59 (W.D. Wash. 2014)

Court Description: ORDER denying Defendants' 36 Motion to Dismiss, by Judge John C Coughenour.(TM)

Download PDF
Kaseburg et al v. Port of Seattle et al Doc. 59 THE HONORABLE JOHN C. COUGHENOUR 1 2 3 4 5 6 UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT SEATTLE 7 8 9 SCOTT KASEBURG, et al., 10 Plaintiffs, 11 CASE NO. C14-0784-JCC ORDER DENYING DEFENDANTS MOTION TO DISMISS v. 12 PORT OF SEATTLE, et al., 13 Defendants. 14 This matter comes before the Court on Defendants Motion to Dismiss (Dkt. No. 36). 15 16 Having thoroughly considered the parties briefing and the relevant record, the Court finds oral 17 argument unnecessary and hereby DENIES the Motion for the reasons explained herein. 18 I. BACKGROUND 19 Plaintiffs, owners of Eastside property extending from Woodinville to Renton, seek to 20 quiet title and obtain declaratory relief in light of allegedly unlawful expansions of former 21 railway easements, following the easements “railbanking” under the Trails Act (16 U.S.C. § 22 1247(d)). 23 The parties agree that Burlington Northern Santa Fe Railway (BNSF), through its 24 predecessors, acquired easements on Plaintiffs land in the late 1800s and early 1900s. (Second 25 Amended Complaint, Dkt. No. 46 at ¶3; Motion to Dismiss, Dkt. No. 36 at 2.) In a 2012 26 decision by Judge Charles F. Lettow of the U.S. Court of Federal Claims, these same easements ORDER DENYING DEFENDANTS MOTION TO DISMISS PAGE - 1 Dockets.Justia.com 1 were determined to be surface easements for railroad purposes only. (Second Amended 2 Complaint, Dkt. No. 46 at ¶99 (citing Haggart v. United States, 108 Fed. Cl. 70, 80 (2012).) By 3 2008, BNSF no longer used these easements. (Motion to Dismiss, Dkt. No. 36 at 2.) 4 The Trails Act provides that railroad easements that have fallen into disuse by a railway, 5 and would thus otherwise revert to the fee simple owner under state law abandonment doctrines, 6 may instead be “railbanked” in a multiparty transfer governed by the Surface Transportation 7 Board. See 16 U.S.C. § 1247(d). In railbanking, the railway effectively abandons the easement, 8 but the federal Trails Act preempts state abandonment and reversion doctrines, and the railway is 9 allowed to transfer the easement to a state or local government that has agreed to maintain it for 10 interim recreational trail use. Id. The railway retains the right to reactivate the railroad easement 11 if, in the future, it reactivates rail service in that corridor. Id. 12 Pursuant to this railbanking process, on May 12, 2008, BNSF entered into a series of 13 agreements with the Port of Seattle (Port) and King County (County) to transfer the corridor via 14 quitclaim deed to the Port and to designate King County as the Interim Trail Manager. (Motion 15 to Dismiss, Dkt. No. 36 at 3.) In this transfer, BNSF made no representations or warranties 16 concerning title and specifically stated that “the Port and County acknowledge and affirm that 17 BNSF may not hold fee simple title to the Property, that BNSF s interest in all or part of the 18 Property, if any, may rise only to the level of an easement for railroad purposes . . . and the Port 19 and County are willing to accept the Property on this basis.” (Second Amended Complaint, Dkt. 20 No. 46 at ¶110 (citing the Donation Agreement, Dkt. No. 46, Ex. D).) In Haggart, the Federal 21 Claims case that analyzed the takings issue implicated by these easements, Judge Lettow found 22 that the Trails Act-enabled transfer of easements from BNSF to the Port granted the Port a 23 surface easement for recreational trail use with potential reactivation of a railroad right-of-way. 24 (Second Amended Complaint, Dkt. No. 46 at ¶99 (citing Haggart, 108 Fed. Cl. at 80).) 25 In alleged contravention of the axiom that one cannot transfer a greater property interest 26 than one holds, the Port, along with King County, assigned some of these recreational trail use ORDER DENYING DEFENDANTS MOTION TO DISMISS PAGE - 2 1 surface rights, as well as subsurface and aerial rights (which the Port does not appear to have 2 possessed in the first place), to Defendant Central Puget Sound Regional Transit Authority 3 (Sound Transit) for public transportation purposes (the building of a High Capacity Transit 4 System), and also to Defendant Puget Sound Energy, Inc. (PSE), a private utility corporation, for 5 electricity distribution and utility delivery purposes. (Second Amended Complaint, Dkt. No. 46 6 at 47-49; Motion to Dismiss, Dkt. No. 36 at 7.) The fact and scope of these transfers are 7 undisputed by the parties. In these transfers, the Port made no warranty of title as to the Property 8 or Easement Agreement and specifically advised these parties that the Port “may not hold fee 9 simple title to the Property and that the Port s interest in all or part of the Property, if any, may 10 rise only to the level of an easement for railroad purposes.” (Second Amended Complaint, Dkt. 11 No. 46 at 49-50 (citing High Capacity Transportation Easement Agreement, Dkt. No. 46, Ex. 12 L).) Plaintiffs do not dispute that the Port and County possess surface easements on Plaintiffs 13 14 parcels, for recreational trail use. However, Plaintiffs do object to these allegedly scope15 exceeding transfers of the subsurface and aerial rights under and above these surface easements, 16 as well as the easements imminent use in public transportation and energy transmission 17 ventures, rather than for recreational trails. Plaintiffs seek to quiet title in their favor to these 18 non-recreational trail use surface rights and aerial and subsurface rights to which PSE, Sound 19 Transit, and the Port now lay claim. Plaintiffs seek declaratory relief confirming that they 20 maintain the fee simple estates underlying the easements. (Second Amended Complaint, Dkt. 21 No. 46 at 51-54). Defendant King County has filed the instant Motion to Dismiss (Dkt. No. 36), 22 which Defendant Port of Seattle has joined (see Dkt. No. 39). 23 II. DISCUSSION 24 A. 25 Pursuant to Federal Rule of Civil Procedure 12(c), “[a]fter the pleadings are closed – but Legal Standard 26 ORDER DENYING DEFENDANTS MOTION TO DISMISS PAGE - 3 1 early enough not to delay trial – a party may move for judgment on the pleadings.”1 To grant a 2 motion for judgment on the pleadings, the court must conclude that the moving party is entitled 3 to judgment as a matter of law, even after accepting all factual allegations in the complaint as 4 true and construing them in the light most favorable to the nonmoving party. Fleming v. 5 Pickard, 581 F.3d 922, 925 (9th Cir. 2009). There must be no genuine issues of material fact in 6 dispute. Id. 7 However, to survive a motion to dismiss or a motion for judgment on the pleadings, a 8 plaintiff must cite facts supporting a “plausible” cause of action. Bell Atlantic Corp. v. Twombly, 9 550 U.S. 544, 555-56 (2007). Defendants’ Direct Critiques of Plaintiffs’ Complaint 10 B. 11 This Court does not see how, even crediting the allegations of and making inferences in 12 the light most favorable to the moving party, Defendants arguments could establish that they 13 were entitled to judgment as a matter of law. Defendants spend the majority of their Motion 14 creating and attacking the straw man issues of abandonment and the current state of the railroad 15 easement. In doing so, they misconstrue Plaintiffs position. 16 First, although Defendants may be correct that at times, Plaintiffs incorrectly refer to 17 BNSF as having “abandoned” the rail corridor, the Court recognizes this to be more of a 18 rhetorical precision issue than a legal mischaracterization of the technical aspects of the 19 railbanking process. In the everyday sense of the word, BNSF did “abandon” its right of way. 20 But, in the portions of their briefing in which Plaintiffs actually describe the technical aspects of 21 the railbanking process, they completely concede that the Trails Act preempts abandonment qua 22 abandonment triggering reversion under state law. Whether “abandonment” has occurred is 23 24 1 That Defendants entitle their Motion a motion to dismiss but include authorities pertaining to a 25 motion for judgment on the pleadings is not problematic as these two motions are “functionally identical[;] the same standard of review applicable to a Rule 12(b) motion applies to its Rule 26 12(c) analog.” Dworkin v. Hustler Magazine, Inc., 867 F. 2d 1188, 1192 (9th Cir. 1989). ORDER DENYING DEFENDANTS MOTION TO DISMISS PAGE - 4 1 irrelevant2 because Plaintiffs are not, as Defendants seem to imply, taking the extreme position 2 that the Trails Act is preempted by state law such that BNSF s functional abandonment of the 3 right of way should have caused the easements to revert. Second, Defendants make much of Plaintiffs statements that the railway easement “no 4 5 longer exists.” (See e.g., Plaintiffs Brief in Opposition, Dkt. No. 48 at 13.) This is another 6 straw man, rhetorically-focused argument that, again, would be relevant only if Plaintiffs were 7 arguing that the full easement ought have reverted to them. Instead, Plaintiffs argue, and are 8 supported by federal and state law precedent in doing so, that the present easements burdening 9 their land are surface easements for recreational trail use.3 These trail use easements replaced 10 the railway easements, pursuant to the Trails Act.4,5 Thus, Plaintiffs argue, the Port did not have 11 the power to convey surface and subsurface and aerial easements for electricity transmission 12 and mass transit purposes to PSE and Sound Transit.6 13 14 15 16 17 18 19 20 21 22 23 24 25 26 2 See Ybanez v. United States, 102 Fed. Cl. 82, 87 (2011) (“Where the scope of a new easement exceeds the original grant, a determination of whether abandonment occurs is unnecessary.”) (citing Preseault v. United States (Preseault II), 100 F.3d 1525, 1533 (Fed. Cir. 1996) and Toews v. United States, 376 F.3d 1371, 1381 (Fed. Cir. 2004)). 3 See, e.g. Plaintiffs Brief in Opposition, Dkt. No. 48 at 16 (stating, in reference to Lawson v. Washington, 730 P.2d 1308 (Wash. 1986), that “[t]he blocking of abandonment pursuant to the Trails Act prevented the vesting of Plaintiffs reversionary interest, consisting of Plaintiffs rights in the surface only, and authorized the placement of an easement for recreational trail use with the potential reactivation of a railroad.”); id. at 30 (“Plaintiffs assert that [recreational, surface-limited] trail use is entirely appropriate and authorized by the Trails Act. . . Plaintiffs assert and agree that the former right-of-way is legally railbanked . . . Plaintiffs lawsuit has nothing to do with any claim that railbanking is not authorized or appropriate.”). 4 See Plaintiffs Brief in Opposition, Dkt. No. 48 at 17 (“The railroad purpose easement is converted to a new easement upon the Plaintiffs land.”). 5 At times, Defendants themselves seem to concede this description: the “combination of retaining the existing railroad easement and adding the right to use the property for trail use is sometimes shorthanded in takings decisions as a „conversion of the prior easement, or even as the creation of a new easement.” (Defendants Reply in Support of Motion to Dismiss, Dkt. No. 51 at 6 (emphasis added).) 6 See Plaintiffs Brief in Opposition, Dkt. No. 48 at 23-24 (“Because the railroad only held a surface easement and could only transfer what it owned to the Defendant Trail Users, the Defendant Trail Users only own a trail/railbanked easement and Plaintiffs continue to own the underlying fee including the subsurface and aerial rights in the trail/railbanked easement.”). ORDER DENYING DEFENDANTS MOTION TO DISMISS PAGE - 5 1 In sum, Defendants direct Rule 12(c) attacks on Plaintiffs Complaint fail because 2 Plaintiffs simply do not dispute the validity of the recreational trail use surface easements on 3 their parcels.7 Given their lack of arguments on the topic, nothing in the Defendants Motion or 4 Reply would allow the Court to conclude that Defendants were entitled to judgment as a matter 5 of law on the central issue of whether the Port lacked the power to grant PSE and Sound Transit 6 the easements they now claim. 8,9 7 C. Preemption Arguments 8 Defendants raise three preemption arguments they claim compel this Court to dismiss 9 Plaintiffs case. 10 First, Defendants state that Plaintiffs are barred from collaterally attacking the STB s 11 NITU order approving BNSF s transfer of the easement to the Port. Defendants allege that 12 Plaintiffs “seek to effectively undo the STB s work and cause an abandonment of the railroad 13 easement” and that this Court, as a “District Court[,] lack[s] jurisdiction to review an STB 14 15 Defendants themselves concede that the “property rights formerly held by BNSF in the South Rail Corridor were transferred by Quit Claim deed to the Port.” (Motion to Dismiss, Dkt. No. 36 16 at 6.) 7 See e.g., Second Amended Complaint, Dkt. No. 46 at ¶¶121, 134, 138, 141 (relief sought does 17 not include exclusive surface possession). 8 18 The only arguments Defendants make regarding the central issue of whether the Port was in a position to grant these subsurface/aerial and non-recreational trail use rights to PSE and Sound 19 Energy consist of citing dicta from 150-year-old cases explaining that railway easements are “robust” and “very substantial thing[s]” that may include subsurface and aerial rights incidental 20 to rail use. (See Motion to Dismiss, Dkt. No. 36 at 13.) Furthermore, these pre-Trails Acts dicta say nothing about the “robustness” and inherent scope of a former railway easement that is now a 21 recreational trail easement no longer in the hands of the railroad. 9 22 For the authorities supporting Plaintiffs legal positions, see Preseault v. Interstate Commerce Comm’n (Preseault I), 494 U.S. 1 (1990) (holding that Rails to Trails conversions giving rise to 23 just compensation claims are clearly authorized by the Trails Act and that railbanking is not a railroad purpose); Preseault II, 100 F.3d 1525 (holding in a Trails Act case that state property 24 laws dictate the nature of the property held by a railroad, and holding that the trail use easement 25 acquired by similarly situated defendants did not receive the incidental use benefits the predecessor railroad had held); Lawson, 730 P.2d 1308 (holding that “when an easement is 26 granted to a railroad through a private conveyance, the easement is not a perpetual public easement”). ORDER DENYING DEFENDANTS MOTION TO DISMISS PAGE - 6 1 order.” (Motion to Dismiss, Dkt. No. 36 at 16.) Again, Defendants thoroughly mischaracterize 2 Plaintiffs position. Plaintiffs do not challenge the STB s authority to preside over the transfer of 3 BNSF s railway easement to the Port, in the form of a surface easement for recreational trail use, 4 nor challenge the transfer itself. Instead, they dispute that the Port lacked authority to then grant 5 larger easements than it had received received to PSE and Sound Transit.10 That the STB s 6 blessing of the original, Trails Act-compliant transfer to the Port somehow gave the Port absolute 7 immunity when assigning property rights that it never had in the first place, is not a compelling 8 argument to this Court. 9 Second, Defendants argue that any state law remedies that would cause an abandonment 10 of the rail corridor are pre-empted by the ICCTA, the Trails Act, and associated federal 11 regulations. (Motion to Dismiss, Dkt. No. 36 at 17.) This preemption argument misses the 12 mark, at the point that Plaintiffs are not arguing that BNSF abandoned the railway corridor, in 13 the technical sense of an abandonment that would trigger reversion under state law. See Section 14 II(B), supra. 15 Third, Defendants argue that any abandonment of the corridor lies within the exclusive 16 jurisdiction of the STB, and is outside this Court s jurisdiction. (Motion to Dismiss, Dkt. No. 36 17 at 20.) This argument is similarly inapposite. That the “STB has exclusive plenary authority 18 over freight rail operations in interstate commerce under the ICCTA” (id.) hardly mandates the 19 conclusion that no federal court may ever touch a suit in which the STB once played a role in the 20 underlying events. Plaintiffs are not suing the STB, nor are they questioning the STB s well21 established authority to preside over and approve transformations of railway easements into 22 recreational trail use easements under the Trails Act. Defendants cannot seriously suggest that 23 the fact that the STB supervised that original transfer means that any suit related to the resultant 24 recreational trail easement, whether sounding in tort, contract, property law, or even criminal 25 26 10 See footnote 3, supra. ORDER DENYING DEFENDANTS MOTION TO DISMISS PAGE - 7 1 law, must be reserved for the extra-Article III review of the Surface Transportation Board. 2 III. CONCLUSION 3 For the foregoing reasons, Defendants Motion to Dismiss (Dkt. No. 36) is DENIED. 4 DATED this 5th day of December 2014. 5 6 7 A 8 9 10 John C. Coughenour UNITED STATES DISTRICT JUDGE 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 ORDER DENYING DEFENDANTS MOTION TO DISMISS PAGE - 8

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.