-MD UNITED STATES OF AMERICA v. DICK CORPORATION ET AL, No. 3:2008cv00056 - Document 675 (N.D. Fla. 2010)

Court Description: ORDER denying the 539 Motion for Summary Judgment filed by UNITED STATES OF AMERICA, for the use and benefit of JAMES B. DONAGHEY, INC. Signed by District Judge M CASEY RODGERS on 11/9/2010. (djb)

Download PDF
-MD UNITED STATES OF AMERICA v. DICK CORPORATION ET AL Doc. 675 Page 1 of 10 IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF FLORIDA PENSACOLA DIVISION UNITED STATES OF AMERICA, for the use and benefit of JAMES B. DONAGHEY, INC. Plaintiff, v. Case No. 3:08cv56/MCR/MD (Lead Case/Consolidated) DICK CORPORATION, et al., Defendants. __________________________________/ ORDER This matter is part of a consolidated action stemming from the construction of four buildings at the Pensacola Naval Air Station. The plaintiff, United States of America, for the use and benefit of James B. Donaghey, Inc. (“Donaghey”), filed suit against Dick Corporation (“Dick”) (doc. 27), the general contractor on the project, asserting claims under the Miller Act and Prompt Payment Act, as well as for breach of contract, unjust enrichment, negligence, and quantum meruit, in connection with work Donaghey performed on the project.1 Dick asserted a counterclaim against Donaghey (doc. 166) seeking to recover liquidated damages as a result of alleged work delays.2 Pending before the court is Donaghey’s motion for summary judgment (doc. 539), to which Dick has responded in opposition (doc. 564). The court, having fully considered the record and the parties’ 1 In response to Donaghey’s first am ended com plaint, Dick filed a m otion to dism iss Donaghey’s breach of contract, unjust enrichm ent, negligence, quantum m eruit, and Prom pt Paym ent Act claim s. Donaghey did not oppose dism issal of its unjust enrichm ent and negligence claim s. By order entered April 27, 2009, the Court dism issed the unjust enrichm ent, negligence, and Prom pt Paym ent Act claim s. 2 In its counterclaim , Dick also alleges that Donaghey’s breached the subcontract by perform ing defective work, failing to install work in accordance with the subcontract, procuring incorrect equipm ent, failing to provide adequate m anpower, and failing to perform warranty work. Based on its response to Donaghey’s m otion, however, it appears that Dick intends to pursue only its claim regarding work delays. Dockets.Justia.com Page 2 of 10 arguments, concludes that Donaghey’s motion should be denied. BACKGROUND Dick entered into a contract with the United States of America Naval Facilities Engineering Command (“Navy”) to design and build four buildings at the Pensacola Naval Air Station.3 In accordance with 40 U.S.C. § 3131, Dick secured a payment bond on the project in the amount of $79,017,192. Dick thereafter entered into a number of subcontracts for performance of various aspects of the work, including a subcontract with Donaghey for installation of the plumbing and HVAC systems.4 As required by the subcontract, Donaghey submitted monthly pay applications for the work performed; Dick was to pay Donaghey within ten days of the Navy’s payment to Dick. Although Donaghey alleges that numerous payments were late, it does not dispute that Dick paid all amounts due under the subcontract until October 2007, when Dick began withholding payments as a result of Donaghey’s alleged work delays. In all, Dick withheld $748,690.40 from Donaghey in payments and retainage under the subcontract.5 Donaghey filed this lawsuit seeking to recover that amount. Dick claims that it was justified in withholding the remaining payments because of extensive delays Donaghey caused at the end of the project when it was unable to provide the required test and balancing approvals (“T&B approvals”) on the Visitors Quarters, preventing the Navy from taking beneficial occupancy of the buildings. In order to obtain the T&B approvals, Donaghey had to make certain repairs and modifications, including drywall demolition to re-route and replace duct work. As a result of the additional work required by Donaghey, Dick had to remain on the site to provide supervision far longer than it had anticipated. In addition to delays in completion of the Visitors Quarters, Dick claims Donaghey performed its work behind schedule throughout the course of the project, delaying successor trades and the project as a whole, 3 In particular, Dick was to design and build Visitors Quarters, which consisted of two buildings; an Aviation Rescue Swim m ers School; and a Physical Fitness Center. 4 The am ount of Dick’s subcontract with Donaghey was $8,900,00. 5 Although Dick claim s it had a right under the subcontract to withhold paym ent from Donaghey, there is no provision in the subcontract expressly allowing Dick to withhold paym ent for work delays. Consolidated Case No.: 3:08cv56/MCR/MD Page 3 of 10 including substantial completion of the Aviation Rescue Swimmers School. In the event of delays to the substantial completion of the buildings, the parties agreed that Dick would be awarded liquidated damages in the amount of $5,400 per calendar day for the Aviation Rescue Swimmers School and $24,898 per calendar day for the Visitors Quarters. Dick filed a counterclaim seeking a total of $1,741,374 in liquidated damages – $1,568,574 as a result of 63 days of delay on the Visitors Quarters and $172,800 as a result of 32 days of delay on the Aviation Rescue Swimmers School. Donaghey seeks summary judgment as to its claims against Dick and Dick’s counterclaim against it. In support of its Miller Act and breach of contract claims, Donaghey argues that it is entitled to summary judgment as a matter of law because it completed its scope of work under the subcontract, as evidenced by the fact that the Navy accepted its work and did not withhold any payments from Dick under the prime contract. Insofar as Dick’s counterclaim is concerned, Donaghey urges the court to find the liquidated damages provision unenforceable, arguing that the liquidated damages provision was a “pass through” provision and that, because the Navy did not assess liquidated damages against Dick, Dick is not entitled to assess liquidated damages against Donaghey. Donaghey further argues that, due to extensions granted by the Navy, it timely completed its work, as a result of which there was no delay triggering the liquidated damages provision, or alternatively, that it caused at most a seven day delay in completion of the Visitors Quarters. Finally, Donaghey contends that the liquidated damages provision constitutes an unenforceable penalty that, even if valid, would be unconscionable to apply in this case given the amount of Dick’s actual damages.6 In response to Donaghey’s motion, Dick maintains that it was entitled to withhold payments as a result of Donaghey’s work delays and that the liquidated damages to which it is entitled exceed the amount Donaghey is seeking in damages under its claims. In support of its counterclaim, Dick points to the absence of “pass through” language in the liquidated damages provision and the fact that the subcontract, as a whole, and the liquidated damages provision, in 6 Dick determ ined that it incurred $1,621,499.22 in actual dam ages as a result of work delays caused by five subcontractors, including Donaghey. Dick attributes $548,221.42 of that am ount to Donaghey. Consolidated Case No.: 3:08cv56/MCR/MD Page 4 of 10 particular, were carefully negotiated between the parties because actual damages were not readily ascertainable at the time the subcontract was entered into. Although Dick acknowledges that the Navy granted extensions of time under the contract, it argues that those extensions did not pertain to Donaghey’s scope of work and, in any event, did not change the milestone completion dates. In the event the court finds the liquidated damages provision unenforceable, however, Dick argues that the court should invoke its equity powers and award it actual damages.7 For the reasons set forth below, the court finds the liquidated damages provision enforceable and that there are genuine issues of material fact with regard to Donaghey’s Miller Act and breach of contract claims, precluding the entry of summary judgment. DISCUSSION A. Summary Judgment Standard Summary judgment is appropriate where “the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(c). “[T]he plain language of Rule 56(c) mandates the entry of summary judgment, after adequate time for discovery and upon motion, against a party who fails to make a showing sufficient to establish the existence of an element essential to that party’s case, and on which that party will bear the burden of proof at trial.” Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). “[T]he mere existence of some alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment; the requirement is that there be no genuine issue of material fact.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). An issue of fact is “material” if it might affect the outcome of the case under the governing law, and it is “genuine” if the record taken as a whole could lead a rational fact finder to find for the non-moving party. Id. Summary judgment is not appropriate “if a reasonable fact finder evaluating the evidence could draw more than one inference from the facts, and if that inference introduces a 7 The liquidated dam ages provision includes a waiver of actual dam ages. Consolidated Case No.: 3:08cv56/MCR/MD Page 5 of 10 genuine issue of material fact.” Jeffery v. Sarasota White Sox, Inc., 64 F.3d 590, 594 (11th Cir. 1995). When assessing the sufficiency of the evidence, the court must view all the evidence, and all factual inferences reasonably drawn therefrom, in the light most favorable to the nonmoving party. See Hairston v. Gainesville Sun Publ’g Co., 9 F.3d 913, 918 (11th Cir. 1993). B. Donaghey’s Claims 1. Breach of Contract In order to prevail on its breach of contract claim, Donaghey must prove (1) there was a valid contract; (2) Dick breached the contract; and (3) Donaghey suffered damages as a result of Dick’s breach. See Rollins Inc. v. Butland, 951 So. 2d 860, 876 (Fla. 2d DCA 2006). Although the parties do not dispute there was a valid subcontract, they strongly dispute whether Dick breached the subcontract in withholding payments from Donaghey. Whether Dick breached the subcontract depends on whether Donaghey performed all of its obligations under the subcontract, including timely completion of its work. See Marshall Const., Ltd. v. Coastal Sheet Metal & Roofing, Inc., 569 So. 2d 845, 848 (Fla. 1st DCA 1990) (holding that, “in order to maintain an action for breach of contract, a claimant must first establish performance on its part of the contractual obligations imposed in the contract”). As both Donaghey’s motion and Dick’s response make plain, a genuine issue of material fact exists in that regard, as a result of which summary judgment must be denied as to this claim. 2. Miller Act The Miller Act requires a Government contractor to post a surety bond "for the protection of all persons supplying labor and material in carrying out the work provided for in the contract for the use of each person." 40 U.S.C. 3131(b)(2). Under the statute, a subcontractor who has not been paid within 90 days after the day on which it did or performed the last of the labor . . . for which claim is made may bring a civil action on the payment bond for the amount unpaid at the time the civil action is brought and may prosecute the action to final execution and judgment for the amount due." 40 U.S.C. § 3133(b)(1). To establish a prima facie case under the Miller Act, a plaintiff must prove Consolidated Case No.: 3:08cv56/MCR/MD Page 6 of 10 (1) that materials and/or labor were supplied in carrying out the work provided for in the contract; (2) that the supplier has not been paid; (3) that the supplier had a good faith belief that the materials and/or labor were for the specified work; and (4) that jurisdictional requisites are met. U.S. for Use and Benefit of Krupp Steel Prods., Inc. v. Aetna Ins. Co., 831 F. 2d 978, 979 (11th Cir. 1987). The record clearly demonstrates that Donaghey provided labor and materials in carrying out work provided for under the subcontract and that it in good faith believed that the labor and materials were for the specified work. The court thus has little trouble finding that Donaghey has satisfied the first and third elements of its Miller Act claim. Given the parties’ positions and the evidence in the record, however, the second element cannot be determined on summary judgment. As the Eleventh Circuit has noted, in enacting the Miller Act, “‘[i]t was not the intention of Congress to extend or enlarge the liability of the surety . . . beyond the contractual or quasi-contractual obligations of the contractor who remains primarily liable.’”8 U.S. for Use and Benefit of E. Gulf, Inc. v. Metzger Towing, Inc., 910 F.2d 775, 781 (11th Cir. 1990) (quoting U.S. ex rel. Harrington v. Trione, 97 F. Supp. 522, 526 (D.C. Colo. 1951).9 In considering a Miller Act claim, the trier of fact must thus look to the subcontract to determine the amount due. Id. at 439. “[I]f the subcontract provides for a condition precedent to payment, or a part thereof, which is not fulfilled, the subcontractor cannot recover labor and material expenditures against the surety on the payment bond.” Trione, 97 F. Supp. at 526. In other words, if there has been a default by the subcontractor, the general contractor may assert recoupment or 8 As originally enacted, the Miller Act allowed for recovery only of am ounts “justly due.” Although that language was not included in the am ended version of the Act, the am endm ents “were not intended to change the substance of the Act.” U.S. for the Use and Benefit of Acoustical Concepts, Inc. v. Travelers Cas. and Sur. Co. of Am., 635 F. Supp. 2d 434, 439 n.6 (E.D. Va. 2009). 9 “In general, a surety assum es the liability of its principal.” Travelers, 635 F. Supp. 2d at 437. “That this general principle of suretyship law ordinarily applies with equal force to Miller Act sureties is m ade clear by the language of the statute, which creates a cause of action against the surety to the extent a subcontractor ‘has not been paid in full’ and allows the subcontractor to recover only ‘the am ount unpaid.’” Id. (quoting 40 U.S.C. § 3133(b)(1)). Consolidated Case No.: 3:08cv56/MCR/MD Page 7 of 10 setoff as a defense. See id.10 Because there is a genuine issue of material fact regarding the timeliness of Donaghey’s performance and, therefore, Donaghey’s entitlement to the amounts withheld by Dick, summary judgment is inappropriate as to Donaghey’s Miller Act claim. C. Dick’s Counterclaim As both parties acknowledge, the dispute between Donaghey and Dick hinges largely on the enforceability of the liquidated damages provision in the parties’ subcontract. In the event the liquidated damages provision is enforceable, Dick may be entitled to damages in an amount exceeding the damages claimed by Donaghey; if the liquidated damages provision is not enforceable, Dick may not be entitled to any damages as a result of Donaghey’s alleged delays.11 “In Florida, the law is well-settled that the parties to a contract may agree in advance on an amount to be paid or retained as liquidated damages if the contract is breached.” Mineo v. Lakeside Village of Davie, LLC, 983 So. 2d 20, 21 10 See also U.S. for Use and Benefit of Martin Steel Constructors, Inc. v. Avanti Constructors, Inc., 750 F.2d 759, 762 (9th Cir. 1984) (recognizing setoff as a defense under the Miller Act and the proper subject of a counterclaim against a plaintiff in privity of contract with the general contractor); U.S. for the Use and Benefit of Fed. Roofing and Painting, Inc. v. Foster Constr. (Panama) S.A., 456 F.2d 250, 251 (5th Cir. 1972) (holding that the general contractor was entitled to withhold paym ent from the subcontractor for dam ages it incurred as a result of the subcontractor’s delay); H.B. Zachary Co. v. Travelers Indem. Co., 391 F.2d 43, 48 (5th Cir. 1968) (recognizing nonperform ance as a defense to a Miller Act claim ); U.S. ex rel. Andrews Marine Servs., Inc. v. United Sur. & Indem. Co., 2005 W L 1308919, at *7 (D. P.R. June 1, 2005) (unpublished) (noting that “disallowing recoupm ent would seem to give the supplier ‘rights’ to which his contract does not entitle him ” and holding that “a surety com pany standing in the shoes of the contractor is entitled to recoup the value of any defective or incom plete perform ance”); U.S. for Use of Ascher Bros. Co., Inc. v. Am. Home Assur. Co., 2003 W L 1338020, at *19 (N.D. Ill. Mar. 18, 2003) (recognizing setoff as a defense under the Miller Act); U.S. ex rel. Hussmann Corp. v. Fidelity & Deposit Co. of Maryland, 999 F. Supp. 734, 747-48 (D.N.J. 1998) (recognizing recoupm ent as a defense under the Miller Act and finding that, in order to recover on a Miller Act claim , a subcontractor m ust prove that it was justly entitled to the outstanding sum s); U.S. for Use and Benefit of Arlmont Air Condition Corp. v. Premier Contractors, Inc., 283 F. Supp. 343, 348, N.7 (D. C. Me. 1968) (holding, in a Miller Act case, that state law determ ines the substantive rights of the parties under their contracts and that “[i]t is axiom atic in the law of contracts that a party cannot recover on his contract unless he can show substantial perform ance of his own obligations under the contract or that perform ance was m ade im possible by the breach of the other party” and concluding that the subcontractor’s m aterial breach of contract justified the general contractor’s term ination of the contract). 11 As m entioned, the liquidated dam ages provision contains a waiver of actual dam ages. Dick argues that it would not have waived its right to actual dam ages if it had known that Donaghey would challenge the enforceability of the liquidated dam ages provision and that, even if the waiver was effective and the liquidated dam ages provision is deem ed unenforceable, the court should award it actual dam ages as a m atter of equity. Consolidated Case No.: 3:08cv56/MCR/MD Page 8 of 10 (Fla. 4th DCA 2008). The Florida Supreme Court has established a test to determine if a liquidated damages clause will be upheld, or if it will be stricken because it is a actually a penalty clause.” Id. (citing Hyman v. Cohen, 73 So. 2d 393 (Fla. 1954)). “First, the damages upon a breach must not be readily ascertainable.” Id. “Second, the sum stipulated to be forfeited must not be so grossly disproportionate to any damages that might reasonably be expected to follow from a breach as to show that the parties could have intended only to induce full performance, rather than to liquidate their damages.” Id. at 21-22. Even if a liquidated damages provision is enforceable, the court may refuse to award liquidated damages if circumstances at the time of breach demonstrate that it would be unconscionable to allow the non-breaching party to recover the sum in question. See Parrish v. Dougherty, 505 So.2d 646, 649 (Fla. 1st DCA 1987); Hutchison v. Tompkins, 259 So. 2d 129, 132 (Fla. 1972).12 Although the liquidated damages Dick claims are far in excess of its actual damages, the court finds that the actual damages resulting from Donaghey’s work delays were not readily ascertainable at the time the parties entered into the subcontract. As Dick argues in its response, although it was able to calculate the administrative costs it would incur in the event of a delay, administrative costs were only one of many factors that could have caused damage to Dick in the event of a work delay by Donaghey. There were a number of additional factors that could have resulted in damages to Dick, at least some of which were not readily ascertainable at the time the parties entered into the subcontract.13 It is for that reason the parties negotiated and agreed upon a liquidated damages 12 “The [Florida] suprem e court has identified two factors that support the finding that a forfeiture is unconscionable: (1) that the buyer’s ‘failure to fulfill the contract was due to any m isfortune beyond his control’ and (2) that the seller received a benefit, ‘the retention of which was shocking to the conscience of the court.’” Hot Developers, Inc. v. W illow Lake Estates, Inc., 950 So. 2d 537, 541 (Fla. 4th DCA 2007) (quoting Beatty v. Flannery, 49 So. 2d 81, 82 (Fla.1950)). 13 For exam ple, as Dick points out, Donaghey’s delays could have delayed other trades and resulted in costs and possibly even dam ages that could not have been ascertained at the tim e the subcontract was entered into. Consolidated Case No.: 3:08cv56/MCR/MD Page 9 of 10 provision.14 Not only were Dick’s damages as a result of delay not ascertainable at the time the parties entered into the subcontract, but they also were not grossly disproportionate to damages that might reasonably be expected to follow from Donaghey’s work delays. Indeed, had the Navy assessed liquidated damages against Dick as a result of Donaghey’s delays, Dick’s actual damages could have exceeded its liquidated damages. The court therefore finds that the liquidated damages provision in the parties’ subcontract is valid and enforceable.15 See U.S., for the Use and Benefit of Sunbeam Equip. Corp. v. Commercial Constr. Corp., 741 F.2d 326, 328 (11th Cir. 1984) (holding that the fact that they Navy did not assess liquidated damages against a general contractor would not preclude the general contractor from recovering liquidated damages against subcontractor 14 Although the liquidated dam ages provision in the subcontract contains figures identical to those provided for in the prim e contract, it is clear that the figures were negotiated between the parties in an arm ’s length transaction as to which Donaghey was represented by counsel. In fact, in the course of the parties’ negotiations, Donaghey proposed certain liquidated dam ages am ounts that were rejected by Dick before the parties agreed to the am ounts set forth in the subcontract. 15 The fact that the parties negotiated the am ount of liquidated dam ages underm ines Donaghey’s argum ent that the liquidated dam ages provision was intended as a “pass through” provision, as does the absence of “pass through” language in the liquidated dam ages clause. The interpretation of an unam biguous contract is a m atter of law. See Lawyers Title Ins. Corp. v. JDC (Am.)Corp., 52 F.3d 1575, 7580 (11th Cir. 1995). The court determ ines the parties’ intent from the four corners of the contract and only considers extrinsic evidence to explain or clarify am biguous or unclear language. See Taylor v. Taylor, 1 So. 3d 348, 350 (Fla. 1st DCA 2009); Ospina-Baraya v. Heiligers, 909 So. 2d 465, 472 (Fla. 4th DCA 2005). The court finds no am biguity in the liquidated dam ages provision. Although the am ount of liquidated dam ages in the subcontract coincides with the am ount of liquidated dam ages in the prim e contract, there is no indication in the subcontract that the parties intended Donaghey’s liability for liquidated dam ages to be dependent upon the Navy’s assessm ent of liquidated dam ages against Dick. Had they so intended, they clearly could have included “pass through” language in the liquidated dam ages clause as they did in two other provisions in the subcontract. Because the parties did not include such a condition in the liquidated dam ages provision, the court cannot now im pose it. See State Farm Life Ins. Co. v. Florida Asset Fin., Corp., 786 So. 2d 1, 3 (Fla 4th DCA 2000) (holding that “[w]here a contract is sim ply silent as to a particular m atter, that is, its language neither expressly nor by reasonable im plication indicates that the parties intended to contract with respect to the m atter, the court should not, under the guise of construction, im pose contractual rights and duties on the parties which they them selves om itted”) (internal quotations om itted); Sterling Investor Servs., Inc. v. 1155 Nobo Assocs., LLC, 818 N.Y.S.2d 513, 516 (N.Y. 2006) (noting that, “[u]nder accepted canons of contract construction, when certain language is om itted from a provision but placed in other provisions, it m ust be assum ed that the om ission was intentional”); see also Foster Constr., 456 F.2d at 251(holding that the am ount of liquidated dam ages in the prim e contract did not govern the general contractor’s claim against the subcontractor in the absence of language in the subcontract adopting the liquidated dam ages in the prim e contract as the m easure of dam ages for breach of the subcontract, even though the subcontract contained a clause providing that the parties generally would assum e the correlative positions of the parties in the prim e contract). Consolidated Case No.: 3:08cv56/MCR/MD Page 10 of 10 if the general contractor could demonstrate that damages arising out of the subcontractor’s delay were not otherwise compensated). Whether circumstances existed at the time of breach rendering enforcement of the liquidated damages provision unconscionable is a question of fact to be decided at trial. See Multitech Corp. v. St. Johns Bluff Inv. Corp., 518 So. 2d 427, 432 (1st DCA 1988) (holding that “a liquidated damages clause will not be enforced if circumstances at the time of the breach indicate it would be unconscionable to do so”); see also MTM Television Distrib. Group, Ltd. v. Pub. Interest Corp., 1992 WL 80625, at *1 (M.D. Fla. Mar. 24, 1992) (holding that “the question of whether the damages provision is so high as to be considered unconscionable is clearly a question of fact”). CONCLUSION Accordingly, it is hereby ORDERED that Donaghey’s ‘motion for summary judgment (doc. 539) is DENIED. DONE AND ORDERED this 9th day of November, 2010. s/ M. Casey Rodgers M. CASEY RODGERS UNITED STATES DISTRICT JUDGE Consolidated Case No.: 3:08cv56/MCR/MD

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.