Court Description: ORDER granting in part and denying in part Sherwin-Williams' 127 Motion for Partial Summary Judgment. Sherwin-Williams' motion for summary judgment on the breach of contract claims and unjust enrichment claims is DENIED. Its motion for summary judgment on Defendants' fraud claims is GRANTED IN PART AND DENIED IN PART. The alleged misrepresentations made to induce Defendants to enter the JB Supply Agreement are time barred. Signed by Judge Larry Alan Burns on 6/29/15. (kas)

Download PDF
The Sherwin-Williams Company v. JB Collision Services, Inc. et al Doc. 173 1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT 9 SOUTHERN DISTRICT OF CALIFORNIA 10 11 THE SHERWIN-WILLIAMS COMPANY, 12 14 Plaintiff, vs. 13 CASE NO. 13cv1946-LAB (WVG) JB COLLISION SERVICES, INC. et al., ORDER DENYING IN PART AND GRANTING IN PART SHERWINWILLIAMS' MOTION FOR PARTIAL SUMMARY JUDGMENT Defendants. 15 16 17 This dispute arises from a pair of supply contracts between Sherwin-Williams, a paint 18 company, and JB Collision Services, and JJT, Inc., automotive body shops owned by John 19 Tyczki. Sherwin-Williams has filed a motion for partial summary judgment. (Docket no. 127.) 20 I. Factual Background 21 A. 22 The first communication between the parties occurred in June 2008 when a 23 Sherwin-Williams sales representative, Jose Garcia, approached Tyczki about a potential 24 exclusive automotive paint products supply contract. Tyczki became interested in 25 Sherwin-Williams' new water-based paint line—AWX. Garcia allegedly represented that AWX 26 was a tested, proven, and perfected product and, with it, a vehicle could go from "prime to 27 shine" in 50 minutes. In September 2008, JB and Sherwin-Williams entered into a Supply 28 Agreement (the "JB Supply Agreement"). JB Supply Agreement -1- 13cv1946 Dockets.Justia.com 1 Under the JB Supply Agreement, JB was to purchase all of its requirements for 2 "Products" used at its body shops from Sherwin-Williams until the gross sales of its 3 purchases of "SW Paint Products" reached $1.3 million. This was the "Term" of the 4 agreement. "SW Paint Products" was defined in the contract as "automotive paints and 5 coatings manufactured and sold by Sherwin-Williams under the 'Sherwin-Williams label.'" 6 "Products" was defined as: "all automotive paints, coatings and related products, including, 7 without limitation, the following: (i) primers; (ii) top coats; (iii) hardeners; (iv) abrasives, tapes, 8 adhesives; and (v) all other associated products." In consideration of exclusivity, 9 Sherwin-Williams gave JB a discount on certain products and a $275,000 advanced 10 payment. The JB Supply Agreement stipulated that upon the occurrence of an "Acceleration 11 Event," such as early termination, JB was required to refund a pro-rata amount of the 12 advance payment. 13 B. 14 In May 2011, JJT and Sherwin-Williams entered into a similar supply agreement (the 15 "JJT Supply Agreement"). The Term of the contract was to last until gross sales of SW Paint 16 Products to JJT reached $250,000. Sherwin-Williams made a $40,000 advance payment to 17 JJT, and the entire amount was to be refunded in the case of an Acceleration Event. Tyczki 18 signed a personal guaranty for consideration of the advance payment to JJT. JJT Supply Agreement 19 C. 20 From September 2008 until early 2013, JB and JJT refinished about 12,000 vehicles 21 with Sherwin-Williams paint products. From the inception of the JB Supply Agreement until 22 Plaintiff filed suit for breach of contract in August 2013, Defendants filed four warranty claims 23 on vehicles painted with AWX. Since then, Defendants filed an additional 28 warranty claims. 24 Defendants allege quality issues arose less than a month after entering the JB Supply 25 Agreement, when JB began experiencing color-match defects with AWX. Defendants allege 26 further that, during a meeting in September 2008, Sherwin-Williams admitted it had made 27 false representations about AWX's quality. After the meeting, Sherwin-Williams took AWX 28 out of JB's shops and installed a solvent-based paint line. Because JB hadn't contracted for Contract Performance -2- 13cv1946 1 solvent-based products, Sherwin-Williams supplied them at no charge for the six months 2 between September 2008 and March 2009, at which point the AWX line was reinstalled. 3 Starting again in July 2009, Defendants allege they had further complications with 4 AWX, including dieback—a defect that occurs when paint loses its shine. Defendants allege 5 they voiced their issues with the product line to Sherwin-Williams, usually to Garcia, 6 numerous times each year from 2009 until 2013. And, while Garcia would provide "goodwill 7 adjustments" to account for product defects, Defendants had to absorb the labor costs of 8 repainting vehicles. In 2012, Defendants allege Tyczki met in-person with Garcia and 9 Sherwin-Williams Vice-President David Sewell to discuss the problems. Tyczki alleges he 10 never heard back from Sewell despite a promise that he'd "get to the bottom" of the issues. 11 Further, although Defendants contend they were repeatedly assured they were the 12 "only ones" experiencing issues with the AWX line, a number of other auto body shops 13 reportedly experienced similar issues. The cause of these issues, specifically Defendants' 14 problem with dieback, lies at the heart of Defendants' counterclaims. Defendants allege that 15 they encountered problems because AWX is defective. Sherwin-Williams maintains that the 16 product isn't defective, and the issues are within the painter's control. 17 Defendants allege that, beginning in March 2009, in response to the issues with the 18 AWX product line, Plaintiff provided on-site technical training to Defendants' painters and 19 eventually certified them for use of the AWX line. Defendants allege their problems persisted 20 and, in 2012, Sherwin-Williams proposed the adoption of a "30-60-90 Plan" which was 21 intended to improve Defendants' body shops by optimizing the area for painting vehicles. 22 Ultimately, the 30-60-90 Plan was never completed because, in late 2012, Tyczki stated his 23 intention for Defendants to completely terminate their business relationship with 24 Sherwin-Williams upon completion of the Term of the JB Supply Agreement with JB, which 25 he contended would occur once gross sales on that account reached $1.3 million. 26 D. 27 On February 28, 2013, Sherwin-Williams sent JB and JJT letters stating their belief 28 that both Defendants had breached their respective Supply Agreements by installing a Sherwin-Williams' Allegation that Defendants Breached -3- 13cv1946 1 competitor's paint line in their body shops. Defendants maintain they didn't actually 2 discontinue their exclusive relationship with Sherwin-Williams until the end of March 2013, 3 once they believed they had satisfied the Supply Agreement's gross sales requirement. At 4 that time Defendants had purchased $1.3 million in Sherwin-Williams Products, but, 5 according to Sherwin-Williams, only about $900,000 worth of SW Paint Products. On April 6 3, 2013, Tyczki sent Sherwin-Williams a letter, enclosed with a $40,000 check refunding the 7 advance payment, stating that JJT was terminating its Supply Agreement as of April 8, 2013. 8 Sherwin-Williams also alleges Defendants breached the Supply Agreements by 9 purchasing covered products from Keystone Automotive. Prior to entering into the Supply 10 Agreements, Defendants were in an exclusive contractual relationship with Keystone for the 11 supply of Spies-Hecker paint products. While Defendants claim this relationship ended in 12 2008, discovery revealed that they continuously purchased supplies from Keystone well into 13 2012. 14 Sherwin-Williams' lawsuit for breach of contract followed. 15 E. 16 Defendants filed a counterclaim based on Sherwin-Williams' alleged defective 17 products and unfulfilled promises. (Docket no. 36.) It contains causes of action for breach 18 of contract, fraud, intentional misrepresentation, negligent misrepresentation, and unjust 19 enrichment. (Id.) Defendants' Counterclaims 20 F. 21 Sherwin-Williams' motion seeks: 22 (1) Summary judgment on its breach of contract claims against all Defendants; 23 (2) Summary judgment on Defendants' breach of contract claims; 24 (3) Summary judgment on Defendants' claim for consequential and incidental 25 Sherwin Williams' Motion for Partial Summary Judgment damages; 26 (4) Summary judgment on Defendants' unjust enrichment claims; 27 (5) Summary judgment on Defendants' fraud claims; 28 (6) Summary judgment on Defendants' misrepresentation claims -4- 13cv1946 1 Defendants oppose Sherwin-Williams' motion, contending summary judgment is 2 improper and Sherwin-Williams isn't entitled to attorney's fees based on the indemnity 3 provision in the Supply Agreements. 4 II. Legal Standard 5 Summary judgment is appropriate where the evidence shows "there is no genuine 6 dispute as to any material fact and the movant is entitled to judgment as a matter of law." 7 Fed. R. Civ. P. 56(a). A party seeking summary judgment bears the initial burden of informing 8 the court of the basis for its motion and of identifying those portions of the pleadings and 9 discovery responses that demonstrate the absence of a genuine issue of material fact. See 10 Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). All reasonable inferences from the 11 evidence are drawn in favor of the nonmoving party. See Anderson v. Liberty Lobby, Inc., 12 477 U.S. 242, 242 (1986). Where the moving party doesn't bear the burden of proof at trial, 13 it is entitled to summary judgment if it can demonstrate that "there is an absence of evidence 14 to support the nonmoving party's case." Celotex, 477 U.S. at 325. 15 If the moving party meets its burden, the burden shifts to the nonmoving party 16 opposing the motion, who must "set forth specific facts showing that there is a genuine issue 17 for trial." Anderson, 477 U.S. at 256. Summary judgment is warranted if a party "fails to 18 make a showing sufficient to establish the existence of an element essential to that party's 19 case, and on which that party will bear the burden of proof at trial." Celotex, 477 U.S. at 322. 20 A genuine issue of fact exists if "the evidence is such that a reasonable jury could return a 21 verdict for the nonmoving party." Anderson, 477 U.S. at 248. A fact is material if it "might 22 affect the outcome of the suit under the governing law." Id. 23 III. 24 25 Discussion A. Breach of Contract Claims 1. Summary Judgment on the Parties Breach of Contract Claims 26 Sherwin-Williams seeks summary judgment on its breach of contract claims against 27 JB, JJT, and Tyczki. It also seeks summary judgment on Defendants' breach of contract 28 claims against it. -5- 13cv1946 1 Sherwin-Williams is correct that the plain language of the JB Supply Agreement 2 required JB to purchase $1.3 million in "SW Paint Products," and the parties agree that JB 3 didn't. See Wohl v. Swinney, 118 Ohio St. 3d 277, 280 (2008) ("When interpreting a 4 contract, we will presume that words are used for a specific purpose and will avoid 5 interpretations that render portions meaningless or unnecessary.").1 Sherwin-Williams is also 6 correct that JJT didn't purchase $250,000 in "SW Paint Products," as required by the JJT 7 Supply Agreement, and the agreement doesn't limit potential damages to return of the 8 advance. The Court finds no support for Defendants' argument that Tyczki's personal 9 guaranty on the JJT Supply Agreement is unenforceable because he signed it before the JJT 10 Supply Agreement became binding. Indeed, Tyczki doesn't dispute that the terms of the JJT 11 Supply Agreement were known to him when he signed the guaranty. 12 But, summary judgment on the breach of contract claims is improper because issues 13 of fact remain regarding whether the AWX paint product Sherwin-Williams supplied to JB and 14 JJT was defective. As all parties agree, the Supply Agreement is a contract for the sale of 15 goods governed by the Uniform Commercial Code. (Docket no. 25 at 6); (Docket no. 143 16 at 16); see also Sherwin-Williams Co. v. Coach Works Auto Collision Repair Ctr., Inc., 2011 17 WL 709714, at *10 (D. Md. Feb. 22, 2011); Alaska Pac. Trading Co. v. Eagon Forest 18 Products, Inc., 85 Wash. App. 354, 359-60 (1997) (the UCC "replaced the common law 19 doctrine of material breach . . ."). Because the Supply Agreement "authorizes the delivery 20 of goods in separate lots to be separately accepted," it's an installment contract. Ohio Rev. 21 Code Ann. § 1302.70(A). Installment contracts are only "breach[ed] in the whole" when 22 "non-conformity or default with respect to one or more installments substantially impairs the 23 value of the whole contract." Id. at § 1302.70(C). In that case, the buyer may cancel the 24 contract, recover the price paid, "cover" by purchasing substitute goods, and recover 25 damages. Id. at § 1302.85(A). Thus, if Sherwin-Williams provided nonconforming products, 26 1 27 28 The Supply Agreements are governed by Ohio law. But, the choice of law provision is limited to claims arising from, or relating to, the contract. See Wehlage v. EmpRes Healthcare Inc., 821 F. Supp. 2d 1122, 1127 (N.D. Cal. 2011). Thus, California law controls the fraud-based claims. See Nat'l Seating & Mobility, Inc. v. Parry, 2011 WL 4831198 at *4 (N.D.Cal. Oct.12, 2011). -6- 13cv1946 1 or otherwise defaulted, and thereby substantially impaired the value of the Supply 2 Agreements "in the whole," Defendants' performance would be excused and they could 3 maintain a lawsuit for Sherwin-Williams' breach. 4 The evidence presented by the parties is susceptible to multiple interpretations. As 5 Sherwin-Williams argues, a jury could view the low number of pre-suit warranty claims as 6 evidence that Sherwin-Williams didn't provide defective products or otherwise substantially 7 impair the value of the Supply Agreements. Conversely, a jury could view the warranty 8 claims, Defendants' claimed oral complaints, and the uninstallation of the AWX paint line in 9 JB's body shop as evidence that Sherwin-Williams did breach the contract as a whole. 10 McCullough v. Bill Swad Chrysler-Plymouth, Inc., 5 Ohio St. 3d 181, 186, 449 N.E.2d 1289, 11 1294 (1983) (stating that whether a defect amounts to substantial impairment is an issue of 12 fact). That's especially true because "notice of nonconformity or rejection of the goods by 13 the buyer need not be in any particular form and may be implied from conduct." Coach 14 Works, 2011 WL 709714, at *12 (internal quotation marks omitted). Sherwin-Williams' 15 motion for summary judgment on the breach of contract claims is DENIED. 16 17 2. Contract Damages Available to Defendants In the Supply Agreements, Defendants disclaim any right to special, indirect, 18 incidental, or consequential damages. This is a valid waiver of warranties. 19 Sherwin-Williams Co. v. JJT, Inc., 2014 WL 2587483, at *2 (S.D. Cal. June 10, 2014). While 20 Defendants don't contest the disclaimer's validity, they contend they're entitled to "direct 21 contract damages in the amount of the value in materials and labor costs for warranty work 22 that Defendants have performed and continue to perform in order to correct dieback defects 23 on customer vehicles caused by S-W's AWX paint products." (Docket no. 143 at 16.) See 24 This sort of injury proximately resulting from a breach of contract falls squarely into 25 the definition of consequential damages. Ohio Rev. Code Ann. §§ 1302.86(B), 1302.88(B), 26 1302.89(B); cf. Contempo Metal Furniture Co. v. East Texas Motor Freight Lines, Inc., 661 27 F.2d 761, 765 (9th Cir. 1981) (labor costs wasted in an attempt to use materials damaged 28 in shipping are consequential damages). Thus, the damages Defendants can recover are -7- 13cv1946 1 limited to the difference in value between the products received from Sherwin-Williams and 2 the value of those products as warranted under the Supply Agreement. See Nat'l Mulch & 3 Seed, Inc. v. Rexius Forest By-Products Inc., 2007 WL 894833, at *27 (S.D. Ohio Mar. 22, 4 2007). 5 3. Attorney's Fees Available to Sherwin-Williams 6 Citing a general indemnification provision in the Supply Agreements, Sherwin-Williams 7 contends Defendants must indemnify it for attorney's fees arising out of this lawsuit. (Docket 8 no. 127 at 3.) Courts are split on whether an indemnification provision authorizes the award 9 of attorney's fees with regard to claims between the parties to the agreement. NevadaCare, 10 Inc. v. Dep't of Human Servs., 783 N.W.2d 459, 471 (Iowa 2010) (collecting cases). Some 11 jurisdictions have found that "indemnification provisions do not authorize the award of 12 attorney fees with regard to claims between the parties to the agreement because 13 indemnification provisions only apply to third-party claims." Id. Ohio falls into this category. 14 Am. Premier Underwriters, Inc. v. Marathon Ashland Pipeline, LLC, 2004 WL 937316, *5 15 (Ohio Ct. App. 2004) ("The agreement contemplates that indemnity is available only for 'suits, 16 costs and expenses' brought by a third party and not for a dispute between the parties to the 17 agreement concerning the meaning of their contract."); Cf. Wilborn v. Bank One Corp., 121 18 Ohio St. 3d 546, 548 (2009) ("Attorney fees may be awarded when a statute or an 19 enforceable contract specifically provides for the losing party to pay the prevailing party's 20 attorney fees."). Thus, the indemnification provision doesn't provide Sherwin-Williams a basis 21 to collect its attorney's fees from Defendants in this case. 22 B. 23 "[A] claim for unjust enrichment may be pled in the alternative when the existence of 24 an express contract is in dispute and may be maintained despite the existence of an express 25 contract where there is evidence of fraud, bad faith, or illegality." (Docket no. 56 at 15) 26 (quoting Cheers Sports Bar & Grill v. DirecTV, Inc., 563 F. Supp. 2d 812, 819 (N.D. Ohio 27 2008)). The Court explained it interprets Cheers to stand for the proposition that, whether or 28 not the existence of an express contract is up for debate, an unjust enrichment claim may Unjust Enrichment Claim -8- 13cv1946 1 be pled in the alternative where there are also allegations of fraud. Id. Sherwin-Williams now 2 seeks summary judgment on Defendants' unjust enrichment claim, contending it arose 3 before October 1, 2010, so it's time barred under the three year statute of limitations for fraud 4 claims. 5 The statute of limitations on a cause of action doesn't begin to run until "all of its 6 elements" have occurred. Pooshs v. Philip Morris USA, Inc., 51 Cal. 4th 788, 797 (2011). 7 "Under Ohio law, a plaintiff must prove the following elements to succeed in an action for 8 unjust enrichment: (1) a benefit conferred by the plaintiff upon the defendant, (2) defendant's 9 knowledge of the benefit, and (3) improper retention of the benefit without the defendant's 10 rendering of payment to plaintiff for same." Cheers, 563 F. Supp. 2d at 819 (internal 11 quotation marks omitted). The parties' allegations are susceptible to multiple interpretations 12 regarding when Sherwin-Williams' retention of the benefits of the Supply Agreements 13 became unjust. For example, Defendants allege the JJT Supply Agreement wasn't entered 14 until May 2011, and that, from 2011 through 2013, Sherwin-Williams verbally assured 15 Defendants that they would correct the alleged defects. (Docket no. 36, ¶¶ 20(h)-(l). From 16 these allegations, a jury could determine that Defendants' unjust enrichment claim didn't 17 accrue until October 1, 2010, or later. Thus, Sherwin-Williams' motion for summary judgment 18 on Defendants' unjust enrichment claim is DENIED. 19 C. 20 Defendants allege Sherwin-Williams made knowing misrepresentations from 2008 to 21 2013. These alleged misrepresentations fall into two categories: (1) false statements about 22 the quality of Sherwin-Williams' products and (2) ultimately unfulfilled promises to cure 23 defects. (Docket no. 56 at 7.) The misrepresentations are the basis for Defendants' causes 24 of action for fraud, intentional misrepresentation, and negligent misrepresentation. 25 Sherwin-Williams moves for summary judgment on these claims, contending: (1) the majority 26 of the fraud allegations are time barred; (2) Defendants can't establish the scienter or intent 27 to defraud elements of misrepresentation; and (3) Defendants can't establish the justifiable 28 reliance element of misrepresentation. Fraud and Misrepresentation Claims -9- 13cv1946 1 1. Statute of Limitations 2 Pursuant to California Code of Civil Procedure § 338(d), there is a three-year statute 3 of limitations for "[a]n action for relief on the ground of fraud or mistake," which "is not 4 deemed to have accrued until the discovery, by the aggrieved party, of the facts constituting 5 the fraud or mistake." "[T]he elements of intentional misrepresentation, or actual fraud, are: 6 (1) misrepresentation (false representation, concealment, or nondisclosure); (2) knowledge 7 of falsity (scienter); (3) intent to defraud (i.e., to induce reliance); (4) justifiable reliance; and 8 (5) resulting damage." Rodriguez v. JP Morgan Chase & Co., 809 F. Supp. 2d 1291, 1296 9 (S.D. Cal. 2011) (internal quotation marks omitted). "Since a cause of action accrues when 10 the elements of the cause of action, including damage occur, the appreciable and actual 11 harm that results in accrual must be harm of the specific type that is recoverable as damages 12 on that type of cause of action." Platt Elec. Supply, Inc. v. EOFF Elec., Inc., 522 F.3d 1049, 13 1054 (9th Cir. 2008) (internal quotation marks omitted). "Although this ordinarily occurs on 14 the date of the plaintiff's injury, accrual is postponed until the plaintiff either discovers or has 15 reason to discover the existence of a claim, i.e., at least has reason to suspect a factual 16 basis for its elements." Id. (internal quotation marks omitted). 17 The Court previously explained that "any claim accruing on or after October 1, 2010 18 will not be barred by the statute of limitations." (Docket no. 56 at 10.) Defendants allege 19 Sherwin-Williams made fraudulent misrepresentations both before and after this date. 20 (Docket no. 36, ¶¶ 17-20). 21 Sherwin-Williams now argues that any fraud claims based on misrepresentations 22 made before October 1, 2010 are time-barred. Defendants correctly point out that the statute 23 of limitations doesn't accrue until all elements of fraud occur, and argue that they didn't know 24 of their damages until they were sued by Sherwin-Williams and "learned that [it] had been 25 lying to them all along." 26 allegations that, in 2008, Sherwin-Williams admitted it made false representations to induce 27 JB to enter into the JB Supply Agreement. (Docket no. 36, ¶ 20(c),(d),(f).) And, since 28 Defendants allege they absorbed the labor costs associated with repainting vehicles due to (Docket no. 143.) - 10 - But, this is contradicted by Defendants' 13cv1946 1 product defects (id., ¶ 20(g)), they can't claim they weren't aware of the damages stemming 2 from these misrepresentations. Thus, the representations made to induce Defendants to 3 enter the JB Supply Agreement are time barred. Issues of fact remain regarding when the 4 claims arising out of the remainder of the alleged misrepresentations accrued. 5 Sherwin-Williams' motion for summary judgment on Defendants' fraud claim on statute of 6 limitations grounds is GRANTED IN PART AND DENIED IN PART. 7 2. Scienter 8 "The intent element of promissory fraud entails more than proof of an unkept promise 9 or mere failure of performance." Mazed v. JP Morgan Chase Bank, NA, 2014 WL 1364929, 10 at *6 (C.D. Cal. Apr. 7, 2014) (internal brackets and quotation marks omitted). "If [a claimant] 11 adduces no further evidence of fraudulent intent than proof of nonperformance of an oral 12 promise, he will never reach a jury." Id. (internal brackets and quotation marks omitted). 13 Based on this authority, Sherwin-Williams alleges Defendants haven't gone beyond alleging 14 an unkept promise. It is wrong. Defendants allege Sherwin-Williams told them they were 15 the "only ones" experiencing defects, but later learned that multiple other Sherwin-Williams 16 customers experienced, and complained to Sherwin-Williams about, product defect issues. 17 From this evidence, a jury could conclude Sherwin-Williams acted with knowledge of falsity 18 and intent to defraud. Sherwin-Williams' motion for summary judgment on Defendants' fraud 19 claim for lack of scienter is DENIED. 20 3. Justifiable Reliance 21 Sherwin-Williams also contends that any reliance by Defendants wasn't reasonable. 22 "Except in the rare case where the undisputed facts leave no room for a reasonable 23 difference of opinion, the question of whether a [claimant's] reliance is reasonable is a 24 question of fact." Alliance Mortgage Co. v. Rothwell, 10 Cal. 4th 1226, 1239 (1995). This 25 isn't the rare case. Defendants allege numerous misrepresentations, and whether they 26 justifiably relied on them is an issue of fact for trial. Sherwin-Williams' motion for summary 27 judgment on Defendants' fraud claim for lack of justifiable reliance is DENIED. 28 /// - 11 - 13cv1946 1 IV. Conclusion 2 Sherwin-Williams' motion for summary judgment on the breach of contract claims and 3 unjust enrichment claims is DENIED. Its motion for summary judgment on Defendants' fraud 4 claims is GRANTED IN PART AND DENIED IN PART. The alleged misrepresentations made 5 to induce Defendants to enter the JB Supply Agreement are time barred. 6 7 IT IS SO ORDERED. DATED: June 29, 2015 8 9 10 HONORABLE LARRY ALAN BURNS United States District Judge 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 - 12 - 13cv1946

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.