American Guarantee And Liability Insurance Company v. Lexington Insurance Company, No. 3:2010cv03009 - Document 57 (N.D. Cal. 2011)

Court Description: ORDER GRANTING DEFENDANT'S MOTION FOR SUMMARY JUDGMENT AND DENYING PLAINTIFF'S MOTION FOR PARTIAL SUMMARY JUDGMENT. Signed by Judge Richard Seeborg on 7/29/11. (cl, COURT STAFF) (Filed on 7/29/2011)

Download PDF
American Guarantee And Liability Insurance Company v. Lexington Insurance Company Doc. 57 *E-Filed7/29/11* 1 2 3 4 5 6 IN THE UNITED STATES DISTRICT COURT 7 FOR THE NORTHERN DISTRICT OF CALIFORNIA 8 SAN FRANCISCO DIVISION 9 No. C 10-03009 RS AMERICAN GUARANTEE AND LIABILITY INSURANCE COMPANY, 11 For the Northern District of California United States District Court 10 Plaintiff, 12 v. 13 LEXINGTON INSURANCE COMPANY, ORDER GRANTING DEFENDANT’S MOTION FOR SUMMARY JUDGMENT AND DENYING PLAINTIFF’S MOTION FOR PARTIAL SUMMARY JUDGMENT 14 15 Defendant. ____________________________________/ 16 17 18 I. INTRODUCTION 19 Plaintiff American Guarantee and Liability Insurance Company (American) brings this 20 contribution action seeking reimbursement from defendant Lexington Insurance Company 21 (Lexington) for sums paid to settle claims arising out of an accident at a construction site. American 22 defended the general contractor BBI Construction (BBI) and paid the settlement. According to 23 American, Lexington had a duty to defend and indemnify BBI under an insurance policy issued by it 24 to the subcontractor RCM Fire Protection (RCM), whose employee was injured. American moves 25 for partial summary judgment seeking a declaration that Lexington owed a primary duty to defend 26 BBI, leaving issues related to money damages for a later date. Lexington seeks summary judgment 27 on reverse grounds, i.e., that no insurance coverage existed and/or that no duty to defend was 28 NO. C 10-03009 RS ORDER GRANTING DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT Dockets.Justia.com 1 triggered. For the reasons stated below, Lexington’s motion for summary judgment is granted and 2 American’s motion for partial summary judgment is denied. 3 4 II. BACKGROUND BBI was the general contractor on a project to renovate the Veterans Memorial Building in 5 Pleasanton, California. It is the named insured of a commercial general liability insurance policy 6 issued by American. RCM was a subcontractor on the project that was engaged by BBI to install a 7 fire sprinkler system. RCM is the named insured of an insurance policy issued by Lexington. The 8 Lexington policy extended insurance coverage to any additional insureds that RCM was required by 9 written contract to name. The additional insured endorsement modifies the commercial general For the Northern District of California United States District Court 10 11 12 13 liability coverage section and provides the following blanket protection: Blanket- Where required by written contract. It is further agreed that such insurance as is afforded by this policy for the benefit of the additional insured shall be primary insurance, but only with respect to claims, loss or liability arising out of the named insured’s operations and any other insurance maintained by the additional insured shall be non-contributing. 14 Exh. D to Quintero Dec. in Support of Def. MSJ (Exh. D), at 69. Under the policy, Lexington 15 generally does not extend coverage for bodily injury or property damage for which RCM becomes 16 obligated to pay based on assumption of liability in a contract or agreement. Id. at 13. This 17 exclusion does not apply if RCM assumes the liability as part of an “insured contract,” provided that 18 the bodily injury or property damage “occurs subsequent to the execution of the contract or 19 agreement.” Id. As defined in the policy, an insured contract includes: “[t]hat part of any other 20 contract or agreement pertaining to your business . . . under which you assume the tort liability of 21 another party for ‘bodily injury’ or ‘property damage’ to a third person or organization.” Id. at 23. 22 As the general contractor, BBI issued an invitation to bid to RCM dated May 5, 2005. Exh. 23 2 to Chan Dec. in Support of Pl. MSJ. The invitation included a one paragraph description of the 24 overall project, which indicated that planned renovations to the building included a new fire 25 sprinkler system. On May 12, 2006, RCM provided a quotation for the fire sprinklers that outlined 26 the proposed work and listed a price. Exh. 3 to Chan Dec. in Support of Pl. MSJ. On August 7, 27 2006, RCM submitted a revised quotation. Exh. 4 to Chan Dec. in Support of Pl. MSJ. BBI then 28 sent a letter of intent dated August 10, 2006, which states: “This letter is to notify you that BBI NO. C 10-03009 RS ORDER GRANTING DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT 2 1 Construction intends to contract with you on the Pleasanton’s Veteran Memorial Building project. 2 We do not yet have formal Notice to Proceed from the Owner, but we have been asked to 3 commence with the submittal process.” Exh. 1 to Chan Dec. in Support of Pl. MSJ (Exh. 1). The 4 letter requests RCM to proceed with its submittals, shop drawings, and material and safety data 5 sheets according to the plans and specifications. Exh. 1, at 1. It also informs RCM of the 6 requirement that it submit documents regarding general liability insurance “naming BBI-Con, Inc. 7 as the additional insured and include [sic] the following as job description: Pleasanton’s Veteran 8 Memorial Building.” Id. The letter further states, “[p]lease sign below and return a copy of this 9 letter to indicate your acceptance.” RCM’s president signed and dated the letter on August 10, For the Northern District of California United States District Court 10 11 2006. Id. at 2. BBI and RCM subsequently signed a document titled “standard form subcontract” listing 12 Pleasanton Veterans Memorial Building as the “job name” and November 2, 2006 as the 13 “subcontract date.” Exh. 5 to Chan Dec. in Support of Pl. MSJ (Exh. 5), at 1. RCM signed that 14 agreement on November 30, 2006 and BBI signed it on March 6, 2007. Id. at 1. The subcontract 15 includes separate paragraphs addressing indemnification and insurance. The indemnification 16 section requires RCM to indemnify BBI against claims “arising out of or in connection with 17 [RCM’s] operations.” Id. at 3. The indemnity is to apply “regardless of any active and/or passive 18 negligent act or omission” of BBI. Id. RCM, however, is not obligated to indemnify BBI for any 19 claims “arising from the sole negligence or willful misconduct” of BBI or its agents. Id. The 20 indemnity provision expressly provides that it is not limited by the insurance requirements in the 21 agreement. Id. Section 14 provides that RCM shall carry at least one million dollars of insurance 22 on its operations and the policy must include an endorsement for “Contractual Liability under this 23 Agreement.” Id. at 4. It also requires that RCM name BBI as an additional insured under its 24 general liability policy. Id. 25 On November 8, 2006, after RCM’s signing of the letter of intent, but before either party 26 signed the subcontract, an RCM employee was injured at the Veterans Memorial work site. David 27 Trahan had exited the building and was walking toward a security gate to take a lunch break when 28 NO. C 10-03009 RS ORDER GRANTING DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT 3 1 he was hit in the head by lumber that fell off the building’s roof. He had removed his hard hat 2 before passing through the gate, in violation of the safety policies of both RCM and BBI. 3 In November 2007, Trahan filed a personal injury suit against BBI and later added the wood 4 contractor, Timber Construction. BBI in turn tendered its claim for defense and indemnity in the 5 Trahan action to Lexington, which denied the claim. Lexington, however, denied that it had a duty 6 to defend or indemnify BBI. BBI filed cross-claims against RCM and Timber Construction, 7 claiming that each violated express indemnities and committed breach of contract by failing to 8 insure, defend, and indemnify it. Subsequently, BBI dismissed with prejudice its claims against 9 RCM. Ultimately, Trahan, BBI, and Timber Construction entered into a settlement agreement. On For the Northern District of California United States District Court 10 August 8, 2010, American filed the present suit alleging that Lexington had the primary duty to 11 defend BBI as an additional insured under RCM’s policy. 12 13 III. LEGAL STANDARD Under the Federal Rules of Civil Procedure, a court shall grant summary judgment “if the 14 pleadings, depositions, answers to interrogatories, and admissions on file, together with the 15 affidavits, if any, show that there is no genuine issue as to any material fact and that the moving 16 party is entitled to a judgment as a matter of law.” Fed. R. Civ. P. 56(c). The moving party bears 17 the initial burden of demonstrating the absence of a genuine issue of material fact. Celotex Corp. v. 18 Catrett, 477 U.S. 317, 323 (1986). The burden then shifts to the nonmoving party to “set forth 19 specific facts showing that there is a genuine issue for trial.” Fed. R. Civ. P. 56(e). The nonmoving 20 party must identify factual disputes that “might affect the outcome of the suit under governing law.” 21 Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). Irrelevant or unnecessary factual 22 disputes do not raise any genuine issue for trial. Id. If a reasonable jury could return a verdict in 23 favor of the nonmoving party, then entry of summary judgment is precluded. Id. 24 IV. DISCUSSION 25 Under the insurance policy obtained by RCM, Lexington extends coverage to additional 26 insureds “[w]here required by written contract.” American argues that two separate documents 27 satisfy this requirement and therefore bring BBI within the Lexington policy. The first is the 28 subcontract. Near the top of that form document, the language reads, “This Agreement is made this NO. C 10-03009 RS ORDER GRANTING DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT 4 1 day between BBI-CON, Inc. dba BBI Construction (Contractor) and RCM Fire Protection 2 (Subcontractor).” Below this sentence, the document lists the companies’ addresses, along with 3 spaces for signing and dating by their respective representatives. RCM’s president signed the 4 document on November 30, 2006 and BBI’s vice president of operations signed it on March 6, 5 2007. Nonetheless, American contends that the “subcontract date” of November 2, 2006 listed on 6 the first page reflects the date that BBI and RCM intended the contract to be effective. 7 In light of the express terms of the Lexington policy, the intent of the parties regarding the additional insured endorsement in that policy. That endorsement modifies the policy’s commercial 10 For the Northern District of California effective date is irrelevant. Any potential coverage extended to BBI arises from the blanket 9 United States District Court 8 general liability coverage. Under that part of the policy, the insurance covers bodily injury claims 11 for which RCM assumes liability in an “insured contract,” but only where such injury occurs 12 “subsequent to the execution of the contract or agreement.” In this case, the subcontract requires 13 RCM to maintain a minimum of one million dollars of insurance “with an endorsement for 14 contractual liability under this Agreement.” Thus, it qualifies as an “insured contract” within the 15 meaning of the Lexington policy. The agreement, however, was not “executed” prior to the Trahan 16 accident on November 8, 2006. 17 As generally understood, a party “executes” a written contract when it signs the agreement. 18 In the strictest sense, the contract is executed when all parties to the agreement have signed it. See, 19 e.g., Nielsen Construction Co. v. International Iron Products, 18 Cal. App. 4th 863, 869 (1993) 20 (interpreting an indemnity provision within California Labor Code section 3864 and declaring that 21 “a written agreement is ‘executed’ when all parties sign the agreement; only then is the written 22 agreement completed and all necessary formalities performed”). Here, there is no dispute that 23 neither party executed the subcontract until after Trahan’s accident on November 8, 2006. Although 24 American refers to the date RCM executed the subcontract, it does not suggest that executing a 25 written contract means anything other than signing it: “Although the subcontract was not executed 26 until November 30, 2006, the contract was dated to take effect on November 2.” Pl. Opp. To Def. 27 MSJ, 10:28-11:1. Even if, as American argues, the parties were in complete agreement that the 28 subcontract was effective as of November 2, Lexington has short-circuited any reliance on that date NO. C 10-03009 RS ORDER GRANTING DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT 5 their contract prior to any covered injury. The factual determination of when the parties reached an 3 agreement or intended any contract to be effective is immaterial. The date at which Lexington 4 provides insurance based on an insured contract is when the contract is executed. As a result, 5 Lexington had no duty to defend or indemnify BBI in the Trahan litigation based on the subcontract. 6 American further contends that the letter of intent, signed by RCM’s president on August 10, 7 2006, represents an “initial contract” between BBI and RCM sufficient to satisfy the written contract 8 requirement in the Lexington additional insured endorsement. The formation of a contract requires 9 mutual assent. See First Nat’l Mortg. Co. v. Fed. Realty Inv. Trust, 631 F.3d 1058, 1065 (9th Cir. 10 For the Northern District of California by including an unambiguous requirement that the named insured and additional insured execute 2 United States District Court 1 2011) (citing Kruse v. Bank of Am., 202 Cal. App. 3d 38, 59 (1988)). “Where any of the terms are 11 left for future determination or there is a manifest intention that the formal agreement is not to be 12 complete until reduced to a formal writing to be executed, there is no binding contract until this is 13 done.” Smissaert v. Chiodo, 163 Cal. App. 2d 827, 830-831 (1958). In other words, an agreement 14 to make a future agreement, by itself, is not a binding contract. First Nat’l Mortg. Co., 631 F.3d at 15 1065 (citation omitted). 16 In the absence of ambiguity, whether a document represents the final contract or instead an 17 agreement to agree is determined “by a construction of the instrument taken as a whole.” Beck v. 18 Am. Health Group Internat., 211 Cal. App. 3d 1555, 1562 (1989). The outward, objective 19 manifestation of the parties’ intent to be bound governs the interpretation. Id. (citations omitted). 20 When parties refer to a document as a “letter of intent,” the general implication is that they intend 21 the document “to be a nonbinding expression in contemplation of a future contract.” Rennick v. 22 O.P.T.I.O.N. Care, 77 F.3d 309, 315 (9th Cir. 1996). Despite the label, a letter of intent may be a 23 contract, if its contents evidence that the parties intended to be bound by its terms. Id. 24 In this case, the purported contract is a letter from BBI’s project manager to the president of 25 RCM with the subject line: “LETTER OF INTENT, Pleasanton’s Veteran Memorial Building.” The 26 first line explains that “BBI Construction intends to contract with you” on the project. BBI informs 27 RCM that it does not have the formal approval from the building’s owner, but it has been asked “to 28 commence with the submittal process.” Accordingly, BBI requests various documents from RCM NO. C 10-03009 RS ORDER GRANTING DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT 6 1 including proof of general liability insurance “naming BBI-Con, Inc. as the additional insured” for 2 the job described as Pleasanton’s Veteran Memorial Building. It also serves to identify members of 3 the “BBI Project team” and provides their contact information. The letter ends, at the top of the 4 second page, with a request for RCM to sign and to return a copy “to indicate your acceptance.” 5 RCM’s president signed and dated the letter on August 10, 2006. 6 In American’s view, BBI needed only to receive notice from the building’s owner to proceed 7 with the project. It therefore characterizes the letter of intent as an enforceable contract with a 8 condition precedent. In support, it points to the bid process and states that “the invitation to bid 9 described the work to be done and other general project requirements.” In response, the bid For the Northern District of California United States District Court 10 provided by RCM “specified the price for which [it] would perform the work.” Thus, by signing the 11 letter, American contends that RCM signified acceptance of “the offer to perform the work” and 12 also “agreed in writing” to name BBI as an additional insured to its general liability insurance. 13 In viewing the letter of intent as a whole, however, there is no objective manifestation that 14 the parties intended to be bound by its terms. The letter is sent from BBI’s project manager to 15 “notify” RCM that the company “intends to contract.” Thus, the document is not just labeled “letter 16 of intent;” it also contains additional language expressly indicating a future intent to contract. 17 Furthermore, the complete lack of the essential terms of a contract also provides objective evidence 18 that the letter itself was not intended by the parties to constitute a binding contract. Although the 19 letter refers to the “Pleasanton’s Veteran Memorial Building” project, it does not mention RCM’s 20 bid or otherwise incorporate any terms from it. Even if RCM’s August 7, 2006 revised quotation 21 were incorporated, neither the bid nor the letter of intent discuss the time for performance of the 22 subcontract. While the letter informs RCM that it must submit documents regarding general 23 liability insurance that name BBI as an additional insured, no description of the amount of insurance 24 or the scope of any indemnity is provided. Instead of outlining the essential terms of an agreement, 25 the letter primarily requests further submittals from RCM within fifteen days of “this notice.” 26 At oral argument on these motions, American suggested that RCM could readily enforce a 27 contract to be paid for the work performed at the Veterans Memorial based on the letter of intent and 28 performance of the work alone. As even American describes the letter as “memorializing” the NO. C 10-03009 RS ORDER GRANTING DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT 7 1 initial contract, it apparently recognizes that the document itself does not suffice as a written 2 contract. Lexington expressly agreed to provide additional insured coverage, not when RCM 3 formed a contract, but when it executed a written contract. Thus, the issue is not whether or when 4 the parties reached an agreement that RCM would add BBI as an additional insured, but the 5 narrower question of when any agreement was reduced to writing. In this case, the letter of intent 6 simply does not constitute a written contract. In summary, BBI and RCM neither executed their written subcontract prior to Trahan’s 7 provisions in RCM’s policy with Lexington, BBI was not covered as an additional insured at the 10 For the Northern District of California accident nor entered into a written contract by virtue of the letter of intent. Based on express 9 United States District Court 8 time Trahan was injured.1 Therefore, Lexington had no duty to defend or indemnify BBI in the 11 Trahan litigation and its motion for summary judgment is granted. V. CONCLUSION 12 For the reasons set forth above, Lexington’s motion for summary judgment on the grounds 13 14 that it did not owe a duty to defend or indemnify BBI in the Trahan litigation is granted and 15 American’s motion for partial summary judgment is denied. 16 IT IS SO ORDERED. 17 18 19 Dated: 7/29/11 RICHARD SEEBORG 20 UNITED STATES DISTRICT JUDGE 21 22 23 24 25 26 27 28 1 In its motion, Lexington raised additional grounds for summary judgment including: (1) that Trahan’s accident did not “arise out of” RCM’s work as required in its policy; (2) that the policy should be construed in light of the indemnity provision in the subcontract as excluding liability based on BBI’s “sole negligence;” (3) that because BBI had dismissed its claims against RCM in the Trahan litigation, Lexington’s present claims are barred; and (4) that an entity other than American, namely Zurich American Insurance Company, funded the settlement with Trahan. Based on the conclusion that no written contract was executed prior to the Trahan accident, these additional arguments need not be reached. NO. C 10-03009 RS ORDER GRANTING DEFENDANTS’ MOTION FOR SUMMARY JUDGMENT 8

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.