Sharp Elec. Corp. v. McHugh, No. 12-1299 (Fed. Cir. 2013)
Annotate this CaseSharp, a federal supply contractor, submitted a termination compensation claim to the Department of the Army contracting officer, and later brought a Contracts Dispute Act claim before the Armed Services Board of Contract Appeals, claiming that, because the Army failed to exercise the entirety of the last option year under a delivery order, Sharp was entitled to premature discontinuance fees under its General Services Administration schedule contract. The ASBCA dismissed for lack of subject-matter jurisdiction, concluding that the Federal Acquisition Regulation, does not permit ordering agency contracting officers to decide disputes pertaining to schedule contracts. The Federal Circuit affirmed. Under FAR 8.406-6, only the GSA contracting office may resolve disputes that, in whole or in part, involve interpretation of disputed schedule contract provisions.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.