Environmental Defense Fund v. Federal Energy Regulatory Commission, No. 20-1016 (D.C. Cir. 2021)
Annotate this Case
Spire planned to build a St. Louis-area pipeline and unsuccessfully solicited natural gas “shippers” to enter into preconstruction “precedent agreements.” Spire later entered into a precedent agreement with its affiliate, Spire Missouri, for 87.5 percent of the pipeline’s projected capacity. Spire applied to the Federal Energy Regulatory Commission (FERC) for a certificate of public convenience and necessity (Natural Gas Act, 15 U.S.C. 717f(c)(1)(A)), conceding that the proposed pipeline was not needed to serve new load but claiming other benefits. As evidence of need, Spire relied on its precedent agreement with Spire Missouri. FERC released an Environmental Assessment, finding no significant environmental impact. EDF challenged Spire’s application, arguing that the precedent agreement should have limited probative value because the companies were corporate affiliates. The Order approving the new pipeline principally focused on the precedent agreement.
The D.C. Circuit vacated the approval. FERC may issue a Certificate only if it finds that construction of a new pipeline “is or will be required by the present or future public convenience and necessity.” Under FERC’s “Certificate Policy Statement,” if there is a need for the pipeline, FERC determines whether there will be adverse impacts on existing customers, existing pipelines, or landowners and communities. If adverse stakeholder impacts will result, FERC balances the public benefits against the adverse effects. FERC’s refusal to address nonfrivolous arguments challenging the probative weight of the affiliated precedent agreement did not evince reasoned and principled decision-making. FERC ignored evidence of self-dealing and failed to thoroughly conduct the interest-balancing inquiry.