Petitioners challenged FERC's failure to account for the effect on electricity prices of the permanent retirement of the Brayton Point Power Station, a coal-fired electric plant in Somerset, Massachusetts. Petitioners alleged that the closure was an attempt to manipulate the results of forward capacity auction (FCA 8). The DC Circuit held that it lacked jurisdiction to consider the petition in the absence of final agency action. In two later proceedings, petitioners asked FERC to correct for what they assert were effects of Brayton Point’s illegal closure on the next two annual forward capacity auctions (FCA 9 and FCA 10). FERC denied the petitions and approved FCA 9 and FCA 10 results.
The court held that petitioners lacked standing to challenge FERC's acceptance of the FCA 9 and FCA 10 results because no record evidence established a causal link between the claimed manipulative closure of Brayton Point and the clearing prices of FCA 9 and FCA 10 that FERC approved.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.