Plaintiffs, Woodward employees, filed a qui tam action under the False Claims Act, alleging that Woodward falsely certified helicopter engine parts that it sold to the government. Plaintiffs had complained that the sensors at issue did not meet quality standards and had refused to work on the order. Following an investigation, a Defense Contract Management Agency Technical Specialist concluded that there was “nothing either incorrect or wrong with the procedures, assembly, or testing of the sensors.” The government continues to order, pay for, and use Woodward’s sensor The Seventh Circuit affirmed summary judgment in favor of Woodward, agreeing that even if Woodward made false statements to the government, no reasonable jury could find that it made the statements knowingly or that the statements were material.

Download PDF
In the United States Court of Appeals For the Seventh Circuit ____________________ No. 15 1866 UNITED STATES ex rel. DEBRA MARSHALL, et al., Plaintiffs Appellants, v. WOODWARD, INC., Defendant Appellee. ____________________ Appeal from the United States District Court for the Northern District of Illinois, Eastern Division. No. 1:06 CV 01746 — Gary S. Feinerman, Judge. ____________________ ARGUED OCTOBER 29, 2015 — DECIDED DECEMBER 11, 2015 ____________________ Before FLAUM, MANION, and ROVNER, Circuit Judges. FLAUM, Circuit Judge. Plaintiffs Debra Marshall and Peggy Thurman bring this qui tam action against Woodward, Inc. under the False Claims Act (“FCA”). Plaintiffs allege that Woodward falsely certified helicopter engine parts that it sold to the government. They also claim that Woodward vio lated the FCA and Illinois state law by terminating their em ployment. In the district court, Woodward moved for sum 2 No. 15 186 66 mary y judgment. . The court t granted th he motion, holding th hat even if Woodwa ard made fa alse stateme ents to the governmen nt, ury could find that W Woodward d did so know w no reasonable ju ingly and that the statem ments were material. The distri e ict court t also rejecte ed plaintiff fs’ retaliatio on claims. M Marshall an nd Thurm man appeal and for th he reasons t that follow, we affirm. I. Background d Woodward is W s a governm ment contra actor that m manufactures parts used in mi ilitary aircr rafts. One o of these par rts, the “T70 00 HMU regulate fuel flow for engi U,” es w ines in Bla ackhawk an nd Apache helicopt ters. Woodw ward sells the T700 H HMU to Gen eral E Electric (“GE”) for inco orporation into helicop pter engine es. It also sells the part direct to the U Depart o tly U.S. tment of D De fense (“DOD”) f for spare an nd replacem ment parts. On ne of the co omponents s of the T70 00 HMU is the “T2 sen sor,” which help regulate fuel flow by measur ps e ring changes in air r temperatu ure. A pictu ure of the T2 2 sensor is included b be low: sensor has a a coil end a and a bello ows end con nnected by y a The s capill lary tube. T The coil end d measures s changes in n air tempe er ature. Any chan in temp nge perature ca auses alcoh containe hol ed in the capillary tube to ex e xpand or c contract, w which in tur rn trigge ers movement in the b bellows end d and contr rols fuel flo ow No. 15 1866 3 to the engine. Crucially, the functionality of the sensor de pends on the amount of alcohol in the capillary tube; if any alcohol leaks, the sensor will add more fuel than it should. A defective sensor can cause the engine to smoke, decrease thrust, lose horsepower, or burn up. The T2 sensor has a total of eight “sealing joints” that connect the various parts of the component and contain the alcohol. Joints are sealed by “brazing,” a process that joins two metal surfaces by melting a filler metal. Woodward clas sifies its joints by category, such as Grade A, Grade B, and so forth. These classifications help determine what procedures are used to braze the joint and how the joint is inspected for imperfections. One of the T2 sensor’s sealing joints, the joint that connects the capillary tube to the sensor head at the bel lows end, is designated as a Grade A joint (hereinafter “the Grade A joint”). Plaintiffs allege that Woodward failed to properly braze and inspect the Grade A joint. Woodward, like every military supplier, must follow a set of comprehensive quality requirements. Woodward de velops these requirements and certifies compliance with them when delivering parts and requesting payments. The procedure for brazing and inspecting joints is generally gov erned by Woodward’s Shop Procedure 865 (“SP 865”). Woodward can revise provisions of SP 865 without notifying or obtaining consent from GE or the DOD. Further require ments for the Grade A joint are set forth in engineering drawings and process drawings. The parties disagree about the specific requirements for the Grade A joint, including: (1) the appropriate diametrical clearance (i.e., the distance be tween the capillary tube and the sensor head); (2) how “stop off” and “flux” (materials used during the brazing process) 4 No. 15 1866 are removed and detected; and (3) whether the joint’s non visible edge must be inspected by an alternative to visual ex amination, such as by X ray. Whenever Woodward ships parts to GE or the DOD, it must include a “Certificate of Conformance,” in which it confirms that all shipments are “in the Quantities and Quali ty called for, and were in all respects in accord with the ap plicable specifications.” The district court assumed, and the parties do not dispute on appeal, that Woodward certifies that it has followed its quality requirements in manufactur ing each part by including these certificates. Neither GE nor the DOD accepts shipments without a certificate. Prior to their termination in 2005, plaintiffs Marshall and Thurman were long time employees of Woodward. They re ceived all of their training at Woodward. Neither has a col lege or technical degree. Both Marshall and Thurman worked on the T2 sensor at Woodward. They were tasked with brazing various joints on the sensor, but not the Grade A joint. On April 6, 2005, Marshall attended a meeting with T700 engineer Heather Diedrich, senior X ray technician Mark Frutig, and two other engineers. Diedrich noted an increased incidence of leakage in the T2 sensor. Marshall volunteered to investigate the problem and asked Frutig to X ray the Grade A joint. Based on Frutig’s findings and her own in spection, Marshall determined that the diametrical clearance of the joint was too small, that stop off and flux were not removed, that there was insufficient braze in the joint, and that braze from another joint was “masking” the problems with the Grade A joint. Marshall also learned from Frutig that the Grade A joint was not typically inspected by X ray. No. 15 1866 5 She concluded that the joint did not meet Woodward’s quali ty standards and that the part was unsafe. That same day, Marshall relayed her conclusions to her direct supervisor, Mark Meichtry, and Meichtry’s supervisor, Steven Gorman. In a series of emails, Marshall stated that she would not perform her assigned tasks on the T2 sensor until her concerns were properly addressed. Thurman was included on some of these emails. On April 7, Meichtry re sponded with an email to Marshall and Thurman saying, “[l]et’s keep this job moving.” Marshall continued to inspect leaking parts and reiterated her earlier findings. Frutig also sent an email expressing the same concerns as Marshall. On April 11, Marshall placed a hold on the production of T700 parts. Diedrich and senior engineer David Kuchinski investi gated Marshall’s concerns. On April 12, Meichtry informed plaintiffs that “[t]he hold issue has been discussed with the engineers and engineering leaders and the consensus was the parts are good to ship.” Still, Marshall and Thurman re fused to resume work on the sensor. In response, Meichtry sent an email to plaintiffs stating that “(1) it’s going to take too much time and cost too much money to fix these prob lems, (2) GE wants the parts regardless of the problems and (3) it’s the two of you against the world.” In addition, manu facturing engineer Doug Hollenberger commented to plain tiffs that at Woodward, quantity is number one and quality is number two. Marshall persisted. She informed Meichtry that she was going to disclose her concerns to the DOD. On April 13, Meichtry suspended Marshall and sent Thurman home early the next day. 6 No. 15 1866 Later on April 14, Meichtry called Marshall and Thurman into Woodward for a meeting with Diedrich, Gorman, hu man resources manager Carol Smith, and quality director Spitaman Tata. Gorman reiterated that the engineers had concluded that the parts were “okay.” According to plain tiffs, Gorman claimed that the sensors “leak slowly.” Mar shall persisted in her objection. She maintained that another joint masked the problems with the Grade A joint. She asked that Woodward study the problems further. Tata agreed to provide more X rays of the joint but the parties were other wise unable to reach an agreement on how to proceed. At 10:30 that night, Marshall and Thurman returned to Woodward, gathered scrap T2 sensor parts, and cut two of them open. Marshall claims she identified masking in these parts. On April 18, Meichtry and Diedrich provided plaintiffs with sixteen X ray images of the joint. Only two of the imag es were discernable. Although the discernable X rays showed evidence of masking, Diedrich and another engineer concluded that it was not problematic. Plaintiffs continued to refuse to work on the T2 sensor. At that point, Meichtry asked Marshall and Thurman to leave Woodward. The par ties dispute whether they were fired or merely suspended. The next day, Marshall called a Woodward hotline for re porting suspected violations of Woodward’s quality policies. Marshall left a message echoing her belief that there was “a safety issue on the T700 sensor.” She claimed that the sensor “does not meet the SP on the bellow end of the part … .” In response to Marshall’s message, Woodward’s General Coun sel Robert Reuterfors referred the matter to Woodward’s Business Conduct Oversight Committee (“BCOC”). Reuter No. 15 1866 7 fors told plaintiffs that they were on administrative leave with pay pending the BCOC’s investigation. Reuterfors asked senior engineer Ted Erickson to conduct a special review of plaintiffs’ concerns and instructed him that “[y]our overriding instruction … is to prepare a report that is accurate and correct from the standpoint of profes sional engineering analysis. If you agree with the concerns … you should say so and let the chips fall where they may.” Erickson concluded that the Grade A joint was not inferior, the diametrical clearance was proper, using stop off did not affect the joint’s quality, X ray inspection was not necessary, and any masking was not relevant. In a separate investiga tion, Tata agreed with Erickson’s conclusions. Based on these findings, the BCOC determined that plaintiffs’ allegations were not credible and that they had acted unreasonably by refusing to work. The BCOC advised that Woodward would be justified in terminating them. On May 6, 2005, Marshall and Thurman met with Meichtry and Kirk Snyder, the leader of the group that produces the T2 sensor. Plaintiffs remained unwilling to work on the sensor, and Snyder terminated them—for the second time, accord ing to plaintiffs. Meanwhile, on April 26, Marshall and Thurman met with DOD Special Agent Daniel Boucek and expressed their con cerns regarding the T2 sensor. Plaintiffs then met with De fense Contract Management Agency Technical Specialist Harrison DySard. DySard decided to review plaintiffs’ con cerns. Under the pretense of a general audit, DySard investi gated Woodward’s manufacturing process for the T2 sensor. He reviewed Woodward’s operations, engineering drawings, and procedures and met with Woodward engineers. DySard 8 No. 15 1866 also consulted with his counterpart on site at GE, Ed Craft. During DySard’s investigation, Tata falsely stated to DySard that the Grade A joint was regularly inspected by X ray. In an email to Boucek, DySard concluded that there was “nothing either incorrect or wrong with the procedures, as sembly, or testing of the sensors.” He noted that “[t]he spe cific claim that the sensor was supposed to be x rayed but hadn’t was found to be false based on a review of the x ray records for that part.” Similarly, GE conducted its own inves tigation and also concluded that there was no cause for con cern. The government continues to order, pay for, and use Woodward’s T2 sensor. On March 30, 2006, plaintiffs filed a complaint under seal in the Northern District of Illinois. The United States de clined to intervene and the district court unsealed the com plaint. Plaintiffs filed an amended complaint in March 2012. Following discovery, Woodward moved for summary judg ment and on March 27, 2015, the district court granted Woodward’s motion. Marshall and Thurman appeal. II. Discussion We review a district court’s grant of summary judgment de novo, examining the record in the light most favorable to the nonmoving party. U.S. ex rel. Feingold v. AdminaStar Fed., Inc., 324 F.3d 492, 494 (7th Cir. 2003). Summary judgment is appropriate if there is no genuine dispute of material fact and the nonmoving party is entitled to judgment as a matter of law. Id. (citing Fed. R. Civ. P. 56(c)). The district court granted Woodward’s motion for sum mary judgment on plaintiffs’ claim that Woodward violated the FCA by making false statements to the government and No. 15 1866 9 their claim that Woodward violated the FCA and Illinois law by terminating them. Plaintiffs renew both of these argu ments on appeal. A. False Claims To state a claim under the FCA, plaintiffs must show that: (1) the defendant made a statement in order to receive mon ey from the government; (2) the statement was false; (3) the defendant knew that the statement was false; and (4) the false statement was material to the government’s decision to pay or approve the false claim. U.S. ex rel. Yannacopoulos v. Gen. Dynamics, 652 F.3d 818, 822, 828 (7th Cir. 2011). The district court expressly assumed that Woodward made false statements to the government in its Certificates of Conformance. But the court concluded that the false state ments were made without knowledge of their falsehood and were immaterial to the government’s decision to pay. On ap peal, plaintiffs challenge these two conclusions. 1. Knowledge Under the FCA, a defendant must make a “knowingly” false statement. 31 U.S.C. § 3729(a)(1)(B). The FCA defines knowledge to include actual knowledge, deliberate igno rance, or reckless disregard for the truth; knowledge does not require specific intent to defraud. § 3729(b)(1). Accord ingly, knowingly false statements do not include those that are the product of “[i]nnocent mistakes or negligence … .” Yannacopoulos, 652 F.3d at 823 (citation and internal quota tion marks omitted). First, plaintiffs argue that proof of Woodward’s knowledge turns solely on whether Woodward knew its own quality requirements. They claim that it is undisputed 10 No. 15 1866 that Woodward knows its own quality requirements and thus, Woodward had the necessary knowledge for liability under the FCA. However, this analysis overlooks the focus of the knowledge inquiry: whether the false statements were made with the requisite state of mind. Even if Woodward was generally aware of its quality requirements, it lacked “knowledge” if the particular false statements were the re sult of a difference in interpretation or even negligence. Id. Second, plaintiffs contend that Woodward did know that their statements to the government were false. They point to comments from Meichtry, Hollenberger, and Gorman as evi dence that Woodward ignored quality concerns to meet its customers’ demands. Plaintiffs claim that Woodward did not take their concerns seriously and that the internal investiga tions were insincere. But these stray remarks do not amount to knowledge of falsity. They do not demonstrate that any one at Woodward believed that plaintiffs’ concerns were val id. And the evidence shows that Woodward did takes plain tiffs’ concerns seriously. Woodward thoroughly investigated plaintiffs’ allegations on at least two separate occasions. Woodward’s engineers concluded that the parts were fine and that the allegations were unfounded. Plaintiffs have not produced evidence to show that Woodward’s investigations were unreliable. In fact, everyone at Woodward, including the engineers who investigated plaintiffs’ concerns, disagreed with plain tiffs. Meichtry and others in management deferred to Die drich’s investigation. Even Frutig, who initially agreed with Marshall, changed his mind based on the outcome of Die drich’s investigation. Plaintiffs do not point to any evidence that a decision maker at Woodward agreed with their con No. 15 1866 11 cerns at the time Woodward made the statements to the gov ernment. Plaintiffs maintain that Steve Krugler, a Woodward engi neer, knew that the Grade A joint’s inspection procedure vio lated Woodward’s quality requirements. In 1997, Krugler removed the X ray requirement for the Grade A joint. Plain tiffs allege that Krugler did not provide a compliant alterna tive to X ray inspection and that he knew that this omission violated Woodward’s quality requirements. However, Krugler did not testify to that effect. Krugler explained at the time that X ray inspection was unnecessary, and he reiterat ed that belief during litigation. Instead, plaintiffs rely on tes timony by their own experts, Roger Moseley and Jeff Diestelmeier, to suggest that Krugler knew that X ray in spection or another alternative inspection was required. Spe cifically, Moseley testified that “when [Krugler] removed the x ray inspection from this joint, he knew he had to do some thing else and didn’t do it.” Testimony regarding the knowledge of another person based merely upon speculation is insufficient to demonstrate a genuine issue of material fact. See Widmar v. Sun Chem. Corp., 772 F.3d 457, 460 (7th Cir. 2014) (explaining that a plaintiff must rely on more than “speculati[on] as to [a de fendant’s] state of mind, or other intuitions, hunches, or ru mors” to defeat summary judgment). Moreover, Moseley’s testimony relates to knowledge existing roughly fifteen years before the relevant time period. Hence, Moseley’s tes timony is insufficient to show that Krugler had knowledge that Woodward’s certifications were false at the time that they were made. In sum, we agree with the district court that 12 No. 15 1866 no reasonable jury could impute knowledge of falsity to Woodward based on the evidence presented. 2. Materiality Additionally, to prevail under the FCA, plaintiffs must show that the allegedly false statements were material to the government’s decision to pay. The FCA defines material as “having a natural tendency to influence, or be capable of in fluencing, the payment or receipt of money or property.” § 3729(b)(4). We have described this as an objective standard. United States v. Rogan, 517 F.3d 449, 452 (7th Cir. 2008) (“The question is not remotely whether [the defendant] was sure to be caught … but whether the omission could have influ enced the agency’s decision. That’s an objective standard … .”). Plaintiffs make a circular argument that the materiality inquiry should focus on whether Woodward’s certificates were capable of influencing the decision to pay. According to plaintiffs, because the government would not have paid Woodward without a certificate and Woodward would not have knowingly submitted a false certificate, a false state ment on a certificate is necessarily material. We disagree. Following plaintiffs’ logic, any false statement contained in a certificate, no matter how inconsequential, would be materi al. This would nullify the materiality requirement and make even “minor technical violations” material. U.S. ex rel. Lamers v. City of Green Bay, 168 F.3d 1013, 1019 (7th Cir. 1999) (“Such minor technical violations … do not give rise to an FCA claim.”). Furthermore, our case law focuses on whether the false statement itself, rather than the certificate or document con No. 15 1866 13 taining that statement, is capable of influencing the govern ment’s decision. See, e.g., Yannacopoulos, 652 F.3d at 828 (fo cusing on whether defendant’s “failure to check the proper box in the Certification Agreement was a material false statement”); Rogan, 517 F.3d at 452 (assessing whether the “statement or omission” itself is material). Hence, the ap propriate inquiry is whether Woodward’s allegedly false statements—that the Grade A joint meets its quality stand ards—are capable of influencing the government’s decision. With this in mind, we conclude that Woodward’s false statements were immaterial. The government learned of plaintiffs’ concerns, thoroughly investigated them, and de termined that they were meritless. To this day, the govern ment continues to pay for and use the T2 sensor. Therefore, the government’s actual conduct suggests that the allegedly false statements were immaterial. GE also conducted an in vestigation into plaintiffs’ allegations and reached the same conclusion as the government. In addition, Woodward has the right to change its shop procedures at any time without the government’s permission. If specific quality standards are truly material to the government’s decision to buy the sensor, it would be odd to give Woodward a unilateral right to change them. Plaintiffs maintain that because materiality is an objective standard, the government’s actual conduct is irrelevant. However, as the district court correctly found, plaintiffs mis interpret the materiality standard. Our prior case law estab lishes that the government’s conduct is relevant to assessing materiality. See, e.g., Yannacopoulos, 652 F.3d at 831 (consider ing that “the agency failed to take action when it actually learned of the supposed misrepresentation”); U.S. ex rel. Lus 14 No. 15 1866 by v. Rolls Royce Corp., 570 F.3d 849, 855 (7th Cir. 2009) (“If the military services knew what they were getting and de cided to accept blades that [plaintiff] deems ‘inferior’ rather than pay a higher price, then [defendant] will prevail on the merits.”); Luckey v. Baxter Healthcare Corp., 183 F.3d 730, 732– 33 (7th Cir. 1999) (“[Plaintiff] has not offered any evidence tending to show that the omission … was material to the United States’ buying decision; the Department of Justice has conspicuously declined to adopt [plaintiff’s] position or to prosecute this claim on its own behalf. As far as this record reveals, the federal government is 100% satisfied with the blood products … .”). Plaintiffs also challenge the reliability of the govern ment’s investigation. Accordingly, plaintiffs argue that the outcome of DySard’s investigation and the government’s continued decision to pay for and use the sensor should not be dispositive. They point to inadequacies in DySard’s inves tigation, particularly that Tata falsely told DySard that Woodward regularly inspected the Grade A joint by X ray. However, DySard testified in his deposition that he was not misled by Tata’s statement. He stated that he knew that Woodward did not X ray the Grade A joint as part of its reg ular inspection process. DySard also testified that Tata’s false statement did not affect the outcome of his investigation. As a result, plaintiffs’ attack on the government’s investigation is unpersuasive. And even if the government was misled by Tata’s false statement at the time, it has since been made aware of Woodward’s actual practices yet continues to buy and use the sensor. Hence, we agree with the district court that Woodward’s allegedly false statements were not materi al. No. 15 1866 15 B. Retaliation Finally, plaintiffs bring claims for retaliatory discharge under the FCA and Illinois state law. Plaintiffs allege that they were terminated because they raised concerns with the T2 sensor, which they argue is protected conduct under the FCA and Illinois law. The district court held that plaintiffs were terminated for insubordination and not for any pro tected conduct. To pursue a retaliation claim under the FCA, employees must show that they were terminated because of their pro tected conduct. 31 U.S.C. § 3730(h); Halasa v. ITT Educ. Servs., Inc., 690 F.3d 844, 847 (7th Cir. 2012). Similarly, under Illinois law, Marshall and Thurman must demonstrate that they were “(1) discharged; (2) in retaliation for [their] activities; and (3) that the discharge violates a clear mandate of public policy.” Darchak v. City of Chicago Bd. of Educ., 580 F.3d 622, 628 (7th Cir. 2009) (quoting Blount v. Stroud, 904 N.E.2d 1, 9 (Ill. 2009)). Although we have not squarely addressed this issue, the parties agree that under both the FCA and Illinois law plaintiffs must demonstrate “but for” causation. That is, plaintiffs must show that they would not have been termi nated but for their protected conduct. Plaintiffs maintain that they were terminated by Meichtry on April 18, an allegation we must accept on a mo tion for summary judgment. They also point to the fact that Marshall told Meichtry that she would disclose her concerns to the DOD prior to their termination. Accordingly, plaintiffs argue that Meichtry fired them in retaliation for Marshall’s threat to disclose her concerns to the government. 16 No. 15 1866 But even reviewing the record in the light most favorable to plaintiffs, we agree with the district court that any reason able jury would find that plaintiffs were terminated because of their insubordination, not protected activity. First, we agree with the district court that plaintiffs were in fact in subordinate. Plaintiffs contend that they were following their training to protect U.S. military personnel, and thus were not insubordinate. But their training did not authorize them to repeatedly refuse to resume working in the face of direct commands from multiple supervisors and an investi gation dismissing their concerns. Second, we also agree with the district court that plain tiffs’ insubordination was the but for cause of their termina tion. Certainly, Woodward’s management was irritated by plaintiffs’ allegations. But Woodward terminated Marshall and Thurman only after investigating their concerns, inform ing plaintiffs that their concerns were unfounded, and giv ing plaintiffs multiple opportunities to resume their as signed tasks. Instead, plaintiffs engaged in insubordination by repeatedly refusing to work when faced with overwhelm ing evidence contradicting their allegations. The BCOC in vestigation, which determined that Woodward would be jus tified in terminating plaintiffs because of their insubordina tion, further bolsters the conclusion that plaintiffs were fired because of insubordination, not protected activity. Therefore, the district court correctly concluded that no reasonable jury could find that plaintiffs were terminated because of pro tected activity. III. Conclusion For the foregoing reasons, we AFFIRM the judgment of the district court.

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.