Johnson v. Albin Carlson & Co.
Annotate this Case
A contractor hired a subcontractor to work on a remote bridge construction project. The scope of the work changed, and neither party kept detailed records of the changes and associated costs. Years after the project was completed, the subcontractor sued for damages, claiming unpaid work. The superior court found that the subcontract did not govern the extra work, awarded some damages to the subcontractor, and precluded some claims due to discovery violations. The court also found the contractor to be the prevailing party and awarded attorney’s fees. Both parties appealed.
The superior court denied summary judgment motions from both parties, finding factual disputes. It precluded the subcontractor from pursuing certain damages claims due to insufficient documentation but allowed evidence for contingent findings. After a bench trial, the court awarded the subcontractor $191,443.42, later reduced to $146,693.42 upon reconsideration. The court found the contractor to be the prevailing party under Rule 68 and awarded attorney’s fees.
The Supreme Court of Alaska reviewed the case. It concluded that the superior court abused its discretion by precluding the subcontractor’s claims for snowmachine use and labor without considering less severe sanctions. The court affirmed the superior court’s findings on other damages but reversed the awards for Morris Johnson’s labor and boat use, remanding for recalculation. The prevailing party determination and attorney’s fee award were vacated and remanded for reconsideration. The court otherwise affirmed the superior court’s judgment.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.