§8A-6-3. — Enforcement and guarantees.
Code Resources
West Virginia Resources
West Virginia Website
West Virginia Governor
West Virginia Legislature
West Virginia Courts
Search this Code
in Google Scholar
on the Web
Google Web Search
MSN Web Search
Yahoo! Web Search
in the News
Google News Search
Google News Archive Search
Yahoo! News Search
in the Blogs
BlawgSearch.com Search
Google Blog Search
Technorati Blog Search
in other Databases
Google Book Search
§8A-6-3. Enforcement and guarantees.
(a) The planning commission is vested with all the necessary authority to administer and enforce conditions attached to the final plat approved for a development project, including, but not limited to, the authority to:
(1) Order, in writing, the remedy for any noncompliance with the conditions;
(2) Bring legal action to ensure compliance with the conditions, including injunction, abatement, or other appropriate action or proceeding; and
(3) Require a guarantee satisfactory to the planning commission in an amount sufficient for and conditioned upon the construction of any physical improvements required by the conditions, or a contract for the construction of the improvements and the contractor's guarantee, in like amount and so conditioned, which guarantee shall be reduced or released by the planning commission upon the submission of satisfactory evidence that construction of the improvements has been completed in whole or in part.
(b) Failure to meet all conditions attached to the final plat approved for a development project shall constitute cause to deny the issuance of any of the required use, occupancy or improvement location permits, as may be appropriate.
(a) The planning commission is vested with all the necessary authority to administer and enforce conditions attached to the final plat approved for a development project, including, but not limited to, the authority to:
(1) Order, in writing, the remedy for any noncompliance with the conditions;
(2) Bring legal action to ensure compliance with the conditions, including injunction, abatement, or other appropriate action or proceeding; and
(3) Require a guarantee satisfactory to the planning commission in an amount sufficient for and conditioned upon the construction of any physical improvements required by the conditions, or a contract for the construction of the improvements and the contractor's guarantee, in like amount and so conditioned, which guarantee shall be reduced or released by the planning commission upon the submission of satisfactory evidence that construction of the improvements has been completed in whole or in part.
(b) Failure to meet all conditions attached to the final plat approved for a development project shall constitute cause to deny the issuance of any of the required use, occupancy or improvement location permits, as may be appropriate.