Sec. 4309 - Burden of proof on contractor
Download PDF
41 U.S.C. § 4309 (2021) | ||||||
§4309. Burden of proof on contractor | ||||||
In a proceeding before a board of contract appeals, the United States Court of Federal Claims, or any other Federal court in which the reasonableness of indirect costs for which a contractor seeks reimbursement from the Federal Government is in issue, the burden of proof is on the contractor to establish that those costs are reasonable. |
||||||
(Pub. L. 111–350, §3, Jan. 4, 2011, 124 Stat. 3788.) |
||||||
|
||||||
United States Code, 2018 Edition, Supplement 3, Title 41 - PUBLIC CONTRACTS | ||||||
Bills and Statutes | ||||||
United States Code | ||||||
Y 1.2/5: | ||||||
Title 41 - PUBLIC CONTRACTS Subtitle I - Federal Procurement Policy Division C - Procurement CHAPTER 43 - ALLOWABLE COSTS Sec. 4309 - Burden of proof on contractor |
||||||
section 4309 | ||||||
2021 | ||||||
January 3, 2022 | ||||||
Yes | ||||||
standard | ||||||
102 Stat. 4634 108 Stat. 3313 124 Stat. 3788 |
||||||
Public Law 100-700, Public Law 103-355, Public Law 111-350 |
Disclaimer: These codes may not be the most recent version. United States may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.