2015 US Code
Title 2 - The Congress (Sections 1 - 6654)
Chapter 30 - Operation and Maintenance of Capitol Complex (Sections 2001 - 2186)
Subchapter VII - Other Entities and Services (Sections 2161 - 2172)
Sec. 2162a - Promoting maximum efficiency in operation of Capitol Power Plant

View Metadata
Metadata
Publication TitleUnited States Code, 2012 Edition, Supplement 3, Title 2 - THE CONGRESS
CategoryBills and Statutes
CollectionUnited States Code
SuDoc Class NumberY 1.2/5:
Contained WithinTitle 2 - THE CONGRESS
CHAPTER 30 - OPERATION AND MAINTENANCE OF CAPITOL COMPLEX
SUBCHAPTER VII - OTHER ENTITIES AND SERVICES
Sec. 2162a - Promoting maximum efficiency in operation of Capitol Power Plant
Containssection 2162a
Date2015
Laws In Effect As Of DateJanuary 3, 2016
Positive LawNo
Dispositionstandard
Source CreditPub. L. 110-140, title V, §504, Dec. 19, 2007, 121 Stat. 1656.
Statutes at Large Reference121 Stat. 1656
Public and Private LawPublic Law 110-140

Download PDF


2 U.S.C. § 2162a (2015)
§2162a. Promoting maximum efficiency in operation of Capitol Power Plant(a) Steam boilers(1) In general

The Architect of the Capitol shall take such steps as may be necessary to operate the steam boilers at the Capitol Power Plant in the most energy efficient manner possible to minimize carbon emissions and operating costs, including adjusting steam pressures and adjusting the operation of the boilers to take into account variations in demand, including seasonality, for the use of the system.

(2) Effective date

The Architect shall implement the steps required under paragraph (1) not later than 30 days after December 19, 2007.

(b) Chiller plant(1) In general

The Architect of the Capitol shall take such steps as may be necessary to operate the chiller plant at the Capitol Power Plant in the most energy efficient manner possible to minimize carbon emissions and operating costs, including adjusting water temperatures and adjusting the operation of the chillers to take into account variations in demand, including seasonality, for the use of the system.

(2) Effective date

The Architect shall implement the steps required under paragraph (1) not later than 30 days after December 19, 2007.

(c) Meters

Not later than 90 days after December 19, 2007, the Architect of the Capitol shall evaluate the accuracy of the meters in use at the Capitol Power Plant and correct them as necessary.

(d) Report on implementation

Not later than 180 days after December 19, 2007, the Architect of the Capitol shall complete the implementation of the requirements of this section and submit a report describing the actions taken and the energy efficiencies achieved to the Committee on Transportation and Infrastructure of the House of Representatives, the Committee on Commerce, Science, and Transportation of the Senate, the Committee on House Administration of the House of Representatives, and the Committee on Rules and Administration of the Senate.

(Pub. L. 110–140, title V, §504, Dec. 19, 2007, 121 Stat. 1656.)

EFFECTIVE DATE

Section effective on the date that is 1 day after Dec. 19, 2007, see section 1601 of Pub. L. 110–140, set out as a note under section 1824 of this title.

Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.