2015 US Code
Title 10 - Armed Forces (Sections 101 - 18506)
Subtitle A - General Military Law (Sections 101 - 2926)
Part I - Organization and General Military Powers (Sections 101 - 498)
Chapter 9 - Defense Budget Matters (Sections 221 - 239)
Sec. 223a - Ballistic missile defense programs: procurement

View Metadata
Metadata
Publication TitleUnited States Code, 2012 Edition, Supplement 3, Title 10 - ARMED FORCES
CategoryBills and Statutes
CollectionUnited States Code
SuDoc Class NumberY 1.2/5:
Contained WithinTitle 10 - ARMED FORCES
Subtitle A - General Military Law
PART I - ORGANIZATION AND GENERAL MILITARY POWERS
CHAPTER 9 - DEFENSE BUDGET MATTERS
Sec. 223a - Ballistic missile defense programs: procurement
Containssection 223a
Date2015
Laws In Effect As Of DateJanuary 3, 2016
Positive LawYes
Dispositionstandard
Source CreditAdded Pub. L. 108-136, div. A, title II, §223(a)(1), Nov. 24, 2003, 117 Stat. 1420; amended Pub. L. 113-291, div. A, title X, §1060(a)(1), Dec. 19, 2014, 128 Stat. 3502.
Statutes at Large References117 Stat. 1420
128 Stat. 3502
Public and Private LawsPublic Law 108-136, Public Law 113-291

Download PDF


10 U.S.C. § 223a (2015)
§223a. Ballistic missile defense programs: procurement

(a) Budget Justification Materials.—In the budget justification materials submitted to Congress in support of the Department of Defense budget for any fiscal year (as submitted with the budget of the President under section 1105(a) of title 31), the Secretary of Defense shall specify, for each ballistic missile defense system element for which the Missile Defense Agency is engaged in planning for production and initial fielding, the following information:

(1) The production rate capabilities of the production facilities planned to be used for production of that element.

(2) The potential date of availability of that element for initial fielding.

(3) The estimated date on which the administration of the acquisition of that element is to be transferred from the Director of the Missile Defense Agency to the Secretary of a military department.


(b) Future-Years Defense Program.—The Secretary of Defense shall include in the future-years defense program submitted to Congress each year under section 221 of this title an estimate of the amount necessary for procurement for each ballistic missile defense system element, together with a discussion of the underlying factors and reasoning justifying the estimate.

(c) Performance Criteria.—The Director of the Missile Defense Agency shall include in the performance criteria prescribed for planned development phases of the ballistic missile defense system and its elements a description of the intended effectiveness of each such phase against foreign adversary capabilities.

(Added Pub. L. 108–136, div. A, title II, §223(a)(1), Nov. 24, 2003, 117 Stat. 1420; amended Pub. L. 113–291, div. A, title X, §1060(a)(1), Dec. 19, 2014, 128 Stat. 3502.)

AMENDMENTS

2014—Subsec. (d). Pub. L. 113–291 struck out subsec. (d). Text read as follows: "The Director of Operational Test and Evaluation shall make available for review by the congressional defense committees the developmental and operational test plans established to assess the effectiveness of the ballistic missile defense system and its elements with respect to the performance criteria described in subsection (c)."

IMPLEMENTATION OF REQUIREMENT FOR AVAILABILITY OF TEST PLANS

Pub. L. 108–136, div. A, title II, §223(b), Nov. 24, 2003, 117 Stat. 1420, directed that subsec. (d) of this section was to be implemented not later than Mar. 1, 2004.

Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.