2011 US Code
Title 41 - Public Contracts
Subtitle I - Federal Procurement Policy (§§ 101 - 4711)
Division B - Office of Federal Procurement Policy (§§ 1101 - 2313)
Chapter 15 - COST ACCOUNTING STANDARDS (§§ 1501 - 1506)
Section 1503 - Contract price adjustment

View Metadata
Metadata
Publication TitleUnited States Code, 2006 Edition, Supplement 5, Title 41 - PUBLIC CONTRACTS
CategoryBills and Statutes
CollectionUnited States Code
SuDoc Class NumberY 1.2/5:
Contained WithinTitle 41 - PUBLIC CONTRACTS
Subtitle I - Federal Procurement Policy
Division B - Office of Federal Procurement Policy
CHAPTER 15 - COST ACCOUNTING STANDARDS
Sec. 1503 - Contract price adjustment
Containssection 1503
Date2011
Laws in Effect as of DateJanuary 3, 2012
Positive LawYes
Dispositionstandard
Source CreditPub. L. 111-350, §3, Jan. 4, 2011, 124 Stat. 3699.
Statutes at Large References102 Stat. 4062
124 Stat. 3699
Public Law ReferencesPublic Law 93-400, Public Law 100-679, Public Law 111-350

Download PDF
41 USC § 1503 (2011)
§1503. Contract price adjustment

(a) Disagreement Constitutes a Dispute.—If the Federal Government and a contractor or subcontractor fail to agree on a contract price adjustment, including whether the contractor or subcontractor has complied with the applicable cost accounting standards, the disagreement will constitute a dispute under chapter 71 of this title.

(b) Amount of Adjustment.—A contract price adjustment undertaken under section 1502(f)(2) of this title shall be made, where applicable, on relevant contracts between the Federal Government and the contractor that are subject to the cost accounting standards so as to protect the Federal Government from payment, in the aggregate, of increased costs, as defined by the Cost Accounting Standards Board. The Federal Government may not recover costs greater than the aggregate increased cost to the Federal Government, as defined by the Board, on the relevant contracts subject to the price adjustment unless the contractor made a change in its cost accounting practices of which it was aware or should have been aware at the time of the price negotiation and which it failed to disclose to the Federal Government.

(c) Interest.—The interest rate applicable to a contract price adjustment is the annual rate of interest established under section 6621 of the Internal Revenue Code of 1986 (26 U.S.C. 6621) for the period. Interest accrues from the time payments of the increased costs were made to the contractor or subcontractor to the time the Federal Government receives full compensation for the price adjustment.

(Pub. L. 111–350, §3, Jan. 4, 2011, 124 Stat. 3699.)

Historical and Revision Notes
Revised

Section

Source (U.S. Code)Source (Statutes at Large)
1503(a) 41:422(h)(2). Pub. L. 93–400, §26(h)(2)–(4), as added Pub. L. 100–679, §5(a), Nov. 17, 1988, 102 Stat. 4062.
1503(b) 41:422(h)(3).
1503(c) 41:422(h)(4).

Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.