Section 1816 - Construction contracts

View Metadata
Metadata
Publication TitleUnited States Code, 2006 Edition, Supplement 5, Title 2 - THE CONGRESS
CategoryBills and Statutes
CollectionUnited States Code
SuDoc Class NumberY 1.2/5:
Contained WithinTitle 2 - THE CONGRESS
CHAPTER 28 - ARCHITECT OF THE CAPITOL
SUBCHAPTER II - GENERAL POWERS AND DUTIES
Sec. 1816 - Construction contracts
Containssection 1816
Date2011
Laws in Effect as of DateJanuary 3, 2012
Positive LawNo
Dispositionstandard
Source CreditPub. L. 107-68, title I, §130, Nov. 12, 2001, 115 Stat. 580.
Statutes at Large References115 Stat. 580
116 Stat. 1062
Public Law ReferencesPublic Law 107-68, Public Law 107-217

Download PDF
2 USC § 1816 (2011)
§1816. Construction contracts (a) Liquidated damages

The Architect of the Capitol may not enter into or administer any construction contract with a value greater than $50,000 unless the contract includes a provision requiring the payment of liquidated damages in the amount determined under subsection (b) of this section in the event that completion of the project is delayed because of the contractor.

(b) Amount of payment

The amount of payment required under a liquidated damages provision described in subsection (a) of this section shall be equal to the product of—

(1) the daily liquidated damage payment rate; and

(2) the number of days by which the completion of the project is delayed.

(c) Daily liquidated damage payment rate (1) In general

In subsection (b) of this section, the “daily liquidated damage payment rate” means—

(A) $140, in the case of a contract with a value greater than $50,000 and less than $100,000;

(B) $200, in the case of a contract with a value equal to or greater than $100,000 and equal to or less than $500,000; and

(C) the sum of $200 plus $50 for each $100,000 increment by which the value of the contract exceeds $500,000, in the case of a contract with a value greater than $500,000.

(2) Adjustment in rate permitted

Notwithstanding paragraph (1), the daily liquidated damage payment rate may be adjusted by the contracting officer involved to a rate greater or lesser than the rate described in such paragraph if the contracting officer makes a written determination that the rate described does not accurately reflect the anticipated damages which will be suffered by the United States as a result of the delay in the completion of the contract.

(d) Effective date

This section shall apply with respect to contracts entered into during fiscal year 2002 or any succeeding fiscal year.

(Pub. L. 107–68, title I, §130, Nov. 12, 2001, 115 Stat. 580.)

Codification

Section was classified to section 166j of former Title 40, prior to the enactment of Title 40, Public Buildings, Property, and Works, by Pub. L. 107–217, §1, Aug. 21, 2002, 116 Stat. 1062.

Disclaimer: These codes may not be the most recent version. The United States Government Printing Office may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the US site. Please check official sources.