2010 South Dakota Code
Title 5 - PUBLIC PROPERTY, PURCHASES AND CONTRACTS
Chapter 18B - Procurement of Public Improvements
Section 5-18B-5 - Negotiations if lowest responsive and responsible bid exceeds final estimated project cost.

5-18B-5. Negotiations if lowest responsive and responsible bid exceeds final estimated project cost. If the lowest responsive and responsible bid for a public improvement project exceeds the final estimated project cost, the Bureau of Administration, acting on behalf of the state, or any other purchasing agency may negotiate with that low bidder for the construction of a public improvement at the most advantageous price.

Source: SL 2010, ch 31, § 44.

Disclaimer: These codes may not be the most recent version. South Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.